Years ago, people battled to get in contact with each other. If a group of people gained knowledge on a certain topic, they could only share it with those they were in contact with. As technology started improving, the world started changing. The globe started communicating and contacting each other very regularly. Most people are now global citizens, and boarding a plane to another country or continent is second nature. This new trend that opens the world to us also comes with its threats to society. Like internet viruses that started poking its head out when the internet was discovered, a very real risk of international diseases spread by contact and interaction between people has started to emerge.
This article will help you design a business that needs to be virus-proof for the future. In particular, a Corona-proof business.
International Currency Revenue, Local Currency Cost
The first step to any business is understanding your revenue streams and their origins. When doing business in an emerging market, it’s very important to focus on the currency that most of your income is earned. When international disasters happen, emerging currencies and markets tend to fall as investors search for more conservative investments. If the majority of your income is, for instance, in United States Dollars or Euros, you will make more money when the local currency weakens. Your costs for at least your labour and rent components will be in local currency; thus, you will receive more local currency for your dollars or euros.
Designing Your Business to Fight Corona: Employing Millennials
In times of crisis, things need to change quickly, and in a matter of days, the way you have been doing business for years does not apply anymore. Millennials are brilliant at adapting to change. They also fully understand technology; some prefer to work from home and have been doing so for a while. In previous articles on millennials, I tried to get the older generation to understand millennials and allow them to be themselves within your current organization. If companies adapted to the millennial way of doing things early, they would probably have less difficulty coping with the Corona lockdown.
Virtual Office Environment
In times of crisis, as we are experiencing currently, the virtual office has become very important. Previously, the arguments for virtual offices were to save on fuel and rent or to miss the traffic. Many people started exploring the virtual office setup, but in certain organizations, they could not get past the fact that they did not know what each person did every second of the day. Currently, the virtual office setup is not nice, but it is the only way you can continue working during the lockdown. Companies should start to embrace this as it will become the way of the future and protect your company against future disasters.
Designing Your Business to Fight Corona: Culture
A strong culture is probably the most important factor any company should strive to have. Once you have a culture where people take accountability for their responsibilities, you have a winning recipe, and people can be anywhere in the world working towards a common goal. Culture starts right at the top of an organization. It will probably never happen if the company’s management does not trust their employees and systems to perform under difficult circumstances. Focus on always building your culture, which will come in handy in difficult situations.
Global focus
Any company must strive towards multiple locations. The easiest would be to have one office in a location where you feel safe and secure and focus on servicing your clients very well. Although this has worked for many people, it’s not a fail-proof strategy, as things always change. You might find that one of your major clients has financial trouble or that several competing companies have opened up in this area, or, like the disaster we currently have, they have a lockdown in a certain location. If one of your locations does not function at a certain time, your other locations would be able to carry the burden and help your company survive in difficult times.
Designing Your Business to Fight Corona: Diversification on Income Streams
A very similar statement to the locations discussed above would be the diversification of scope. Most construction sites will be closed due to the coronavirus lockdown. If you only had a construction business, all your income would have stopped, but your overhead costs would continue. For instance, if your company had a consulting or procurement arm, that portion of your business could continue and generate money while you weather the storm.
Opportunities
In the most difficult times, new opportunities open up to expand and change your business. A good example would be that during and after this Corona disaster, many companies strived to digitize their business for the future. This would create a great opportunity to specialise in their services. Other companies might start designing and building respirators or hospital beds out of necessity, but this could lead to a whole new line of business and generate an additional revenue stream.
Designing Your Business to Fight Corona: Working as a Team
Understanding the implications of not having all your employees in the same location is very important. It’s very easy to have everyone working from home doing their own thing, but getting them to operate in a team from remote locations takes some management and the correct setup. Regular communication through video conferencing and software designed to have people work together in teams helps a lot. Breaking larger teams into smaller teams, also called scrums, could be a good way to ensure the work gets done with the needed support without crowding the virtual work environment. Teamwork will always be part of any business and needs to get a lot of attention. It’s also very closely related to culture and trust.
Focus on What You Can Do
In many instances, employees and managers of companies would get very frustrated because they cannot do the daily tasks they were planning to do. They would focus on this and never get past this obstacle in the road. Focusing on what you can do can solve problems you might not have time to do during your normal routine. Identify the areas of your business that can continue to operate and execute those areas very well. It might be that once you are up and running at full steam again, your focused efforts in a certain area improve your business as a whole.
Designing Your Business to Fight Corona: Come Out Stronger Than You Went In
While companies are forced to close their doors and only certain service offerings will continue to operate in a state of disaster, nothing stops companies from improving their internal systems and processes. Research and development, as well as tendering, for instance, are areas that can continue and will have a real impact on the future of your business if done correctly. Many companies badly require a reset and improvement of internal efficiencies. This would be a perfect opportunity to do this and come back stronger and ready for the action.
Customer Relationships
A business is only as strong as the customers it serves. Customers should always be a very important part of your business, but in times of distress, it’s arguably more important than ever. Communicating with customers during this time will help sustainability after the crisis. You might even gain a few customers from this process who feel their service providers did not handle the lockdown well. As sites and workshops close down, ensure you do everything you can to help your customers as far as possible and remember they are also in very difficult situations. This will build trust, loyalty, and a strong relationship in the future.
Designing Your Business to Fight Corona: Change Management
Several companies will have contracts with both customers and sub-suppliers or contractors. During these once-in-a-lifetime events, most contracts will have a force majeure clause that should be used if applicable. This protects the service provider as well as the clients. It should be done swiftly and following the contract. Communication between the different parties will greatly affect smoothing this process out.
Disaster Fund
Even after implementing all the topics discussed above, we should be realistic about the situation. The chances that a total lockdown will cost your company money are very real. You will have a lot of costs without a lot of income. From a cash flow point of view, you might only feel the pain a month or two after the lockdown. As for any unknown circumstance outside your control, you have to have insurance. Although insurance policies might cover certain events, the chance of getting a global disaster covered would probably be less likely. The best way to ensure your company survives something like this would be to have an amount of money available to access when needed. So, the next time you plan large dividends or splash money on items that are not necessary, remember rather to save it for a rainy day.
Designing Your Business to Fight Corona: Employees
Last but certainly not least, your employees are your company’s most important asset. Helping them and ensuring they feel safe in such a situation is paramount. Times like this will grow lifelong loyalty towards a company, knowing you have their back when times get tough. You will have certain areas of your business where temporary staff will have to be managed and placed in a short time, make sure your HR department handles this correctly and following the law. In times of crisis, the governments usually have several funds employees can apply for to help them through the difficult times. Ensure you communicate it well and help them with the process if possible. It will also be on every employee to help the company during times like this. Every employee should realize that the machine can only work if all the parts of the machine work together.
By introducing the topics discussed above in your business, you should be able to weather any storm. Remember that you should prepare for disasters in business and have a plan before they occur. If you only start this process once the disaster happens, implementing it will be much more difficult.
Why is Performance Management for Millennials a ‘thing’ in organisations? The textbook and international codes of good practice tell us that a responsible company has a way of assessing and rewarding the contributions of its people. Driven by an obsession with order and predictability, we see that when a business grows beyond a certain size, and the founder-owner realizes that she can no longer control everything, policies (such as performance management) are introduced to simplify matters, manage risk and standardize responses. And, of course, a multi-billion dollar accreditation and consulting industry has grown to assist businesses to get this right.
However, many employees will tell you that performance management is a dreaded part of their work life that adds little value. Only 14% of employees strongly agree that their performance reviews inspire them to improve, and only one in two know what is expected of them when they go to work every day!
“Traditional performance management systems are broken. Companies, leaders, managers and employees have long participated in time-consuming, frustrating performance reviews that have not yielded clear improvements in individual and organizational performance. Many industry leaders, such as Accenture, Adobe, Cargill, General Electric, Google, Microsoft and Netflix, have made headlines for pioneering large-scale changes to their traditional performance evaluation systems, and many more are considering reinventing their approach to performance management.” – Gallup, 2017
Most employees and managers get no sleep the night before the performance appraisal meeting, which has become a once—or twice-a-year paper exercise to generate inputs for salary reviews and HR development plans. Between appraisal sessions, not much happens. The session is often a subjective, one-sided affair in which the manager does all the talking, wanting to get one more irritating administrative formality out of the way as quickly as possible.
In this article, we will examine the assumptions that led to this ‘thing’, explain why it went wrong, and suggest what can be done to correct it if necessary.
The management philosophy that still dominates organisational thinking today, with its roots in the early 20th century, is attributed to Frederick Winslow Taylor – often called the Father of Management Science. It created a model of the organisation as a big machine that can be made more efficient if we organise the component parts properly. It stems from the industrial age, during which most workers’ jobs could be described as repetitive tasks such as assembling a gearbox or sowing a garment.
You do not have to think too deeply to realise that today’s jobs and organisations are not like that and will never be again. Work content changes too fast; challenges are unpredictable, customers are more demanding, and projects come and go. New jobs that did not exist yesterday are invented continuously. A young engineer in a consulting practice is called upon to design a pump station today and a pipe support system tomorrow, produce design reports and respond to technical queries in between. How do you possibly standardize this job content?
The ‘Management by Objectives’ or ‘Management by Results’ movement (attributed to management guru Peter Drucker) is a philosophy that greatly appealed to the managers of the time and is still popular today. It helps managers define objectives, reduce work to discrete steps, and provide the tools to measure and compare every employee’s performance with the standards set. If we could all agree to a set of objectives and organise our work accordingly, the organization would do just fine. We see this thinking clearly when managers compile their strategy documents. They contain 12-month, 3-year and 5-year objectives, goals and action plans. These plans are then cascaded down in decreasing complexity until everyone can see his or her part in the scheme. A manager oversees the execution of work within the framework of the strategy and operational plans.
The difficulty is that projects often develop in dramatic and unpredictable ways, new shareholders and management shift the business model, customers change their minds, new opportunities emerge unannounced, markets don’t develop as we assumed they might, the exchange rate turns against you, competitors make unexpected moves, and things go wrong in spectacular fashion. And so, your strategy assumptions, objectives and goals can be rendered invalid and irrelevant overnight.
The conventional performance model compels us to measure people, identify shortcomings and implement remedial actions. The performance appraisal event helps us to do this – the manager discusses the last three months’ outputs with the employee, provides a score in each of the performance dimensions, identifies areas that must be improved and draws up a list of actions (such as training courses), that will address the person’s development needs. It is hard to fault the logic – pinpoint where the athlete’s technique is weak, work on improving it, and everything will improve.
The world of work moves fast, though. If the performance review takes a historic view, it could miss important opportunities for improvement and changes in direction. Also, focusing on what went poorly or not so well, and on what that says about a person’s competencies, seems out of sorts with wanting to propel the organization forward, and keeps us stuck in reverse.
Some organisations employ a 360-degree assessment approach to achieve a balanced view of people’s contributions and lend more credibility to performance appraisals. Peers, supervisors, direct reports, customers, and suppliers are asked to contribute to an individual’s appraisal. This has merit—the mature worker will invite and welcome opinions from multiple sources to learn and grow.
Our criticism of this practice is that it takes a historical view and perhaps a context-less view at that (since we want to get customers’ and suppliers’ feedback, how can they know the context and critically appraise the person?). Mostly, the feedback is anonymous, which robs you of the opportunity to discover why a peer scored you only 5 out of 10 for communication skills against the 360 average of 8.5.
Interestingly, some of the world’s largest corporations (Adobe, General Electric, and Microsoft, to list a few) have decided to significantly re-engineer their performance management systems, if not abandon them. Their stories make for interesting reading.
Perhaps the most important realisation that contemporary management philosophers and leaders have come to is that the modern organization is a more complex organism (yes, it is living and breathing!) than we ever understood. While it may have a visible structure with job profiles and carefully crafted policies and processes, an evolving system of dynamic and informal networks of people, complicated interactions, and inter-dependencies often underpin, override and confuse the formalities. In such a multi-faceted, intricately connected context, it is a flawed logic that one could solve the whole simply by fixing the parts.
The human contribution to organisational performance does not happen in isolation. People are affected and influenced by how others behave, the space afforded to operate, the constraints of policies, and extraneous factors over which we do not have control; the customer cancelled the order, the supplier went out of business, the exchange rate tanked, the star performer in our team resigned, and so on. We indeed expect employees to own their patch, seek a way out despite the obstacles, find a new solution, and not be put off by the supervisor’s bad attitude and all that. However, performance appraisal systems mostly fail to consider these complexities, leaving the appraised worker disappointed and subjectively unappreciated. The situation worsens when the supervising manager is pressured about her unit’s underperformance and seeks to fix the blame. It must be someone’s fault, right?
Our performance-obsessed world wants to reduce everything to a metric we can evaluate, compare and pass judgment on. Engineers easily fall into this trap: we are taught that you can only manage what you can measure, right? It is a fatal flaw of many performance management systems that they produce a number by which people are ranked, such as “you are in the bottom 10% of performers” or “your overall performance score is 6.34 out of 10” – to more than one decimal if you want! How can I reduce the multi-dimensional world of work and the dynamic context of my job to a number connected to a scale of salary adjustments? Who determines what constitutes a 10 anyway? And why is 6.34 not good enough?
Jack Welch, a 20-year chairman and CEO of GE, made stack ranking a widespread people management policy. During this time, several other companies followed suit and applied similar systems within their organizations. However, 30 years into its inception, GE admits that the old system is not functioning very well anymore. With the move, GE is dumping annual performance reviews and performance management systems over the next couple of years. It will implement more frequent feedback via an app, and an experimental group will pilot feedback without any numerical rankings. https://www.impraise.com/blog/how-ge-renews-performance-management-from-stack-ranking-to-continuous-feedback
To remain competitive, the modern organization has to move quicker and be far more agile than its counterpart of the early 20th century. Technology is moving at breakneck speed, your competitors are plotting new ways to eat your lunch, and your customers are changing their models to stay in business. If a performance management system has two annual appraisal events, and in each, the view is the previous six months, you are probably too late to fix anything, let alone help your employees adapt and grow.
Gallup says appraisal subjectivity is often a source of disenchantment and demotivation. Who says the manager knows better? If not properly communicated, made transparent, and discussed, assessments can be perceived as inaccurate and unfair, producing the one outcome you were not hoping for—disengaged and uninterested employees.
The Gallup Organisation reported from an international research study that the level of global engagement in the workplace is only at 15%. This means that fewer than one in six employees feel the degree of emotional and intellectual alignment and attachment that we are hoping for. If we want to be cynical, the other 5 out of six people are neutral at best, if not apathetic, and perhaps even destructive. Of course, it is wrong to generalize, and this statistic may not be true for your business. But think about this – how many salary dollars are you paying for the benefit of having only one-third or half of your people truly engaged and actively pushing to achieve your goals? If Gallup is only half right, the greater part of your salary bill is like a tax for having a few good people fighting on your side.
Millennials and the generations following them do not have a mindset that tolerates or appreciates what conventional performance management is doing or trying to achieve – for many reasons discussed above. They value meaningful work content and a rich purpose, they want flexibility and an opportunity to learn, they are looking for a coach and not a boss, loyalty is not a big thing, and you had better get your act together or they will up and leave. They engage on their terms, not yours.
What does this have to do with performance management? Everything, we think. The realities of what the modern organization has become, the dynamic world of business and its people, and the challenges we face to stay in business and grow all say that we must engage with our people in completely different and more meaningful ways.
Leadership and performance cannot be separated. They are joined at the hip, so to speak. Leaders are expected to produce results whether the leader runs a not-for-profit community outreach project, a multi-national pharmaceutical company, a sports team, or a municipal finance department. The coach will be pointed to the door when the team does not perform.
A consistent record of sound results best indicates leadership potential and capacity. Top-rated leaders have a history of repeated high-impact results across various contexts and complexities. Helping people achieve the best results possible is a primary challenge for every leader and lies at the heart of effective performance contracting, reviews, correction and reward.
Is business failure the result of leadership failure? Some influences determine business performance and over which business leaders have little control – political instability and economic melt-down or ecological disaster. Short of such extreme events, even subtle shifts in competition or regulatory frameworks can seriously affect sales results and profitability unexpectedly and unpredictably. So, the answer is no – business non-performance is not uniquely caused by leader incompetence or failure. However, with any leadership role comes responsibility and a need to take ownership. Leaders create the structures that drive human behaviour and business performance; how we manage performance is an example of just such a structure. So, leadership is, in many ways, the catalyst for performance because of how leaders set up the systems and structures through which they guide and direct the human effort.
Performance management should aim to continuously develop people’s competencies. It should yield alignment and enrollment so that people are enabled, empowered, and encouraged to be their best. Reframe the link to remuneration and reward. Good results should be recognised and rewarded, but guess what: Predispositions and attitudes are invited if the annual appraisal happens in the week before salary increments are handed down!
Perhaps your performance programme should be called “Performance Development”, and you should drop the term “management”, which is the wrong connotation. Performance management should not be a thing that leaders do to their people. It should be a collaboration process to create new insights, build learning opportunities and forge agreements about how to improve.
Performance management is not an annual event. It should happen all the time. Everything you do as a leader is about understanding and accepting what needs to be done and how you can support people to deliver great results. Every opportunity to connect with your people is to ask: “How is it going with the ACME project?” and “How can I help you succeed?” But you also need more formal sessions to review, reflect and recalibrate.
If your people will own their performance, they have to own the plan. People’s ownership and motivation go up when they participate in decisions that affect their jobs, careers and ability to perform, and they can collaborate in goal setting. Ensure your people see how the next period’s work fits into the strategy and how their contribution will promote the cause. If I do not see the connection between what I do and the purpose, I will lose interest – what am I doing here?
You don’t always know better; the further you are removed from the customer, the less you will. You will likely get lost in the details if you manage a multi-disciplinary team. Your role in performance management is more about coaching, consulting and collaboration than telling. Of course, you will have firm views about direction, purpose, and objectives and must display resolve for the desired results. In between, performance management events are about discovery, reflection, learning, and planning.
What we have stressed in this article about performance management does not negate your responsibility to deal with underperformance and incompetence. Your organisation has policies about disciplining and sanctioning destructive and dysfunctional behaviour; labour legislation provides the tools to handle that. When do you want to discover that your most promising new recruit turned out to be a problem – early on or late in the second half? It is better to support a person’s development at the start than to punish her at the end of the year.
Each person is responsible for managing their own motivation and performance. Effective performance management is a partnership between the leader and her team members. You will be in a far better position to influence outcomes if you correctly position and contract about the rules of engagement from the start.
Performance management should not be the paper war and administrative slog that so many organisations have made it. It presents a magical opportunity to bring out the best in people as your contract for challenging objectives that will deliver meaningful results.
Leaders deliver results – period! And they deliver them consistently – period! Irrespective of title and rank, age or service, those individuals who deliver good results through the efforts of others are the people who are leading. Anything else is just make-believe.
The Clifton StrengthsFinder model of human performance makes a profound statement about people and their work roles. Gallup’s research has shown that innate human talents can be reliably modelled across 34 themes that naturally fall into four domains – Executing, Influencing, Relationship Building and Strategic Thinking. We are all differently wired; my top 5 talent themes are different from yours, and my strong domain is not necessarily yours. At the core of the findings is a tenet that rings true for all of us when we think about it – the magic that happens when you experience a high, a feeling of upliftment, a sense of fulfilment, is when your most prominent talents are gainfully applied. Developing talents into strengths must be a better investment than spending time in training workshops to improve my weaknesses.
In an ideal world, we would all be ecstatic if our talents could be matched perfectly to the job requirements. This is not possible, and there are aspects of every job that we avoid or postpone simply because we don’t enjoy them. A deeper understanding of one’s strengths profile will help find a better talent-job match, combine and coordinate our strengths, and collaborate with others to tackle the various challenges that fill our workday. Your performance management system will benefit from this perspective – instead of focusing on your people’s development needs (their weaknesses), why not spend time discovering their talents and figuring out how to build these?
Marcus Buckingham, a well-published advocate of the Clifton StrengthsFinder approach, offers a really simple solution for the performance management conundrum – the weekly check-in. It means the manager deliberately makes time for a weekly discussion with each person, framed by this one question: “So what are your priorities for the next week? How can I help?” Just that. It focuses on near-term work and the challenges it brings. It creates an opportunity for meaningful engagement and compels the leader to think like a coach, not a manager. This is what managers should be doing. Yes, there are budget meetings and reports to write, and you have to do the admin, visit the customer and negotiate with a strategic supplier, but in between, your job is primarily to guide, assist and coach. Can you think of more important work to be done?
Yes, performance management as it was conceived is broken and in disrepair. But it isn’t dead – it needs a new way of thinking and mindset because the world and your people are moving on. Your organisation’s growth and performance depend on your people’s growth, engagement and meaningful contribution.
About EPCM Culture
The authors recognise the work of Mr Ian Dean, an independent consultant and a leadership scholar. He works internationally to help organizations improve the performance of their leaders and businesses.
Gallup, Washington DC, 2017 – “Re-Engineering Performance Management”
https://www.impraise.com/blog/how-ge-renews-performance-management-from-stack-ranking-to-continuous-feedback
Impraise.com, White Paper: “Why Deloitte, Adobe, and Others Replaced the Annual Performance Review”
Doerr, J: “Measure what Matters – How Google, Bono, and the Gates Foundation Rock the World with OKRs”, Ninjareads, Henrae LLC, 2019
Drucker, Peter F: “The Practice of Management”, Harper Collins, New York, 1954
Buckingham, M and Clifton, DO: “Now, Discover Your Strengths”, The Free Press, New York, 2001
Rath, T: “StrengthsFinder 2.0”, Gallup Press, New York, 2007
https://www.gallup.com/cliftonstrengths/en/home.aspx “Transform Great Potential Into Greater Performance”
Deep changes are occurring in natural gas markets – China is entering the global gas scene, driven by continuous economic growth and strong policy support to curb air pollution; the United States is emerging as a global LNG player (see our article on the shale gas revolution at https://epcmholdings.com/the-united-states-shale-revolution/), and the industrial sector is set to take over from power as the key driver for natural gas demand. In terms of growth, the African gas sector is no different and is looking to continue to boom in the 2020s as the region grows economically and investment increases.
Governments in West African countries are increasing their efforts to secure a stable gas supply to enhance power generation capacity and rely less on revenue generated by crude oil. Power is a key determinant and precursor to economic growth, particularly in 3rd world countries.
Other African governments are looking to set up their delivery of gas infrastructure, including pipelines, floating liquefied natural gas (FLNG) platforms and major gas field projects.
African gas discoveries are stimulating sector growth and infrastructure development in Mozambique, Kenya, and Tanzania on the east coast, while the emergence of shale gas and the strategic environmental assessment commissioned by the South African government are leading exploration on the continent.
The South African Development Community (SADC) leadership has painted a grand vision of an interconnected gas market. To better understand this vision, high-level market research on the gas market in the SADC region has been undertaken. We assess SADC’s current position and suggest a roadmap to achieve it.
The approach we take in this article is to assess the market for natural gas via a desktop assessment of demand vs the ability of the SADC region to supply the natural gas. Available research outputs and other forms of data have been collated from the internet, using news websites, company websites, free research papers, and other online data sources, which are used to build into at least some kind of road map for natural gas demand, and equally for the supply of gas.
We begin with a brief snapshot of the SADC (South African Development Community) region and a few relevant facts, properties, and characteristics about natural gas.
Many reports, articles, and other media releases state large domestic demands in the SADC region. However, little data is provided on the demand’s source in terms of heating, electricity, and other forms. Therefore, there is little data to back up these numbers.
For the demand side assessment, we assess each of the uses of natural gas in the third world setting against an expected price for that particular use. For example, we compare an expected end-to-end cost/production price of natural gas needed for cooking purposes with the (existing) price of a substitute product (e.g. firewood). If the price of natural gas is lower than the price of firewood, then we assume natural gas can act as a substitute for that product. The outcome is that there is then a sufficient price level to warrant a purchaser switching from firewood to natural gas for heating purposes. The demand for natural gas is assumed to be fulfilled by the lower price disparity, and the demand is then (potentially) realized. Of course, for this assessment, we need a price of natural gas, so we have included a brief section on the current state of natural gas prices in the world and what an expected selling price could be in the SADC region.
For the supply portion, a high-level assessment is made through the size and location of gas reserves, and the existing infrastructure capable of delivering it to the largest populations. We have used a trigger of cities with a population of more than 1 million people by 2025. For the infrastructure, we look at transportation through transport corridors, ports and gas pipe networks. To understand how the current state of natural gas supply is developed in the SADC market, we also briefly examine the existing projects in the region, mainly in South Africa, Mozambique, Tanzania, and Angola, and their scope and size.
To conclude, we question whether the current situation in the SADC region is a precursor to the start of the SADC Integrated Natural Gas Market

Figure 1: The South African Development Community (SADC)
As it currently stands, the Southern African Development Community (SADC) is a Regional Economic Community comprising 16 Member States (Figure 1): Angola, Botswana, Comoros, Democratic Republic of Congo, Lesotho, Madagascar, Malawi, Mauritius, Mozambique, Namibia, Seychelles, South Africa, Swaziland, Tanzania, Zambia and Zimbabwe. SADC is committed to Regional Integration and poverty eradication within Southern Africa and has many strategic and regional plans to connect the region, reduce poverty and increase the well-being of the region’s inhabitants. SADC was formed with four principal objectives, namely:
Follow the link below for more about SADC: https://www.sadc.int/about-sadc/overview/
Through a Regional Gas Infrastructure and Market Development initiative, SADC is currently looking at programs and projects aimed to facilitate the availability of sufficient, reliable, least-cost energy services in support of the ambitions of its principal objectives. The objectives are concurrent with the SADC Protocol on Energy of 1996, which promotes the harmonious development of national energy policies and matters of common interest for the balanced and equitable development of energy throughout the Region.
In 2018, South Africa Minister of Energy Jeff Radebe, in the SADC Ministerial Workshop on Regional Gas Infrastructure and Market Development, outlined a vision for the SADC community. In this, he identified key constraints to the realization of this vision:
These are critical questions. Numerous authors in other developing countries have identified them as recurring issues that hinder the development of gas resources and most infrastructure projects. Therefore, the same problems seem to keep arising in most third-world countries.
Here is a summary of some relevant aspects of gas as a brief introduction and for the reader’s convenience.
The readers’ attention should be please be guided to the significantly more extensive articles in the EPCM catalogue if more detail is needed:
https://epcmholdings.com/liquefied-natural-gas-lng-overview/
https://epcmholdings.com/design-and-optimisation-of-micro-scale-natural-gas-liquefaction-processes/
https://epcmholdings.com/energy-outlook-oil-and-gas-dnv-report-notes/
https://epcmholdings.com/liquid-natural-gas-lng-value-chain-the-basics/
https://epcmholdings.com/where-natural-gas-is-found-and-how-it-is-obtained/
In our assessment, the price of natural gas is a key determinant of the likelihood of people switching from one product to natural gas, and in our assumption, in a 3rd world country is the only reason why someone would switch, i.e. environmental impact and other aspects do not play a role in decision making.
In the medium to long term, the IEA forecasts US gas prices will increase in the short term to around $7/MMBtu by 2040. This is because the more profitable reserves are being used first, with the less profitable projects remaining. Inevitably, producers then tend to develop higher-cost projects to meet demand while still maintaining some level of profitability.

Figure 2: LNG prices
The biggest uncertainty surrounding gas demand and price projections is related to
In the longer term, it is also thought that the international gas market will become more flexible, which will narrow the price difference between the European and the Asian markets. The IEA projects that European and Asian market prices will settle above the US price by around $4–5/MMBtu and $5–6/MMBtu, respectively. These spreads result from the US continuing to be the lowest-cost exporting producer in the long run, with Asian prices slightly above European prices owing to the transport cost differential.
The information available on the historical development of the SADC gas market is focused on four SADC countries: Angola, Tanzania, Mozambique, and South Africa. The other remaining SADC countries either started only recently in gas exploration or have gas markets in their absolute infancy. Madagascar is considering exploring natural gas reserves, and Namibia has already discovered two offshore fields.
Gas is currently a minor part of the Angolan hydrocarbons industry, although it is the only country in the SADC region with an LNG regasification plant. Natural gas is overshadowed by oil. BMI estimates marketable gas production for 2016 as at 3.5bcm, yet actual production will have been significantly higher, with the excess gas reinjected into oil fields or flared. Angola stands out from the rest of Southern Africa as the dominant and only oil producer. However, their gas exploration activities have only started recently. The country’s oil industry started commercial-scale production from the off-shore Cabinda fields in the 1960s. Angola has since developed a significant petro-economy with the attendant features of high reliance on oil sector revenues.
Mozambique has been producing gas since the onshore Pande and Temane fields were brought to South Africa through the Sasol Rompco pipeline in 2004. The discovery of major gas reserves in the offshore Rovuma Basin in the north of Mozambique has led to its recalibration as a major natural gas resource country and its ranking first in the SADC region.
Further north in Tanzania, gas exploration has been underway since 1952. The first discovery of natural gas was made in 1974 in the Songo Songo area, Kilwa district in the Lindi Region. Eight years later, in 1982, the second discovery took place in the Mnazi Bay area in the Mtwara region. The discovery of the natural gas reserves in these areas promoted gas research on the coastal and offshore areas, which were arguably the forerunner to the bigger, more recent discoveries. Studies were carried out by international oil companies. There have been other discoveries south of Dar es Salaam, in the areas of Mkuranga, North Kiliwani and Ntorya, between 2007 and 2012, but the extraction from these discoveries awaits infrastructure. In 1991, a natural gas purification plant was built on the island of Songo Songo along with the pipeline for exporting natural gas to Dar es Salaam. To the south of Dar es Salaam, an estimated 2.1 million cubic feet are used to generate electricity that serves the Mtwara and Lindi regions on the southern border.
The SADC region’s markets are rather small compared to those of the rest of Africa. Over the last 40 to 50 years, the gas market has been concentrated in the exploration sector in Tanzania, Mozambique and South Africa. Recently, Namibia and Angola have entered the exploration markets. Madagascar’s oil exploration industry is rather small, but the country has been considering gas exploration. The other SADC countries, such as Zambia, Zimbabwe, Seychelles and Reunion, have not been involved significantly in the exploration sector.
Of the countries in the SADC region, South Africa has been using the most gas over the longest period. The gas pipeline network in Johannesburg, fed from the ROMPCO pipelines, supplies areas of Johannesburg, South Africa’s largest population centre, with gas. Angola has been using gas for its 750MW Soyo gas power plant, which started producing power for the capital city’s electricity grid in 2017, using LNG from a variety of national oil blocks as well as the Angola LNG plant, its only liquefaction facility. The second phase will integrate the Soyo combined cycle power plant into the wider Angola power network. Tanzania’s small reserves south of Dar es Salaam have been producing gas for the local markets, consisting of gas for heating and cooking mainly for lower-income and poor households, as well as the production of electricity for the region just south of Dar Es Salaam.
Here, we assess the market from both a demand side (user needs and population size) and a supply side (available reserves, population size and location, existing infrastructure, and current projects).
As mentioned earlier, there are several reasons for the strong worldwide demand for natural gas, largely driven by the following:
However, in the context of the development of the SADC region, these are secondary. Third-world developing countries have different needs driven by large and poor populations. Their needs are determined by day-to-day living, i.e., heating, cooking, transport, and food production. This, in turn, drives the necessity for electricity, fuel for home fires, feedstock for livestock and fish stock, and fertilizers for agricultural produce.
Typically, the average African homestead does not have access to gas or other fuel for heating and cooking; firewood is the fuel. This is expensive in terms of time to collect. Transport is by foot or bicycle. Little livestock is kept besides several chickens, goats or cows with little to feed on. Agriculture is severely limited by rainfall, heat and soil conditions. Gas can change this, and therefore third world countries have a demand driven by the following interlinked factors:
According to IEA, consumption in Africa is expected to rise at a rate of 3.1% per year. Angola is currently developing 400MW of gas-fired power plants, and Tanzania is aggressively pursuing a domestic gas-to-power agenda that could result in 500 bcm of gas being committed to the domestic market.
Cooking
The majority of the population in sub-Saharan Africa depends on solid biomass for cooking and heating. The proportion is exceeding 90% for the rural population. There are a variety of different issues linked to the use of solid biomass, such as the large health burden resulting from ingesting particulates and pollutants from the combustion of solid biomass. Figure 3 shows the fuels used for cooking in Eastern Africa. In rural areas, up to 93% of the population depends on wood. In urban areas, the fuels most used for cooking are slightly different and vary between wood, charcoal and kerosene.

Figure 3: Fuel types in
To supply natural gas to residential users, a gas distribution network that connects the households to the city gate station has to be deployed. Modular gas containers can be transported via road and rail, but this quickly becomes expensive and is probably better suited to supply rural areas with sparse and small populations. Pipeline infrastructure is economically viable in urban centres due to the dense populations. The penetration of natural gas as cooking fuel in urban and rural areas depends on its price compared to the available alternatives.
Table 1 shows a comparison of the cost of the two main clean alternatives and the three most used cooking fuels in Eastern Africa’s urban areas. The different alternatives have specific efficiencies that have been taken into account to calculate a price for the same reference heat output, which is the heat output provided by one MMBtu of natural gas used in a standard cooking appliance. The cheapest fuels are charcoal ($ 18/MMBtu) and wood ($ 25/MMBtu), which explains why they are still largely used in urban areas.
Kerosene ($41 – $62/MMBtu) is between 2 and 3 times higher than charcoal and wood, depending on the country. Concerning the clean alternatives, LPG is close to the price of kerosene, and electricity is, on average, cheaper. To allow for a large penetration of natural gas for cooking, its retail price has to be competitive with the cheapest alternatives, wood and charcoal, and electricity if its price for residential users is around $0.1/kWh or lower. Using Table 1, we can assume that a competitive retail price for natural gas would be in the range of $15 – 25/MMBtu.

Table 1: Comparison of cooking fuels in East African urban areas
Electricity
With high economic and population growth, electricity consumption in sub-Saharan countries is expected to increase drastically. There are several ways to meet this high demand.
Solar generation has great potential in Africa, with an average daily solar irradiation of 5 – 6 kWh/m2, but it is largely undeveloped due to its high cost.
Hydropower is another important means of providing electricity, with the advantage of low electricity production costs (around $0.03 -0.05/kWh). However, hydro resources are not equally distributed across the SADC region, and long-distance transmission lines are required to fully exploit the sites with the largest potential.
Diesel-driven engines are other alternatives but have high operational and maintenance costs and emissions.
When natural gas is available, gas-fired combined cycle power plants represent an interesting solution. The gas-fired combined cycle power plant is the most efficient (in terms of energy and emissions) technology to convert fossil fuel into electricity.
In sub-Saharan Africa, the production cost of electricity is highly variable (Figure 4). Outside of the borders of coal-powered (and some nuclear-powered) South Africa, power generation is essentially based on hydroelectricity and diesel generators, which are either unreliable or costly and dirty.

Figure 4: Cost of electricity in Sub-Saharan Africa
In 2015, only the most competitive renewable power plant solutions could compete with coal – and gas-powered power plants. This is partly because of the low operating costs resulting from the depressed coal and gas feedstock prices. In the coming years, it is expected that the impressive cost reductions observed in some renewable technologies (particularly wind and solar) will continue to drive down costs, making them increasingly competitive with fossil-fuel-based power plants (Figure 5), which are expected to become more expensive as a result of higher feedstock price projections increasing operating expenditures. Whether renewable energies take off in the SADC region is yet to be seen. Technologies that have already matured and where there are no expected price changes in the feedstock, such as hydropower, are not expected to see significant cost changes.

Figure 5: Energy Costs for 2015 and 2040
Several different studies indicate that for gas-to-power, a gas price below $12 /MMBtu and $48/MMBtu would allow producing electricity with a Combined Cycle Power Plant at a lower cost than from diesel.
Transportation
Compressed Natural gas (CNG) can be used as fuel for road vehicles. Natural gas vehicle growth is particularly important in the Asia-Pacific region, where natural gas represents a cheaper alternative to conventional fuels (gasoline and diesel). An important advantage of natural gas over diesel and gasoline is lower emissions (particles, CO2, NOx and SO2). The drawback of CNG is that the range is about 3.5 times shorter when compared to gasoline or diesel for the same tank volume. The CNG vehicle requires a cylindrical tank pressurized at about ~3500 psi (240 bar). There is currently limited demand for gas vehicles in the SADC region, but there is an opportunity for gas-powered vehicles to realize a large proportion of the region’s transport needs and thus facilitate the expansion of the ‘gas-powered economy’ in the region.
In most sub-Saharan countries, oil products are imported, and the retail prices of diesel and gasoline are high. Hence, domestic natural gas could offer a competitive alternative. Although LPG is only marginally used for transportation, it could be seen as an alternative to conventional fuels. Retail prices have been converted in $/MMBtu to allow the comparison with natural gas. In the US, the CNG price at a refuelling station is, on average, 25% higher than the price at the city gate. Assuming a similar ratio for Eastern African countries, the natural gas price at the city gate should not exceed $25/MMBtu to $52/MMBtu, depending on the country (see Figure 8), to represent a competitive alternative to conventional transportation fuels.
The use of motor vehicles in SADC countries is relatively low compared to other third-world countries like China and first-world countries. A significant step up in terms of vehicle availability and fuel is needed before a decent market is established in this.
Fertilizer production
Sub-Saharan Africa’s agricultural productivity is low compared to other developing countries. The same is true in the SADC region. In Sub-Saharan Africa in 2010, the average fertilizer use was 8 kg/ha, compared to 303 kg/ha in East Asia and 107 g/ha in North America. This low use of fertilizers is essentially due to the relatively high retail prices for the farmers. The supply of fertilizers relies on imports, and the transportation costs (including ocean freight, port costs and truck transport) significantly impact the retail prices.
Fertilizers provide nitrogen (N), phosphorus (P), and potassium (K) as the main nutrients. They are most often produced using natural gas. On average, the cost of natural gas represents around 50% of the price of ammonia, the main feedstock for producing nitrogenous fertilizers such as urea.
If affordable natural gas is available in sub-Saharan Africa, domestic production of nitrogenous fertilizer could be developed. The distribution costs for this fertilizer can be estimated at around $115/ton. It appears that domestic production with a natural gas price as high as $15/MMBtu could supply urea at a very competitive cost ($570/ton) compared to importing urea.
Figure 6 shows a large variation in the yearly average price for urea between 2010 and 2012. In 2010 – the most favourable year – the average price of urea was between $549/ton and $808/ton, depending on the country.

Figure 6: Nitrogenous Fertilizer retail price in Eastern Africa
Considering these values for domestic production and distribution, the price of natural gas should be $14 – 24/MMBtu or lower to produce locally competitive fertilizer.
Animal and fish feed
Natural gas can be used to produce animal and fish feed. The pellets are made using methane-eating bacteria—methanotrophs—found naturally in soil and lakes. These are fed methane gas, which causes them to grow and multiply into protein-rich biomass that can be dried and turned into animal feed.
The process is essentially the fermentation of sugar into acids, gases, or alcohol, mainly by yeast and bacteria. With most fermentation, the carbon source is sugar, whereas here, the carbon source is methane in natural gas. The produce could be more environmentally sustainable and supply the growing demand for feed in the aquaculture and agriculture markets, such as farmed fish, crustaceans, and livestock.
The process uses somewhere between 60 and 80% less water than alternative ingredients, including soy and wheat proteins. In the SADC market, animal and fish feed can be used to supplement either traditional or commercial animal farming activities, thereby substituting more expensive types of feed with a gas produced. Unfortunately, due to the infancy of the development of the research into the commercialization of the process, there is little information available on production costs, but the research suggests that when gas prices are above 20-30% of the current price, the technology is not commercially feasible and will not provide a product that can be substituted for other forms of feed used in the SADC region.
Market size is a key determinant of the demand for natural gas. All else being equal, more people equates to higher demand. The SADC region has several population centres of over 1 million people (Figure 7). By 2025, these spread to several inland locations: Harare, Lusaka, Mbuji-Mayi, Lubumbashi, and an ever-growing Gauteng area in South Africa.

Figure 7: SADC major population centres – 2025 estimates
The largest population centres (14-16m) are concentrated in Dar es Salaam, Johannesburg, and Kinshasha, with Dar es Salaam being the only coastal city with port access for shipping. Luanda, Cape Town, Ethekweni (Durban), Antananarivo, and Maputo are all significant centres (5-8m), with Antananarivo being the only non-coastal city with a significant population.
Short-sea shipping is an option for coastal centres, while a mixture of piping and road/rail transport is necessary for smaller towns. River barging may be appropriate for a location like Kinshasa, but it is likely to be cheaper via pipeline.
According to EIA, at the end of 2019, the world had proven natural gas reserves of some 200,000 cm, and Africa had 15,700 cm, around 8% of the world’s total. Exploration on the continent has yielded an increase of around 1% in total African gas reserves since 2018.
Even though 90% of gas production continues to come from Algeria, Nigeria, Egypt, and Libya, the SADC countries are currently planning to utilize their gas reserves as effectively as possible to grow their economies and improve their people’s livelihoods.
The region has reserves currently estimated at approximately 1,500 cm, around 0.7% of the world’s total, the majority of which are in Mozambique and Tanzania. South Africa, Angola, Zimbabwe, and Namibia all have discovered gas, some more so than others.
Table 2 provides details of the region’s most promising reserves. They are split by country, reserve status (1P = proven reserves at 90% likelihood), and project phase (3P reserves are considered estimates and probable).

Table 2: SADC Gas Reserves
Most of the reserves are still being investigated further. What stands out is the size of the Rovuma gas fields and the offshore gas field in south Tanzania, the three in total amounting to 7,000 cm. South Africa Karoo shale gas as a P3 reserve features prominently, but with several varying estimates, the exact amount is quite uncertain. For more information on South Africa’s Brulpadda reserves, see our article at https://epcmholdings.com/brulpadda-totals-offshore-discovery/.
Concerning Angola, Mozambique, and Tanzania, the volume of gas resources is not a constraint to the wider utilization of natural gas as it is with the smaller gas fields. Each of these countries is attempting to transition to a significant gas producer and consumer from a low base, which, most notably in the case of Mozambique, requires bringing on-stream gas reserves that are orders of magnitude larger than the already producing fields.
Several common themes are present:
Therefore, a coordinated approach is necessary to avoid competition diluting the benefits of low transport costs. However, in a world of competition and free markets, this may be difficult.
With the sheer size of the Tanzanian and Mozambican gas fields, SADC countries close to the reserve have a double advantage: economies of scale and lower transport costs. Within SADC, South Africa, Zambia, and Malawi can all access this gas at relatively cheaper prices through proximity. South Africa already has a gas pipeline from Mozambique that runs over a distance of about half that from the Tanzanian and Mozambican fields.

Figure 8: Gas Reserves: Approximate location and size (Green = Operational, Yellow = P1 reserves, Red = Probable Estimates P3 Reserves. Brown sphere = total African reserves at 15,000 bcm)
Gas is different from oil. The lower energy content per unit, dependency on local infrastructure, asset specificity, capital expenditure and the need to secure a market at the early stages of a project make the exploration and production projects for natural gas different from those of oil. As such, a typical contract would treat natural gas somewhat differently from oil, and from the producer’s perspective, the contract between the producer and the gas purchaser becomes crucial for the project.
Long-term supply contracts are an essential part of the financing of large-scale natural resource projects by providing security as to off-take and prices, from exploration and production to pipelines and/or natural gas liquefaction facilities.
Long-term natural gas commodity contracts have been the backbone of the EU’s security of supply for decades. Since the 1970s, these contracts have been used to import more than 250 Bcm/year of natural gas to the EU area. Accepted as the modus operandi among both producers and the EU purchasers, the traditional view is that long-term take-or-pay contracts provide for the security of demand for the producer and the security of steady supply for the purchaser. The producer has the certainty of demand and can plan for the necessary investments with a long-term rationale. The purchaser has the certainty of supplies and can, therefore, adopt a long-term strategy in downstream markets.
In the SADC context, the long-term contract needs project developers to trust that governments will uphold their end of the contract. Perhaps traditionally, Africa has a legacy of poor contractual performance, an unsophisticated, if any, regulatory environment, and a poor justice system. These are precursors to a lack of trust in contracts. Regulations are essential, and indeed, this seems to be changing, perhaps off the back of the success of other African hydrocarbon industries, such as Libya’s, Nigeria’s and Angola’s. In Mozambique and Tanzania, for example, long-term contracts are largely in place for a large proportion of the reserves in the ground, a highly promising position. To top it off, South Africa has, of course, been importing gas from Mozambique since 2003, and it has a 16-year history of trust.
The SADC region has an extensive network of freight transport corridors. These corridors were first established in the 1980s because of the many landlocked countries in the region. A particular motivation was to bypass South Africa in rejection of the apartheid government there at the time. The corridors were mostly identified starting from a port and developed, protruding inwards towards the landlocked countries (Figure 9).

Figure 9: Transport Corridors and ports in the SADC region
Today, the SADC transport corridors are regarded as some of the most successful corridors in the world. Some features that made them successful include common political objectives, adopting a common language (English), similar road and rail design and operational standards, cooperation among member states, and the establishment of corridor-specific secretariats. The SADC corridor approach to regional development is based on well-maintained and operated infrastructure and the provision of seamless transport services.
However, although the corridors have been successful to date, there are several challenges relating to providing adequate regional infrastructure and related transport services, a setting that urgently requires strategies to improve and expand the freight transport system to meet emerging demand. Freight transport in the SADC region is furthermore characterized by extreme polarization in favour of road transport. The setup translates into a situation in which there are numerous negative aspects, including a high rate of transport-related accidents, road congestion, high infrastructure expenditure, and environmental damage. This inevitably results in high transport costs.
South African ports dominate the extensive port system in the SADC region, both in terms of sheer numbers and capacity and volumes handled. South African ports also serve the majority of landlocked countries in the SADC region (Figure 9). Most ports in the SADC region were primarily designed to serve the needs of the individual countries and their natural hinterlands, and thus, there is an apparent fragmentation in the general transport networks that connect the ports. Many of the SADC ports are also general ports focused on a variety of imports and mineral exports and, hence, are not adapted to SSS.
Additionally, Africa’s high average growth rate over the last few years has had a marked effect on the utilisation and efficiency of these ports, and many are operating around their design capacity. Opportunities for new operations are emerging slowly, such as the specialization of ports for container handling or dry bulk handling, especially in high-potential markets such as Namibia and Tanzania.
Short sea shipping has the theoretical potential to work in the SADC, given the large geographic region, projected freight volumes, and customs and trade policies the SADC region is pursuing. Such a system would have three main roles: to offer unimodal freight transport between port cities, to offer the main leg of an intermodal route, and to offer feeder services to deep-sea shipping in a hub-and-spoke cycle. However, freight transport in the SADC region has several shortfalls that need to be addressed—of note, port competitiveness, customs provisions, and policies for intra-regional trade require impetus. However, the uploading and discharge of the gas from the vessel through liquefaction and regasification via FSRU offshore can be challenging, especially in environmentally sensitive and harsh offshore ocean conditions.
The SADC pipe network is in an early stage of development. Sasol pipes gas from the Pande Temane reserve in Mozambique to Sasolburg, from where it is distributed to the greater Johannesburg area.
Several other projects are currently being studied to increase the available pipe network in the SADC region, and these are mostly focused on the Eastern SADC countries. These studies are still in their infancy, but SASOL has indeed shown that long-distance gas pipelines can work in Africa.

Figure 10: SADC Gas Pipe Network
Mozambique
Mozambique’s current natural gas production is operated by Sasol (South Africa) in Inhambane Province, which holds proven reserves of 300 bcm. The natural gas is produced and processed at a central facility in Temane and then transported via an 865 km pipeline to South Africa, with a link to southern Mozambique for domestic use. Additionally, Sasol will develop an integrated oil and liquefied petroleum gas project adjacent to its existing petroleum facility. The project includes 13 wells and an LPG production facility at an estimated cost of USD 1.4 billion.
Due to the discovery of over 4500bcm of natural gas reserves in the Rovuma basin by Texas-based Anadarko (Area 1) and Italian firm ENI (Area 4), Mozambique is expected to become a major exporter by 2023. Anadarko will build an LNG plant to process the gas they discovered in Area 1, off the northern coast of Mozambique near the border with Tanzania. It selected a joint venture of developers that includes McDermott (USA), Saipem (Italy), and Chiyoda (Japan) to construct the Afungi LNG Park, which is valued at USD 25-30 billion. Anadarko expects to conclude several sales and purchase agreements (SPA) by year-end for liquefied natural gas (LNG), and they announced their final investment decision in June 2019 for USD 25 billion during the recent US-Africa Doing Business Summit Conference. This is a major investment for Mozambique and the first of such value in the entire African continent.
On June 1, 2017, ENI announced the final investment decision amounting to USD 8 billion for the construction of six subsea wells connected to a Floating Liquified Natural Gas (FLNG) production facility in Area 4, which is due for completion in mid-2022. The Engineering Procurement and Construction (EPC) contract was officially awarded to a TechnipFMC, JGC, and Samsung Heavy Industries consortium. Furthermore, in 2018, ExxonMobil acquired a 25% indirect interest in the Area 4 block from ENI. As part of this agreement, ENI will lead all upstream operations, and ExxonMobil will lead the construction and operation of liquefaction facilities onshore to be located in the Afungi LNG Park.
Tanzania
The international gas outlook indicates that the overseas natural gas markets are large and lucrative enough in the medium to long term to make the development of Tanzanian offshore gas deposits economically viable. Therefore, it is understandable why proposals from international oil companies (IOCs) in Tanzania have focused on liquefying the gas for export.
As recognized by the Government of Tanzania, however, natural gas can be a powerful tool to facilitate the country’s broader economic development and diversification. Compared with coal, liquid fuels, and biomass, it provides a readily available and relatively clean source of energy for power generation, industrial use, and residential consumption.
Thus, all countries that develop their gas primarily for export must answer the complex and important questions related to domestic use. The Government of Tanzania, through Article 8 of its production-sharing agreements, has the right to require IOCs to make up to an extra 10% of the exported gas available to be sold within Tanzania.
Before its final approval of the offshore development and LNG proposals, the Government must agree with upstream companies on the arrangements as to how much gas will be reserved for domestic use, how it will be delivered, how costs will be shared, and the price for the gas that will be paid to the developers. Each of these upstream arrangements must be considered in conjunction with decisions on how onward usage, transmission and pricing of that gas to final consumers will work. This section outlines some of the key considerations that must be considered in domestic gas allocation.
South Africa
Most of the dry natural gas is exported to South Africa via the ROMPCO international gas pipeline, which currently exports some 3.65 cm. Those fields are estimated to end their life around 2027, and Sasol is, therefore, actively exploring adjacent blocks.
Sasol and its partners’ development of the Temane fields in the Inhambane province has moved onto engineering design to handle wet and dry gas as well as LPG. Most of the gas will go to a 400-megawatt (MW) power plant in Maputo, with the rest destined for third-party customers using the ROMPCO pipeline.
VGN and NGV Gas receive natural gas at a distribution station in Langlaagte via the Sasol Gas pipeline, which runs from Temane to Secunda and then to Johannesburg. The company then distributes gas to customers anywhere within a 300 km radius of this distribution station, managing the entire delivery process on a pay-as-you-use basis according to customers’ energy requirements.
Getting the gas to the markets
The large reserves found in Tanzania and Mozambique, totalling some 3% of the world’s reserves, will undoubtedly assist in taking the SADC region’s vision of an integrated gas market to fruition. Piping natural gas from Mozambique to South Africa has shown that this can technically work over some 1000km. Connecting this existing pipeline to the gas fields in northern Mozambique and southern Tanzania, as well as to Dar es Salaam, will significantly open up the entire eastern seaboard of Africa, south of Kenya, to the gas market. Relatively short tap-in lines can then feed the internal landlocked markets of Harare, Lusaka, Mbuji-Mayi and Lubumbashi and open up Zimbabwe, Malawi and Zambia to gas markets. The existing road and rail network can assist in getting the gas to the smaller markets, i.e. villages and other types of informal settlements, in a small modular form suitable for cooking and heating.
For the western seaboard of SADC, Cape Town and Windhoek, as the largest population centres, can be served via short sea shipping from the gas export facilities in Mozambique and Tanzania. The markets of Kinshasha and Luanda can be served from Angola’s 3P reserves and perhaps even the Mozambique and Tanzania reserves.
The industry can be reassessed in the large capital cities for manufacturing plants for gas-assisted fertilizer and animal feedstock plants, especially where these cities are close to the larger agriculture and livestock farming economies.
Re-alignment of the long-term contract
Due to the increased flexibility of LNG, spot markets and potentially unconventional natural gas providers, the significance of long-term take-or-pay contracts from the purchaser’s point of view has started to change in the EU. Alternative sources of supply, together with the storage of natural gas where possible, provide flexibility in the incumbent’s purchasing portfolio that downplays the need to rely on long-term contracts. It requires a well-developed gas market in the SADC region before this approach can be emulated between the major SADC gas producers (arguably Tanzania, Mozambique, Angola and South Africa) and the potential major SADC purchasers (Democratic Republic of Congo, South Africa and Madagascar).
Achieving SADC Developmental Goals
Natural gas is already a reality for industrial and transport sectors within a 300 km radius of Johannesburg thanks to NERSA-approved gas traders Virtual Gas Network (VGN) and NGV Gas’ development of a compressed natural gas distribution infrastructure, including delivery networks, filling stations and conversion systems. These companies have already converted state hospitals, canneries and manufacturing and assembly plants across a range of industries, in addition to commercial fleets, busses and around 1,000 taxis, to natural gas.
In so doing, the end-users have been able to:
The increased availability of this superior, alternative energy source in Gauteng is enhancing the long-term profitability of assets in the industrial and transport sectors. As South Africa’s gas economy develops, the country will be able to increase production efficiencies, economic growth, and job creation while reducing reliance on a less efficient, polluting fuel used in ageing energy infrastructure.
An early start?
South Africa, Angola, and Tanzania are far more advanced in terms of using gas for domestic use and electricity generation than the remainder of SADC. This is important because it means there is an example for SADC to learn from, a backbone of exploration activities (most of the SADC countries), moderate levels of extraction from the relatively small fields in Mozambique, Tanzania and Angola, liquefication facilities and supply network feeding the cities (Johannesburg) and the power plants (Angola and Tanzania), which all provide a very positive indication that SADC has (at least, pre-emptively) started to move forward in its grand ambition to connect the member countries with natural gas.
Gas has a huge role to play in the social and economic development of the region, from heating, cooking, transport, fertilizer, feedstock and bunker fuel; the direct and indirect benefits to the population are immense, and perhaps it has already begun.
Demierre, Jonathan & Bazilian, Morgan & Carbajal, Jonathan & Sherpa, Shaky & Modi, Vijay. (2014). Potential for regional use of East Africa’s natural gas. Applied Energy. 143.
http://wiki.openoil.net/History _of_Tanzania’s_Oil_and_Gas_Industries
https://www.chathamhouse.org/sites/default/files/public/Research/Africa/260213presentation.pdf
https://energypolicy.columbia.edu/sites/default/files/Potential-for-Regional-Use-of-East-Africas-Natural-Gas-SEL-SDSN.pdf
https://macauhub.com.mo/2017/08/14/pt-central-de-ciclo-combinado-do-soyo-angola-comeca-a-produzir-energia-electrica/
https://www.allaboutfeed.net/New-Proteins/Articles/2018/7/The-future-of-feed-might-be-microbial-protein-312228E/
https://www.alliedmarketresearch.com/press-release/bunker-fuel-market.html
https://www.dbsa.org/EN/DBSA-in-the-News/NEWS/Pages/20191113-DBSA-Mozambique.aspx
https://www.dmr.gov.za/mineral-policy-promotion/shale-gas
https://www.eia.gov
https://www.export.gov/article?id=Mozambique-Oil-Gas
https://www.mdpi.com/2071-1050/11/6/1532/htm
https://www.psmarketresearch.com/market-analysis/bunker-fuel-market
https://www.rystadenergy.com/newsevents/news/press-releases/the-australian-lng-market/
Obadia KB, Lingling Z, Witness GM, Shaldon LS, Grace GM, An overview of the natural gas sector in Tanzania – Achievements and challenges, Journal of Applied and Advanced Research, 2018: 3(4) 108−118
Wanzala, Maria, and Rob Groot. “Fertiliser Market Development in Sub-Saharan Africa.” International Fertiliser Society. Windsor, UK, 2013.
Concerns surrounding the world’s current dependence on fossil fuels and their negative environmental impacts have instigated research into alternative, renewable and sustainable energy sources. With exponential population and economic growth, plastic usage is a concomitant increase. With space becoming a premium commodity and environmental protection a necessity, landfilling most of the world’s waste is no longer feasible. Thus, research is being carried out into waste-to-energy processes and refuse-derived fuels. Of these processes, pyrolysis is increasingly being used to turn waste plastic into diesel. This article will explore how pyrolysis works and whether it can meet expectations.
Plastic is formally defined as ‘anyone of a large group of materials consisting wholly or in part of combinations of carbon with oxygen, hydrogen, nitrogen, and other organic or inorganic elements which, while solid in the finished state, at some stage in its manufacture is made liquid, and thus capable of being formed into various shapes, most usually through the application, either singly or together, of heat and pressure.’
Less formally, plastics are an inexpensive and durable group of materials with the desirable property of being moldable into a limitless variety of products that find use in a vast range of applications. Due to the diversity in the applications and their convenience in use, the production of plastics has increased markedly over the last 60 years with a concomitant increase in waste generation, albeit with a time lag dictated by the product’s lifetime. However, current levels of plastic usage and disposal generate several environmental problems. Approximately 4% of the world’s oil (irreplaceable) production is used as feedstock for plastics, and a further 3–4% is expended to provide energy for their manufacture. A major portion of plastic produced yearly (up to 50%) is used to make single-use disposable items of packaging or other short-lived products discarded within a year of manufacture (Hopewell, Dvorak, and Kosior 2009). Compounding this is the short lag-time from manufacture to discard of this application of plastic.
Unfortunately, the majority of plastics are known not to be biodegradable and will remain in landfills or the environment for at least decades and probably for centuries. Even plastics known to be degradable may persist for a considerable time depending on local physical environmental factors, such as levels of ultraviolet light exposure, oxygen, and temperature.
Therefore, the combined impact of the large quantity of the short usage lifespan applications and the high durability and longevity of the polymers means substantial quantities of discarded plastics are accumulating as debris in landfills, natural habitats and oceans worldwide. There is growing concern about landfills’ potential hazards and environmental impacts. Increased waste means that larger, unsightly landfills are required, bringing noise, smell, and pollution with them. There are also long-term risks of contaminating soils and groundwater by some additives and breakdown by-products in plastics. As a result, the general public is becoming less accepting of current waste disposal techniques, and there is increasing pressure on the government and industry to find alternatives to dumping and incineration.
Plastic to Diesel The Pyrolysis Process: Recycling is one of the most important actions currently available to reduce these impacts and represents one of the most dynamic areas in the plastics industry today. Recycling provides opportunities to reduce oil usage, carbon dioxide emissions, and the quantities of waste requiring disposal. Additionally, useful products can be derived from plastics. Recycling is typically grouped into four main categories: primary (mechanical reprocessing into a product with equivalent properties), secondary (mechanical reprocessing into products requiring lower properties), tertiary (recovery of chemical constituents) and quaternary (recovery of energy).
Only approximately 20% of waste plastics can be effectively recycled by primary and secondary mechanical recycling technologies. Beyond this, plastics have become increasingly mixed and contaminated with impurities such as soil, metal foils, labels, and food remnants. Plastics, as high molecular weight substances, cannot be purified by physical processes like distillation, extraction, or crystallization. They can only be recycled by gasification or pyrolysis of their macromolecules into smaller fragments. Pyrolysis (Greek: pyro “fire” and lysis “separating”) is a tertiary recycling technique suitable for converting plastic waste into oil products, combustible gas, fuels or monomers using a thermal decomposition process under oxygen-free conditions. The pyrolysis products can then be refined (following a catalytic upgrading process) by conventional petrochemical separation processes to yield higher-value commodities. Moreover, it allows the treatment of mixed, unwashed plastic wastes. Further, there are no toxic or environmentally harmful emissions or by-products. Pyrolysis thus has great potential for recycling heterogeneous plastic waste that cannot be economically physically separated and classed. The production of gasoline, kerosene and diesel from waste plastics is an emerging technology solution to the vast amount of plastics that conventional recycling cannot economically recover.
In short, the key advantages of pyrolysis which differentiate it from other recycling systems mean that this process:
Pyrolysis produces three phases of fuel products: solid (char), liquid (pyrolysis/fuel oil) and gas in different ratios depending on process conditions and process type. Once the process conditions are optimised and when coupled with catalytic cracking, pyrolysis of plastic waste can generate liquid fuel yields of up to 80%, with the resulting product resembling diesel fuel, kerosene, gasoline or other useful hydrocarbon liquids. Sharma et al. 2014 demonstrated using high-density polyethene grocery bags as a feedstock produced 74% fuel oil, 9% gas and 17% solid char.
There are two main types of pyrolysis: conventional (or slow) and fast pyrolysis. Vacuum pyrolysis is a hybrid between the two, combining the low heating rates used in conventional pyrolysis with the very short volatile residence times in fast pyrolytic setups. Each has different process conditions and setups and is used to achieve different end products. Vacuum and conventional pyrolysis are very similar in the process set-up, differing only in the process atmosphere and residence times, which are much shorter for vacuum conditions. The reduced residence times decrease the likelihood of undesirable secondary reactions whereby the primary pyrolysis products are further degraded. Thus, vacuum pyrolysis produces more oil and less char and gas than conventional pyrolysis, making it particularly suitable for plastic to diesel operations.
The pyrolysis product yield and composition are controlled not only by the temperature but also by the residence time. As a general rule of thumb, the higher the pyrolysis temperature, the higher the yield of non-condensable gaseous products and the lower the yield of liquid fuels such as diesel. The optimum temperature range for producing diesel products from waste plastics is 390–425◦C.
Following pyrolysis in the thermal cracking reactor, which performs the thermal decomposition of the plastic, the gas stream is purified of hydrochloric acid derived from polyvinyl chloride (PVC) feedstock (through a scrubber) and subsequently reformed by contacting with a catalyst in a reactor (Figure 1). The condensate from this reaction is routed to a fractionating tower, where the desired fuels can be separated. The carbon residue precipitated in the thermal cracking reactor is continuously discharged out of the process using a centrifugal separator. A wide variety of reactor designs operate commercially on this principle, known as catalytic upgrading, with operating parameters optimised based on the feedstock composition and the desired output fuel.
Once optimised, the plastic-derived diesel produced using this technique is suitable as a direct replacement for conventional diesel. In studies comparing the two, compression ignition engines required no modification to run on the plastic-derived diesel and exhibited increased thermal efficiency and a reduction in smoke (Mani, Nagarajan, and Sampath 2011). Any viscosity variations of the plastic-derived diesel can be offset typically using Diethyl Ether to achieve air-fuel combustion ratios similar to that of conventional diesel, which has been shown to improve the cetane rating beyond that of conventionally derived diesel (Devaraj, Robinson, and Ganapathi 2015). It should, however, be noted that the performance of the waste plastic-derived diesel is always tied to the composition of the feedstock.

While shown to be technically feasible, the potential for conversion of waste plastic to diesel cannot be concluded without examining the challenges, the biggest of which is the need for a consistent feedstock. The quality and physical properties of the diesel resulting from any pyrolysis process heavily depend on the feedstock and the operating parameters. These parameters can be fine-tuned to compensate for changes in the feedstock composition, but this takes time and knowledge of the feedstock and the process. This makes it difficult to do in remote installations. Therefore, coupled with any plastic-to-diesel installation, a waste sorting and characterisation facility would be required for efficient diesel production.
Further challenges arise when benchmarked against renewable energy sources, such as solar voltaic installations, primarily on a cost-per-energy basis. However, these analyses fail to include the benefits of using plastic as a feedstock rather than sending it to landfills or for conventional recycling. Numerous studies have shown that pyrolysis presents a desirable solution compared to traditional recycling, incineration, and landfilling waste plastics. Therefore, pyrolysis represents a powerful additional tool for integrated waste management schemes and, with time and additional research, can provide an economical solution for waste plastic in modern society. Read About EPCM
Kaimal, V. K., & Vijayabalan, P. (2015). A detailed study of combustion characteristics of a DI diesel engine using waste plastic oil and its blends. Energy Conversion and Management, 105, 951–956.
Wongkhorsub, C., & Chindaprasert, N. (2013). A Comparison of the Use of Pyrolysis Oils in Diesel Engine. Energy and Power Engineering, 05(04), 350–355.
Scheirs, J., & Kaminsky, W. (2006). Feedstock recycling and pyrolysis of waste plastics. Wiley Series in Polymer Science (Vol. 2006).
Devaraj, J., Y. Robinson, and P. Ganapathi. 2015. “Experimental Investigation of Performance, Emission and Combustion Characteristics of Waste Plastic Pyrolysis Oil Blended with Diethyl Ether Used as Fuel for Diesel Engine.” Energy 85: 304–9.
Hopewell, Jefferson, Robert Dvorak, and Edward Kosior. 2009. “Plastics Recycling: Challenges and Opportunities.” Philosophical Transactions of the Royal Society B: Biological Sciences 364 (1526):
Mani, M., G. Nagarajan, and S. Sampath. 2011. “Characterisation and Effect of Using Waste Plastic Oil and Diesel Fuel Blends in Compression Ignition Engine.” Energy 36 (1): 212–19.
Sharma, Brajendra K., Bryan R. Moser, Karl E. Vermillion, Kenneth M. Doll, and Nandakishore Rajagopalan. 2014. “Production, Characterization and Fuel Properties of Alternative Diesel Fuel from Pyrolysis of Waste Plastic Grocery Bags.” Fuel Processing Technology 122: 79–90.
Waste not, want not: a home-grown plan to turn plastic and tyres into fuel, Monash University
Turning waste into power: the plastic to fuel projects, Power Technology
Civil Engineering Works at Tank Farms: Tank farms are exciting places for engineers: there are a few examples of how various engineering disciplines have to co-exist, cooperate and integrate as much as in these intimidating, imposing and impressive facilities. Most people think tank farms, with their storage vessels, pipes and pumps, are the exclusive hunting grounds of mechanical and chemical engineers, while civil engineering is about structures, roads, water and concrete, right? Exactly… but let’s start with a bit of context.
The storage of hydrocarbon and other chemical products is necessary for many sectors of the economy to support industrial or commercial operations.
At the large enterprise end of the spectrum, tank farms are built to receive, store, process, and distribute products to consumers. This often means that the facility is geographically placed at the interface between transport modes—for example, to receive the product from an off-shore pipeline and deliver via dispensing trucks or rail. At the smaller end, a tank farm may be built to uniquely serve the operations of a factory or airport operations and secure supply continuity.
Mega tank farms, some owned and operated by governments, are used as buffers against the volatility of price or supply. One of the largest tank farms on the planet is located in Pengerang, Malaysia: the site can hold 420,000 cubic metres of crude (2.6 million barrels) and provides blending and distribution services. The Houston Fuel Oil Terminal Company, reportedly the largest oil storage terminal on the US Gulf Coast, has a capacity of more than 13.8 million barrels. In the Emirate of Fujairah, the UAE is building the world’s largest underground crude storage facility with a capacity of 42 million barrels. Imagine the size of this thing!
Notwithstanding size and purpose, all tank farms are business enterprises in their own right. In addition to the commercial motive, their continuity, safety, efficiency, and environmental impacts are the topics of compliance with regulations and service level agreements with consumers. The facility has to be designed against the backdrop of these realities. Enter the civil engineer.
Petroleum products and other chemicals are undeniably critical to the functioning of every economy on the planet. If an airport tank farm ceases operation, planes don’t take off. If the fuel supply at a commercial farm runs out, crops don’t get harvested.
The risk goes beyond economics: tank farms are hazardous places. Fires, explosions, and chemical releases risk humans, infrastructure, and the environment. Because of where they are placed, catastrophic failures at tank farms will create disastrous effects. Safety and Reliability Engineering, Fire Engineering, and Control and Instrumentation (C&I) are key disciplines in tank farm operations and utilise sophisticated early warning detection, protection, and shut-down systems.
More than one-fifth of tank farm failures are attributable to human error, and over half are due to tank failures. Advances in IoT, automation, digitalisation, artificial intelligence, predictive maintenance, and geomatics reveal new opportunities for engineers to understand, anticipate, predict, and mitigate risks. The growth in global environmental awareness and political (and statutory) and societal pressures to reduce carbon emissions will accelerate these developments.
Tank farms are ideal targets for malicious attacks. They require physical security and protection infrastructure and management systems worthy of a military installation. Here, too, there is a rise in the application of AI and intelligent detection science. Given the obvious implications for designing physical infrastructures such as perimeter walls, access points, canopies, and internal protective walls, the civil engineer is a key member of the professional team responsible for security.
Why standards and specifications? Consistency, efficiency, quality, and integrity of design and operations are the keywords here for all the good reasons of safety, security, and environmental protection already mentioned. Knowing the integrated system of standards informs the civil designs and construction works in tank farms is useful.
The petroleum industry relies on national and international bodies to develop specifications and codes of practice. Examples are the International Organisation for Standardisation (ISO), the American Petroleum Institute (API), the British Standards Institution (BSI), the American Society of Mechanical Engineers (ASME) and the Society for Petroleum Engineers (SPE). Their specifications and codes, specifically those of the API, are considered the de facto international standards and often form the basis for national or regional standards. However, in a particular country or region, there will be differences that account for local contexts and practices.
The Association of Oil and Gas producers explains the hierarchy of standards as follows:
The need for a harmonized global approach has been pushing the industry towards international standards based on the ISO system. Several API codes have already been transferred to ISO to become global ISO standards. 

Safety, health, and environmental protection, in conjunction with best practices in quality management – collectively, SHEQ – are disciplines that are in their own right. Practitioners qualified to implement an integrated SHEQ management system comprising safety and health (OHSAS 18001 or its local equivalent), environmental management (ISO 14001) and quality management (ISO 9001) are mandated and indispensable role players in petroleum projects and operational teams.
Engineers are used to working with standards, so there is nothing new here: there are industry-specific design codes for fuel tanks, pipes and pumps, reinforced concrete structures, earthworks and treatment of contaminated effluent, and specialists are no strangers to these. For civil engineers, the challenge is to discover how the standards applicable to tank farms inform and shape their application of discipline-specific standards: the design of a drainage system is simple enough to do, but it has to comply with the requirement to separate contaminated- and stormwater run-off. It is often at the interface between a civil design and a mechanical system where detail is overlooked.
The engineering disciplines involved in a tank farm do not act in isolation – to develop a solution, they have to integrate their respective contributions, cooperate with SHEQ practitioners, planners, architects, environmental consultants and C&I specialists, and account for the operator’s management system requirements. This says a lot about the need for civil engineers to widen their scope of consideration, bring systems thinking to the table and become acquainted with new technologies. A new breed of civil engineers is in the making…
Except in the perfectly automated tank farm of the future, vehicles and people are integral parts of the facility. Fuel dispensers and loaders manoeuvre to loading and metering bays, service vehicles carry technicians between workshops and pump bays, personnel walk from point to point, contractors and visitors arrive, park and leave. These movements require roads, parking areas, and various types and sizes of platforms.
Civil engineering comes into its own in this domain – the site layout plan is a starting point, accompanied by a conceptual design to serve operating requirements. Basic designs will consider design vehicles (i.e. vehicle classes, their operating loads and speeds, and turning circles), pedestrian movements, tank farm operations, drainage and soil conditions. The geometric design will specify gradients, space and layouts to optimise earthworks, assist operating flows and ensure the safety of movement. The roadway and platform design will put down a layered structure capable of carrying vehicles over its design life (often 20 years and more) and channelling rainwater run-off.
It is common for detailed road designs to consider several options. Roadways and parking surfaces could be built of gravel, asphalt, or concrete, and drainage could be along open (grated) channels or pipes. When making a detailed design recommendation to the client, the engineer evaluates the options by considering the appropriate standards, soil characteristics, available materials, constructability and economic parameters, and the impact on operations and maintenance.

Tank farm loading platforms must be impermeable and resistant to damage by the product and fire, and containment must be provided in the case of spillage. This mostly leads to the decision to use Portland cement concrete because it presents a life-cycle cost advantage with regard to maintenance.
A critical input to the design work is a geotechnical survey, which will assess the geology of the site and the surrounding area, collect meteorological and hydrological data, assess seismic activity and perform in-situ and laboratory tests of soil characteristics. These surveys and tests must be carried out by a geotechnical specialist who will produce a report with recommendations about drainage, the suitability of in-situ materials as foundations, and special soil treatments that may have to be applied. Of specific concern to civil engineers is the presence of clay (which would be susceptible to heave and settlement), collapsible soils and corrosive materials. Soil mechanics, a discipline of civil engineering, is a well-established science and design code that makes provisions for handling the variety of conditions likely to be encountered during projects.
Planners and architects will play the leading role in designing administrative buildings and workshops, paying due attention to the relevant building codes, safety specifications, functional requirements, and human needs. Working in a tank farm is a hazardous business, and the intention is to make these facilities comfortable, functionally effective, safe, and, increasingly, green.
These designs should include the inputs of civil engineers and their colleagues from the oil and gas and C&I disciplines, who can incorporate the constructability of designs and requirements for safety and effective interfaces to operations into the planning. The designs and construction must achieve structural and functional integrity, for which the civil engineer will complete detailed designs of columns, footings and foundations, reinforced concrete walls, floors and roofing structures.
Similar to the requirements for roads and platforms, the site’s geotechnical characteristics will be prominent in the design of footings, foundations, and structures that will withstand lateral pressures, seismic activity, and the design loads.
Of course, the civil engineer’s responsibility does not end with designs. During the procurement and construction phases of the project, she made a critical contribution to oversight, quality control, and commissioning. In these matters, the engineer’s primary accountability is to produce an outcome consistent with standards and protect the client’s and facility users’ interests.
When it rains, water wants to run to the lowest point. During heavy downpours, this run-off can flood operations and become a safety hazard, in few places more acute than a tank farm with its containment structures. Civil engineers consider hydrological information and geotechnical surveys to design drainage capacity for the water volumes generated by a storm size of selected recurrence probability, such as a 1 in a 20-year flood. Drains must have a specified minimum gradient of 0.6% to prevent the drainage system from acting as a reservoir and carry run-off away quickly and effectively.
Contaminated runoff is particularly important to design because industry codes require the separation and containment of such effluent. To prevent contamination of external stormwater drainage systems, effluent drainage should be capable of being released to natural courses only when it is safe to do so, namely when hydrocarbons have been sufficiently separated and removed to achieve water quality in keeping with local discharge standards.
Civil engineers design the structures, pipes and channels that carry and contain spillage and contaminated run-off. The containment structures typically include bunded areas (say around pump bays), separator vessels (in which contaminated effluent is treated mechanically, chemically or organically) and attenuation dams (to contain a sudden large volume of run-off and control its release). These structures require a civil engineer to design their capacity (again, industry codes prescribe the standards and parameters for use) and functional operation. Separator tanks could be built on-site as a reinforced concrete structure, but specialised vessels and technologies are also commercially available. No matter the type, containment and treatment vessels require earthworks and foundations, which are uniquely civil engineering territory. Again, geotechnical information is an important input to the design process.
Spillage in tank farms has the potential to permeate and contaminate groundwater. Many tank farms include monitoring wells in their designs to enable continuous measurement, reporting, and planning to mitigate the risk of pollution. The geotechnical survey is of great assistance here because it will identify the level of the groundwater table and how in-situ materials may assist or impede the ingress of contaminants.
Tanks in a tank farm, and any other functional system that may spill hydrocarbons (e.g. the loading bay), have to be placed in bunded containment areas, for which there are specific standards and design requirements. Bund walls and floors must, for example, be water-tight and able to withstand the rush of a large volume of fuel in the event of a tank rupture. This translates into reinforced concrete retaining walls and foundation structures for large vessels. This translates into more civil engineering design and construction work.
Around a tank farm, various functional systems, such as filter bays, loading bays, and pump stations, are placed on foundations and bunded platforms that are impermeable and resistant to damage from products and fire. Of course, they can accommodate the static and dynamic loads imposed on them. Their protection with firewalls and canopies to direct rainwater elsewhere requires structural design work. Think civil engineering again!
Appurtenant to these structures is the steel furniture of elevated walkways and stairs, inspection gantries, work platforms, and structures to support overhead cranes, pipes, and equipment. The civil engineer with a love for steel has all the challenges to be desired!
Civil engineers have always been, and will remain, an indispensable element of how tank farms are planned, designed, built and operated. It is just that their contribution is not that visible to the casual observer, what with the size of the thing and all the intimidating tanks, pipes, pumps and valves around. Look a little deeper, and you will discover a world with magnificent challenges and exciting solutions for which civil engineers are uniquely qualified. Here’s to the civil engineers who make our buildings trustworthy, our roads and dams functional, our tank farms productive and safe, and our world overall a better place to live in!
Read more about EPCM Storage here
https://oilfiltration.globecore.com/characteristics-types-purpose-tank-farms/
https://www.eia.gov/todayinenergy/detail.php?id=21552
http://lightningsafety.com/nlsi_lls/Causes-of-Failures-in-Bulk-Storage.pdf
http://www.piping-engineering.com/tankfarm-types-design-considerations-plot-plan-arrangement-dyke-enclosure.html#
https://www.tankstoragemag.com/display_news/10521/ADNOC_to_build_worldrsquos_largest_underground_crude_oil_storage_facility/
Florea, Gheorghe and Popa, Marian – Safety and Security Integration in LPG Tank Farm Process Control in Proc of the 14th IFAC Symposium on Information Control Problems in manufacturing, Bucharest, May 2012
https://www.digitalrefining.com/article/1001311,Automation_of_tank_farm_systems.html#.XjEq5y17FsY
https://www.extractiveshub.org/servefile/getFile/id/5185
http://www.ogp.org.uk/pubs/426.pdf
http://www.iogp.org/wp-content/uploads/2016/12/Standards-Issued-2017.pdf
https://www.sciencedirect.com/topics/engineering/tank-farm
Gas is a substance (elements or compounds) that expands freely to fill an entire container. This implies that gas will expand freely to fill the shape of any stored container. Various elements and compounds exist in gaseous states, including oxygen, nitrogen, hydrogen, carbon monoxide, carbon dioxide, and hydrocarbon gas (Methane, Ethane, Propane…, etc.).
Hydrocarbons are organic compounds consisting entirely of carbon and hydrogen. In this article, EPCM emphasizes hydrocarbon gas (Natural gas).
Natural gas is a naturally occurring hydrocarbon gas mainly consisting of methane. It may contain a varying amount of other higher alkanes, a small percentage of hydrogen sulphide, carbon dioxide, and helium. Natural gas is formed when organic materials (plants and animals) buried deep in the earth’s crust are exposed to intense heat and pressure for years.
Natural gas is an energy source for electricity generation, cooking, heating, etc.
Natural gas, in its processed state, is gaseous. However, it can be conditioned to a liquid state (this is called Liquid Natural Gas or LNG).
Natural gas exists naturally in the gaseous state unless processed and conditioned to exist in a liquid state. It is colourless and odourless and is transported in its gaseous state using pipelines, specially built tubes/storage vessels mounted on trucks and Ships.
Natural gas can be processed and conditioned to a liquid state called LNG (Liquefied Natural Gas). It can be liquefied by cooling the gas to –260° F (–162° C). At this temperature, the gas changes into a liquid. Using specially built LNG transport Vessels, natural gas is transported in large quantities in its liquefied state (1/600th of its original gas volume) over long distances. Natural gas cannot be used in its liquefied state; therefore, at its destination, it is converted into a gaseous state by warming the gas through regasification.
Natural gas, either in a gaseous or liquid state, can be transported between facilities or to consumers by Ships/Vessels, Special Trucks and pipelines.
Ships can be used to transport both natural gas in its compressed state (compressed natural gas CNG) and its liquefied state (liquefied natural gas (LNG).
However, due to cost implications, transporting CNG by Ship is not as popular as transporting LNG by ship.
Ships are mostly used to transport a large volume of liquefied gas (LNG) over a long distance, especially in the absence of pipelines. Natural gas cannot be used in its liquid state, so the liquefied gas is converted back into a gaseous state at its destination. The liquefied gas is fed into a regasification facility installed on the ship or facility nearby. The regasification process converts the liquefied gas to a gaseous state before the gas is transported by pipelines or trucks to end-users.
This entails transporting Natural Gas, either in the liquid or gaseous state, on roads using special trucks. This method of transportation is suitable for transporting a small volume of gas over a short distance compared to transporting gas using Vessels/Ships and pipelines. Special-purpose pressure vessels (ISO containers/special tubes) mounted on trucks convey gas to end-user facilities.
When gas is transported in a liquefied state, the storage vessel should be able to maintain the LNG temperature below the phase change temperature of natural gas.
When gas is transported by storage tubes mounted on trucks, it is transported in a compressed state (at high pressure and low temperature) called Compressed Natural Gas (CNG). CNG can be transported at pressures over 200 bar, so the storage tubes are high-strength steel capable of safely holding the gas.
Gas compression is performed in a facility that receives natural gas from pipelines. The gas is fed into a drying unit, where water vapour is removed.
From the dryer, the gas is fed into a compressor or series of compressors, where it is compressed, thus increasing its pressure.
The gas exits the compressor into storage cylinders connected to the dispensing unit. The dispensing unit discharges the gas from the storage cylinders into storage tubes for onward transportation to the customer’s facility.
A Gas Chiller unit is incorporated into the system downstream of the compressor. This primarily ensures a larger volume of gas is stored and dispensed.
At the customer facility, the compressed natural gas is fed into a facility unit that depressurises the gas and increases the temperature to a value that gas consumers can handle. The CNG is fed into a heat exchanger unit where the gas temperature gradually increases. The gas exits the exchanger and enters a pressure reduction and metering unit, where the gas pressure is reduced before entering the consumer facility.
GNSL, a subsidiary of Axxela Group, currently operates a 5.2MMSCFD Compressed Natural Gas (CNG) Mother Station in Lagos, Nigeria. At the mother station, natural gas is compressed into mobile tubes and transported by trucks for onward delivery to customers’ locations. (https://axxelagroup.com/operations/gas-network-services-limited/).

Figure 1: Compressed Natural Gas Tubes on Trucks
This is the most efficient and safest means of transporting Natural gas.
Some of the advantages of using the pipeline to transport gas are
Several transmission and distribution pipelines convey natural gas within cities and countries to other countries or within cities.
The West Africa Gas Pipeline (WAGP), operated by West Africa Gas Pipeline Company (WAPCo), transports gas from Nigeria to three West African countries (the Benin Republic, Togo and Ghana. The pipeline receives gas from the Escravos – Lagos Pipeline at the Nigeria Gas Company’s Itoki Natural Gas Export Terminal in Nigeria. The West Africa Gas Pipeline is designed to deliver a volume of 170MMscfd initially and, in later stages, a capacity of 460MMscfd to gas users. (https://www.wagpco.com/the-project/wapco-pipeline)
Gaslink (GNL) is a subsidiary of Axxela Group. In conjunction with the Nigerian Gas Marketing Company (NGMC), it operates a 100 km-long gas distribution pipeline network in Lagos, Nigeria, with a capacity of 140MMSCFD and peak utilisation of about 70MMSCFD. (https://axxelagroup.com/operations/gaslink-nigeria-limited/).
There are several pipelines transporting gas across various European and American countries.
A gas pipeline system connects various facilities, equipment, and fittings to deliver gas efficiently to end-users.
Pipelines may be categorised into any of the following.
Flowlines transport fluid (gas or liquid) from wells to storage or processing facilities. The processing facility may be used for preliminary processing of the fluid. The fluid transported by the flowline is not pure. Therefore, the flowline must be designed to handle the fluid in its natural state. Flowlines are usually small in diameter (2” to 4”); however, depending on the production capacity of the well, the size may be larger.

Figure 2: Well Head with Connected Dual Flowlines
These pipelines transport fluids from processing and storage facilities to a common trunk pipeline. The trunk lines may be larger than the flowlines.
As defined in ASME B31.8 section 803.2, A transmission line is a segment of pipeline installed in a transmission system or between storage fields. While a transmission system is one or more segments of a pipeline, usually interconnected to form a network that transports gas from a gathering system, the outlet of a gas processing plant, or a storage field to a high- or low-pressure distribution system, a large-volume customer, or another storage field.
According to ASME B31.8 section 803.3, a gas main or distribution main is a segment of pipeline in a distribution system installed to convey gas to individual service lines or other mains. Distribution pipelines convey gas to power generating facilities, factories, industries, residential apartments, gas dispensing stations, etc.
A gas pipeline distribution system may have various distribution lines originating from the city gate, all connected to a distribution manifold. Depending on the project design philosophy, the pipeline could be made of steel pipes, ductile iron pipes, plastic pipes, or a combination of different materials.

A gas distribution system aggregates facilities, equipment, and fittings installed to transport and distribute gas efficiently to end-users.
A gas distribution system may contain any of the under-listed components.
The city gate interfaces the Transmission line and the gas distribution system. The equipment listed below may be installed at a city gate.
The distribution manifold, mostly installed above ground, splits the gas stream into different distribution lines. The city gate is a central location where different distribution lines originate; these lines may be of different sizes depending on gas demand on each axis of the distribution network. All the distribution lines are tied into a manifold at the City gate. There are isolation valves installed on each line connected to the manifold; the function of the valve is to allow for the shutdown of any of the lines independently from the other lines. The manifold should be appropriately sized to deliver the gas current end users require and envisaged future customers.
Pressure reduction units are installed on the gas distribution network to regulate the gas pressure to a level that the downstream distribution pipeline, inline components, and gas consumers can handle. A gas meter is installed within the PRMS skid to measure the quantity of gas flowing through the equipment.
PRMS is designed to suit customer gas requirements and, per the project design philosophy, to suit the pressure range it will handle. Usually, a pressure reduction skid is installed at the city gate to reduce the transmission line pressure to a set value. The reduced pressure may not be the pressure required by the customers but the pressure required to convey the gas along with the network. Other pressure reduction skids may be installed within the network, called “District Pressure Reduction and metering skids” (DPRMS). The DPRMS further reduces the pressure of the line to a level that can be handled by the “Customer Pressure Reduction and Metering Skid (CPRMS)”. The CPRMS is installed on the customer service line, preferably at the customer’s facility before the gas turbine/generator. The CPRMS reduces the pressure of the gas supplied from the main distribution line to the required pressure range required by the customer. Most gas generators’ intake pressure is less than 2 bar and, in some cases, as low as 0.2 bar. Therefore, the CPRMS installed on line-conveying gas to generators should be designed to regulate the pressure to suit the generator gas pressure requirements.
It should be noted that reducing the pressure at the city gate is necessary because high pressure implies higher pipeline wall thickness and higher pressure class of inline components, hence higher material and installation costs. It should also be noted that the reduced pressure should satisfy the hydraulic requirements to convey gas conveniently to all customers; hence, rigorous hydraulic analysis is performed to determine the pressure required along the pipeline and at the customer’s location.

Figure 3: Installed Pressure Reduction and Metering Skid
Pressure indicators should be installed upstream and downstream of the pressure reduction and metering skid at the city gate and customer’s location, all lines originating from the city gate (distribution manifold). If the system is automated, pressure transmitters may be used to transmit the measured field pressure to a control room.
Temperature indicators should be installed inline on the distribution manifold at the city gate. The temperature data may be read on the field instrument display or transmitted to a control room in an automated system.
A Gas Scrubber removes liquid droplets or traces of liquid droplets from gas streams to protect equipment installed downstream of the scrubber from damage and failure. A natural gas scrubber system uses filters, coalescers, mesh pads, and other devices to remove pollutants from the gas stream.
Gas scrubbers are installed at the inlet of every generator/turbine to remove liquid droplets. Depending on the gas characteristics, they may also be installed at the city gate or in line with the pipeline network.

Figure 4: Gas Scrubber Installed at the Inlet of a Generator

Figure 5: Gas Scrubber Installed Inline a Pipeline
Natural gas is odourless and very explosive, so it is important to put in place a means of detecting gas leakages. Gas odourisation is mandatory for Natural gas distribution systems, as stated in section 856.1 of ASME B31.8. A method of detecting leaks in the gas pipeline is to inject a strong-smelling substance metered appropriately into the gas. Mercaptan compounds are popularly used for odorizing natural gas.
A gas chromatograph is installed at the city gate to analyse the components of the natural gas. This validates the gas composition in the Gas Sales and Purchase Agreement (GSPA). The gas chromatograph is connected to the gas pipeline via small diameter stainless or other material pipes. The Chromatograph takes gas from the pipeline, analyses the gas, and separates the gas into various components by sending the gas through a chromatographic channel. The devices calculate the composition of each component and send the report to a display system.

Figure 6: Installed Rosemount Gas Chromatograph
A fire and gas detection system shall be installed at the city gate. The field instruments detect gas leakages by measuring the gas concentration in the atmosphere. Installed temperature sensors shall detect any possible fire. When facilities are automated, the fire detection system should trigger the shutdown of the gas network and activate the firefighting system.
Spur lines are branches from the main distribution line transporting gas to each consumer. These lines may be made of carbon steel, Plastic materials, Ductile iron, etc. Spur lines are low-pressure because the pressure required by gas consumers is significantly lower than the pressure on the distribution main. When the pressure delivered via the spur line to the gas consumption is higher than required, a pressure regulator shall be installed at the inlet connection to the consumer facility.
A gas compressor facility shall be installed along the pipeline if the pipeline pressure cannot transport the gas to the customer’s location, satisfying the pressure required by the customer. The actual location of the compressor station shall be specified based on the hydraulic analysis. A gas compression unit can also be installed at the city gate to increase the gas pressure in the pipeline.
A typical compressor station contains:
Compressors are categorised into two groups: positive displacement compressors and dynamic compressors.
In positive displacement compressors, the inlet volume of natural gas is confined in a given space (cylinder) and compressed by reducing this confined space or gas volume. The compressed gas is discharged into the pipeline at higher pressure. The most common examples of positive displacement compressors are reciprocating or piston compressors and screw compressors.
Dynamic compressors increase gas momentum as it flows through them and convert the energy into pressure. The major types of dynamic compressors are centrifugal and axial compressors.
For adequate isolation, maintenance or repair purposes, blowdown/venting and purging processes and valves are provided to operate a gas distribution pipeline system. Valves may be welded, flanged or threaded depending on pressure class. However, welded valves provide a better leak-tight system. All valves installed in the gas distribution system shall conform to any of the codes stated in section 831.1 of ASME B31.8 or as per other applicable codes and standards. All valves shall be installed in an easily accessible location and accordance with codes and standards such as ASME B31.8. Any of the following valves may be installed on the gas distribution networks.
Depending on the project design philosophy, emergency shut-down valves (ESDV)/block valves shall be installed on the transmission line conveying gas to the city gate or inlet distribution lines. The valve may be installed above or below ground depending on the location of the valve and design requirements. The ESDV provide positive isolation of the city gate from unforeseen operating conditions.
The use of an automatic shutdown valve is not mandatory, as stated in section 846.2 of ASME B31.8; however, when automatic shutdown valves are used, the valves should be fitted with appropriate instrumentation and control system to trigger the valve to close when:

Figure 7: Emergency Shutdown Valve
Sectionalisation or isolation valves should be installed along the pipeline length in the region where major concerns (populated areas, etc.) have been identified, at spur lines branch off from the distribution main, before pressure reduction and metering equipment. Sectionalisation valves shall be installed as per the requirement of section 846 of ASME B31.8 or other applicable codes and standards. This arrangement is useful in limiting gas losses during pipeline leakage or rupture and maintenance of any section of the pipeline. The arrangement should be such that a few customers are cut off from the gas supply during maintenance activities.
The sectionalisation valves may be welded directly to the pipeline to minimise the possibility of gas leakage from flange connections or threaded joints. They may be manually operated, or automatic actuation may be provided.
The sectionalisation valve arrangement may be installed below, above, or in a vault. In any of the above-mentioned installation positions, all valve operators must be easily accessible and protected from damage. When the valve arrangements are installed in underground vaults, the vaults shall be designed under section 847 of ASME B31.8.
Sectionalisation point arrangement may consist of the following:
These valves shall be the same size as the main distribution pipeline. They may be directly welded to the pipeline to minimize the possibility of leakage in the pipeline system or flanged. The valve shall be equipped with appropriate instrumentation for an automated system to facilitate remote operation.
The bypass arrangement may include two ball valves (for shutting off) and two globe valves (for throttling). These shall be used when maintenance or repairs are needed in any section of the pipeline. They are located to depressurize the pipeline segments and bring them online during the start-up process after maintenance or repair of a section of the pipeline.
Vent lines are primarily used for venting and blowdown purposes in the pipeline operation. They are also used to depressurize any section of the line where maintenance is required. Vent lines shall be appropriately located away from public places. A ball valve should be installed at the tail of the line to enable tight shut-off. A permanent vent system may be installed, or a tie-in provision for a temporary mobile vent system may be provided.
Check valves shall be installed downstream of pressure reduction and the metering system, as stated in ASME B31.8 standard section 848.3. The check valves protect the PRMS from back pressure if lower pressure exists upstream due to pipeline failure or any other event.
All steel pipes buried underground must be externally coated to prevent external corrosion. Buried gas distribution lines may be externally coated with 3 Layer Polyethylene Coating (3LPE), any other material following ISO 21809-1 or other codes and standards. However, in many cases, damaged external coating leads to severe pipeline corrosion. In conjunction with 3LPE protection, all underground steel pipelines shall be cathodically protected. The essence of the protection is to eliminate corrosion. Impressed current is the preferred means of protecting buried underground pipelines.
Impressed current entails feeding current generated by a Transformer Rectifier Unit (TRU) connected to an anode ground bed into the buried pipeline. The current is used against the corrosion process, thereby protecting the pipeline. Typical components of a cathodic protection system include a Transformer Rectifier Unit, anode ground bed, cathodic protection cables, cathodic protection test points installed, and the entire steel pipeline network.

Figure 8: Installed Transformer Rectifier Unit
The main function of an isolation joint or flange insulation kit is to isolate various sections of a gas distribution system electrically. The requirement for electrical isolation is well spelt out in section 861.1.3 of ASME B31.8.
The above-ground facilities, e.g., the city gate and customer connections, are externally painted and hence externally protected from corrosion. It is imperative to isolate the underground section protected by CP (Cathodic Protection) and external coating from the above-ground section. This is achieved by installing Isolation joints or flange insulation kits at the transition point from above ground to below ground.
Pipeline isolation joints/ flanges shall also be installed at the identified location to minimise or eliminate current leakages to third-party facilities that may be directly or indirectly connected to the distribution network. Isolation joints may be installed at locations where the pipeline is installed parallel to the Overhead electrical transmission line.
It should be noted that current leakages only occur in the metal pipeline section; non-metallic sections of the gas distribution system do not require the installation of an Isolation joint.

Figure 9: Installed Pipeline Isolation Joints
Depending on the level of automation desired, a gas distribution system may be fully automated or semi-automated.
The control station’s function is to oversee the entire pipeline network and all connected equipment. It receives signals from field instruments such as pressure indicators and transmitters, temperature indicators and transmitters, flow measurement instruments, etc. The control station may also close any valve on the gas distribution pipeline.
During the various design stages of a gas distribution project (conceptualisation to detailed design), various considerations, including gas consumers, gas volume, material selection, pipeline routes, and line size, shall be analysed.
Gas consumers are the key factor in planning a gas distribution pipeline system.
Before conceptualizing a gas pipeline, consumers must be available to use the gas to transport. The number of customers, their locations, the quantity of gas to be purchased by all customers, and envisaged future customers must be analysed to determine the project’s feasibility.
This is an important factor to consider when planning a gas distribution network. The gas volume has to be checked from both the demand and supply end. After identifying all the customers, the volume of gas required by all customers is summed. The total gas available is checked against the total gas demand. It should be noted that having one high-volume gas consumer (e.g., power generating plants) is better than having many customers with low-volume consumption.
This key factor should be analysed when planning a gas distribution network. Customers’ gas requirements, such as delivery pressure and temperature, vary because the gas will be utilised for various purposes. The pressure required by gas engines varies; therefore, the pressure reduction unit installed on each service line may differ. This implies that the cost of PRMS on the distribution network will vary amongst customers.
This entails determining process parameters along with the distribution network. The preliminary analysis utilises assumed data, including route elevation, fittings, etc.; however, as the project progresses from concept studies to detailed design, actual survey data shall be used for hydraulic analysis. Process hydraulic simulation is critical because the simulation results show the gas characteristics (pressure and temperature) at each customer location and the network. The simulated pressure at the customer location will specify the PRMS to be installed if required.
This is critical when planning a gas distribution network. Usually, the network should be designed so that a minimal number of customers are affected during maintenance activities. This is usually achieved by correctly locating isolation valves at strategic locations.
A process engineer performs line sizing. Line sizing entails determining the optimum pipe size that can convey the desired volume of gas to the customers. Line size shall be considered in the future expansion of the gas distribution network. It is critical to properly size the line, especially when future customers are envisaged. This ensures that the line can convey the quantity of gas required by all customers.
The city gate’s location is key to any gas distribution network. The city gate should be situated so the transmission line and distribution network length are significantly reduced. While siting the city gate, the location of gas sources such as processing facilities or export pipelines should be properly analysed. A detailed hydraulic analysis is required to check gas properties (pressure, temperature) upstream and downstream of the city gate.
The pipeline is made up of joined pipes and other inline components. As stated in section 812 of ASME B31.8, the pipeline can be made of steel materials, ductile iron materials, plastic materials or a combination of materials. However, most of the gas distribution pipelines are made of steel pipes.
Material selection is very key when planning a gas distribution network. Steel pipes are more susceptible to corrosion than ductile iron and plastic pipes. Plastic pipes do not corrode; however, they have the lowest strength compared to steel and ductile iron pipes. Ductile iron has low weldability compared to steel pipes, necessitating different joining methods. Therefore, when selecting materials for a gas distribution network, the advantages and limitations of any material should be examined carefully.
Steel pipes manufactured according to the following standards—API 5L, ASTM A53/A53M, ASTM A106/A106M, and ASTM A134—and other standards stated in section 814.1.1 may be used for the pipelines.
As stated in section 14.1.2 of ASME B31.8, ductile iron pipes manufactured following ANSI A21.52, such as those centrifugally cast for gas, may be used in a gas pipeline.
Section 814.3 section of ASME B31.8 permits the use of plastic pipes. Plastic pipes and components manufactured following any of the under-listed standards may be used.
Polyethene Pipes manufactured according to the D2513 standard (Polyethylene (PE) Gas Pressure Pipe, Tubing, and Fittings) may be used.
Polyamide-11 (PA-11) pipes manufactured according to ASTM D2517 (Polyethylene (PE) Gas Pressure Pipe, Tubing, and Fittings) and ASTM D2517 Reinforced Epoxy Resin Gas Pressure Pipe and Fittings may be used in the gas distribution network.
Thermoplastic pipe, tubing, fittings, and cement conforming to ASTM D2513 may be used. However, they shall be produced following the in-plant quality control program recommended in Annex A3 of the specification.
The distribution network shall be routed so that gas can be economically and efficiently transported to gas consumers. The pipeline shall be routed so that it is close to consumers. The routing shall also take into consideration future customers.
Permitting is an essential factor while planning a gas distribution pipeline. Permitting procedures vary across countries. The permit is the certifying document showing that a pipeline can be installed in the designed route as per the specified standard. For example, in Nigeria, pipeline permitting is performed by the Department of Petroleum Resources (DPR). The procedure is performed in adherence to the Oil Pipeline Act.
Before construction activities, all permits from government agencies, including the Ministry of Transportation (for pipeline road crossings and railway crossings), waterways (for pipeline river crossings), etc., shall be obtained.
When planning a gas distribution network, a critical analysis of the fittings will be performed. Some of the fittings’ requirement is explained below:
Bends
Specified pipeline bends shall meet the pressure, temperature, thickness and bend requirements.
The main distribution line may be pigged depending on client and code requirements. When lines are to be pigged, all bends shall meet the requirement of the proposed pigging tools. Some pigging tools require 5D bends to pass the tool easily; therefore, the bends must satisfy the 5D bend radius.
Barred Tee
Barred tees are used on peggable main lines. The specified barred tee shall meet the temperature, pressure, and pigging requirements. The barred tee shall be installed at all branches from the mainline to ensure that the pigging tool is not in stock at branch connections.
Flanges
Flanges are key connecting elements in a gas distribution network. They are the weakest link where gas leakages can occur. The specified flange class shall meet the line’s pressure and temperature requirements.
Pipelines transporting gas should be buried at an appropriate depth per design codes and standards, such as section 841.1.11 of ASME B31.8. Also, local guidelines are mandatory and supersede any international standard requirement. The actual pipeline burial depth shall be decided after critically examining the pipeline route, considering pipeline safety, and other considerations.
Pipeline integrity assessment ensures that the pipeline is operated safely. The envisaged assessment method shall be analysed during the project’s conceptual stage. Several integrity assessment methods exist, such as ultrasonic testing, pigging with intelligent tools, etc.
Pipelines planned for pigging shall have all fittings and valves satisfying the pigging requirements.
A proper cost estimate shall be performed during the design of a gas distribution system to determine the project’s feasibility. The capital expenditure (CAPEX) and operating expenditure (OPEX) shall be analysed to determine if the project is feasible. CAPEX is a category of expenses that results from the project’s design stage to the commissioning stage. At the same time, operating expenditures cover the cost incurred in running the gas distribution system.
Natural gas can be transported in its gaseous state (NG or CNG) or liquid state (LNG) by ocean vessels, Ships, Special Tubes, Pressure Vessels mounted on Trucks, and pipelines.
Selecting a means of transporting gas and the state of transporting the gas require critical evaluation of available transportation infrastructure, the quantity of gas required by end-users, and the total CAPEX and OPEX of the project.
ASME B31.8 – 2016: Gas Transmission and Distribution Piping Systems
ISO 21809-1: Petroleum and natural gas industries – External coatings for buried or submerged pipelines used in pipeline transportation systems – Part 1: Polyolefin coatings (3-layer PE and 3-layer PP).
West Africa Gas Pipeline: https://www.wagpco.com/the-project/wapco-pipeline
Axxela Group: https://axxelagroup.com/operations/gaslink-nigeria-limited/
Axxela Group: https://axxelagroup.com/operations/gas-network-services-limited/
Whether remote taiga, barren desert, on the high-elevation mountainside, or deep ocean, the most impressive and difficult production projects undertaken in today’s industries are those which take place in remote environments. These projects often require the skills of dozens of teams who draw materials and expertise from around the world. One team or technology out of place during this process can throw the entire symphony into disarray, potentially increasing the cost of capital projects by millions of dollars, delaying project completion, or precipitating critical failure.
Today’s complex operations could not be accomplished without the expert coordination of these teams combined with remarkable technologies which increase the effectiveness and efficiency of these operations at bounding rates. Remote drilling operations have long been carried out at phenomenal risk and expense to companies involved. Present-day operations mitigate many of the risks inherent in these projects through several means, including new materials, advanced technologies, and improved project management processes.
Remote drilling and dewatering efforts are increasingly attractive solutions for several industries, mining, perhaps, chief among them. It is an incredible feat of modern engineering to meet the needs of projects which require high-tech drilling rigs in difficult to access environments. Secured on-site, these portable drilling rigs use advanced Geosteering techniques to remove water from the project site, often a construction site or mine shaft.
Drilling operations often take place in environments that have at least minor infrastructural development. However, exploration efforts around the globe have uncovered vast deposits of oil and natural gas in remote, usually challenging, environments. Producing natural resources from these locations has long remained a prohibitively expensive possibility. Today’s technology provides dozens of solutions to the problems faced by producers in the mining and energy sectors. When properly designed and deployed, modern drilling rigs, measurement technologies, and drilling techniques allow for the exploration and production of minerals and other valuable resources. Harsh environments that require unique drilling rigs include:
Innovations within the drilling and exploration disciplines have brought these remote locations from the frontier closer to the mainstream. Previously, resources in remote environments were largely inaccessible, even if their presence could be accurately determined. Early mobile drilling platforms paved the way to exploration in harsh environments. These operations were often inefficient. The risk involved in undertaking a remote exploration or drilling project was dramatically increased when compared to typical projects.
The earliest remote location operations sometimes saw entire projects abandoned for a near-total loss. When the disaster was warded off, early projects such as these were costly and inefficient, supplying fuel to continue operations could single-handedly create a net loss for a project. Subsequent decades resolved many of these issues.
Today’s exploration and drilling techniques effectively allow producers to discover and access vast amounts of higher quality resources in a safer, more effective manner. Once discovered, the application of advanced drilling and well construction methods develop wells which produce significantly greater quantities of oil and natural gas with less risk to both crew and environment.
Today’s remote location exploration and drilling projects benefit from an array of technologies. The overall effect of these benefits allows producers to tap into vast reserves of high-quality minerals and energy resources.
Drilling in remote locations provides several key challenges to expert teams of explorers and producers. It is the mastery of these challenges which makes remote location drilling possible. Several critical developments that make drilling in remote locations viable include:
A host of vital improvements have led to the economic development of resources which would have been far too costly in the recent past to produce. Once reservoirs or gas fields are located and mineral rights acquired, well pads are constructed. These drilling sites are considerably more feasible for remote location drilling. Multiple well paths can easily be drilled from a single wellhead and drilling rigs can be relocated around the well pad with remarkable ease.
Today’s well pads require fewer crew members to operate effectively and make use of advanced models which track the wellbore in real-time. Drilling adjustments are made by a single operator with a screen and joystick. Adding and removing drill strings can be entirely automated. Multiple targets, several kilometres below the surface can be accessed along a single Wellpath, furthering the economic efficiency of drilling sites.=
Along with these technological improvements are those related to fueling on-site operations with highly efficient and much cleaner natural gas. High-horsepower diesel engines are frequently fitted with bi-fuel systems, while dedicated natural gas engines see increasing use. Drilling rigs are routinely fueled by field gas, pipeline quality gas, CNG, or LNG.
Modular systems for transport and vaporization are matured in development and widely available. These fuel systems massively reduce emissions and provide significant cost reduction for drilling rigs. The rapidly improving availability of these fueling solutions only increases producers’ ability to drill in remote environments as though connected to large, efficient infrastructures.
Resources accessed by drilling are sometimes found with liquids that can damage equipment, increase on-site risk, and prevent teams from reaching project production goals. Dewatering is the process which removes liquids from these environments. Commercial dewatering requires expertise in designing, installing, and maintaining water control systems. Dewatering efforts must be tailored to the individual project requirements if they are to remain cost-effective and prevent budget changes or schedule delays. Dewatering often takes the following forms:
Groundwater control and high-wall stability are among the most prominent uses for dewatering operations. Dewatering is particularly critical to the planning and development of mining operations. Compliance with local and international laws often dictate some dewatering requirements for mines. Safety requirements for mining crews mandate reliable, effective dewatering or water control systems completed with ISO or high standards of certification.
Large, open-pit, mines may run into groundwater as the mine grows in size and depth. The inflow of these waters holds the potential to disrupt mining operations. Typically, this takes the form of delaying production and damaging overall project production goals. Wet mining, enduring this groundwater inflow, can easily cost tens of millions of dollars in a single year. Avoiding the delay in production is important yet risks to onsite crew and equipment persist if dewatering remains unaddressed.
Continuous mining operations may require large diameter wells to pump water out of mine pits. Large diameter wellbore is often highly technical. Various ground conditions, lower water tables, fractures, and other considerations must be accounted for. Large diameter wells can be significantly more difficult to achieve in remote drilling environments. Accounting for the difficulties, this type of dewatering is necessary for many projects to maintain production goals.
Custom designed drilling rigs are frequently used in such circumstances. This aspect of drilling and dewatering is critical to most operations. Drilling rigs represent one of the most significant costs in mining or oil and natural gas development. Budget often determines the available rigs, followed by rig depth rating and operating parameters. With the right expertise and rig selection, drilling large diameter wells for dewatering becomes an option for water control.
Water control methods are selected and designed on a case by case basis. Site requirements and budget generally dictate the most effective method for controlling water tables. Construction projects, mining operations, aquifer testing, and many other environments create unique constraints for designers to consider. Each of the following methods provides dewatering and may be used in conjunction to continually serve that end.
Deep wells are most commonly used in excavations where drawdown is required below 6 meters and soil permeability is moderate or high. Certain conditions may call for the installation of deep wells to underdrain less permeable strata.
Multiple deep wells are usually installed in an array, internally or externally controlling groundwater. These arrays pair with physical cut-off walls such as a diaphragm wall, secant-pile, or sheet-pile. Deep wells consist of a borehole, slotted screen, an annular filter pack through the stratum. A submersible electric pump is installed near the base of the well within the liner. The pump is connected via the riser pipe to the surface. Water is then pumped into a header main before it is discharged or recharged.
A hydraulic gradient is formed as water is pumped from the deep well, resulting in a cone of depression forming around the well. Little to no water remains within the pore spaces in the surrounding soil. Drilling deep wells are accomplished using either cable or rotary methods, most often resulting in a 250-300mm bore. Some ground such as chalk or sandstone may utilize wells that feature an open-hole section.
Where soil permeability is low the deep well may be sealed and a vacuum applied to increase well yield. This method can dramatically improve product rates for deep wells. Depths exceeding 40m are much more efficient when using vacuums than ejectors. Deep wells may be created to recharge water back into the ground using recharge or reinjection wells. These wells are similar in overall design to a deep well but serve the narrow purpose of recharging water into a different stratum.
Low permeability soils such as fine sand or silt are best dewatered using ejectors. Ejector wells are most common up to depths of 40m, where vacuum deep wells perform more efficiently. Occupying a unique position in the dewatering toolkit, ejectors operate where pumping levels are deeper than suitable for well points and where well yields are too minimal to justify using submersible electric pumps.
Ejector wells are drilled and installed like deep wells yet differ in the extraction method. Ejectors are designed to pump water and air mixtures without issue. Submersible pumps attempting to pump water and air mixtures can easily burn out. Sealing the borehole on an ejector well creates a vacuum during the pumping action, which in turn improves gravity drainage towards the well.
These well systems use both a high-pressure supply and low-pressure return header main which follows the line of wells. Site conditions may require a concentric or double pipe ejector system to provide the optimal solution. Ejector wells typically require a more experienced crew to operate than deep well or wellpoint systems. They may also require more regular maintenance than other water control systems.
Projects that benefit from relatively shallow, linear configurations such as railways or long and narrow excavations are more likely to use horizontal dewatering methods. Typically, drainage lines are 80 to 100mm in diameter and up to 6 meters in depth, depending on what the site requires. Drainage trenches are excavated using a specialized trenching machine which uses rotary cutting chains to create trenches of appropriate depth and width.
Drainage lines are installed along the bottom of the trench as it is excavated. Once installed, the trenches are backfilled. Aquifers on site with low permeability can use filter gravel for backfill in place of soil to increase drainage capacity. The installed drainage lines are connected to a vacuum piston pump. The pump creates a negative pressure gradient which is necessary for water transfer. Collected groundwater is transported through the pump to an outlet line. Water is further routed to the designated discharge point.
Horizontal dewatering is often less expensive than other means, as less crew are required to install this water control system. Horizontal dewatering systems may be used less in certain environments. This is due to soil profiles being less suitable for this dewatering method. Across Europe, this method is nearly universal in its association with pipeline projects. Despite soil conditions in some locations, horizontal dewatering could still provide benefits.
Wells designed to relieve pressure (sometimes called bleed wells) is a passive well designed to reduce water pressures in certain conditions. Confined aquifers or stratified ground near or beneath excavations are common circumstances where they are installed. Excavations made into the soil with low permeability above a confined aquifer often require relief wells.
In this frequently experienced scenario, the confined aquifer exerts upward pore water pressure, which destabilizes the excavation site. The whole site may heave upward due to the weight and shear strength of rock between the excavation base and the aquifer cannot balance the uplift force created from the confined aquifer. Relief wells are designed to resolve this issue. The ideal solution is a relief well which allows water to seep from the confined aquifer into the excavation.
Relief wells are drilled within a grid pattern on the excavation site. Wells must be installed before the site has reached below the piezometric level in the aquifer. As excavations reach below the piezometric level, water will overflow from the wells. This relieves pore water pressures and stabilizes the site. As water flows from relief wells, sump pumping is employed to transport it to a discharge area. Drainage blankets or drain networks may be installed to direct water to the sumps, which will prevent ponding in the excavation.
Because these wells are not directly pumped, they are classified as passive dewatering systems. Relief well systems require the indirect sump pumps within the excavation to adequately provide water control. This dewatering method requires installation along the pathways which facilitate ‘bleed’ from the aquifer. Installing relief wells in this manner ensures groundwater heads drive flow rather than pumping systems.
Most groundwater control systems use relief wells of large diameter, ranging from 100mm to 450mm, which are formed by drilling or jetting. These relief wells may be backfilled with sand or gravel and feature well screens. Smaller diameter drains may be installed for soil consolidation purposes, but these differ significantly from passive relief wells.
Relief wells are advantageous for several key reasons. They are inexpensive and simple. Many relief wells are simple, backfilled boreholes, which may use perforated well screens. Because relief wells are indirectly pumped, a large diameter borehole is unnecessary. This reduces drilling and installation cost. The sump pumps used in relief wells are more durable and widely available than their submersible, electric counterparts used in deep wells and other dewatering methods.
Another advantage of passive relief wells is their ability to cope with extremely low yield wells. Situations such as those involving low permeability stratum are likely to be low yield and cannot be accommodated for by most other means. Submersible pumps in these circumstances can easily burn out. Several passive wells will collect water in excavation sumps, where the sump pumps wait for adequate levels to activate. Borehole pumps are less suited to performing in this manner.
When designing relief well systems, the spacing between wells should be carefully considered. Flow rates may be anticipated to determine the necessary number of relief wells to handle water volume on-site. Sufficient distance between wells is important to observe, conversely, the distance should not be excessive. Wells too widely spaced may not account for variable ground conditions. If installed too far apart the wells may not properly intercept fissures and permeable zones. In these cases, destabilizing pressures could remain, creating heave between relief wells.
Primarily, bleed wells help to stabilize an excavation base. Deep cofferdams or shafts where the excavations are supported by physical cut-off walls or other structures are sites where stability concerns are of high concern. Excavation sites which feature chalk, mudstones, sandstones, and similar rock types or stiff clays are most in need of passive relief well systems. As relief wells overflow into the excavation, proper drainage networks are often necessary. If drainage blankets or drain networks are not installed, soils may be softened by the water, increasing on-site risks. Directing water to the sumps using the above systems is highly recommended.
Long-term pressure relief may be attained by installing relief wells as a part of permanent infrastructure. Sites constructed above confined aquifers may require permanent relief wells installed with screens and casings to allow periodic maintenance. Such wells may encounter waning performance after years of service.
Open-pit mines may sometimes use passive well systems to relieve groundwater pressures beneath the base of the pit. Low permeability layers which exist below the pit may create the need for bleed wells. Sometimes geological structures such as permeable fault zones may be drained into the pit to reduce pore water pressures and depressurize the mine. Pit pumping systems collect and distribute the water to discharge sites or reinjection points.
A wellpoint is an economic and versatile means of water control. Comprised of a small diameter, closely spaced, shallow well, well points are used for onsite dewatering at depths less than 6 meters. Specialized surface vacuum pumps are used to transport groundwater. Wellpoint’s systems work best in stratified and fine-graded soils. Additionally, wellpoint dewatering systems may be quickly installed, making it a versatile solution for sites with rapidly changing conditions.
Each wellpoint uses a small diameter riser pipe with a slotted filter at the base. The wellpoint pump connects to the header main, where it creates a partial vacuum to draw water. Water is then routed to a discharge point. Most sites employ well points around the perimeter of their excavation or parallel to a pipeline trench. These dewatering systems may be installed by auguring, drilling, or jetting.
Once a surface pump is attached to a wellpoint system, vacuum and flow are created. This limits drawdown to 6-meter depth. Stages of well points may then be installed at lower levels for greater depth of dewatering. While well points may typically be regarded as disposable, certain types of well points—such as steel self-jetted well points—may be retrieved and reused after the pumps are shut down. The advantages of wellpoint dewatering systems include:
Drilling a standard vertical well is a firmly established practice. Deviated or horizontal well paths have only become reliable with the advent of measurement while drilling (MWD) and logging while drilling (LWD) technologies which allow operators to place a wellbore precisely along the desired path. Geosteering uses the information gained while drilling to make trajectory adjustments to the well. These adjustments are essential to optimizing the well utility of any deviated well. Geosteering is typically used in:
Geosteering is necessary for deviating a well, cuttings (hydrocarbon shows and readings), the transmission of LWD tools, and determining drilling parameters such as kicks, losses, rate of penetration, and torque. Often more difficult than anticipated, some of the most limiting factors include:
Even with the above limitations, Geosteering remains essential in drilling the most accurate, consistent, and productive well paths. Its proper application can singlehandedly determine whether a well or field is economically viable. Drilling in a permeable formation with tight formations on either side or sometimes in long horizontal wells, the path of least resistance may be followed by the bit. It may move through the most permeable layer, steering between and bouncing off of harder layers.
In the case of mining and hydrocarbon projects, Geosteering is an invaluable practice. Reaching the water-bearing zones for water control may be achieved through Geosteering the desired Wellpath for proper site drainage. Hydrocarbons, particularly those formations along fault lines, inaccessible otherwise, or unconventional require Geosteering techniques to gain access to. Additionally, many if not most drilling sites would be prohibitively expensive without Geosteering, which is an integral part of horizontal drilling and allows producers to create nearly 50 well paths from a single wellhead.
Without today’s Geosteering experts, drilling horizontal wells would not be a viable option for producers. Unconventional resources such as tight gas and shale oil would remain inaccessible. Many of the tools and technologies pioneered for Geosteering are required to produce these unconventional resources. The data gathered from advanced sensors play an instrumental role in advancing production goals for these projects. Typically, this data is interpreted to determine formation properties, directional, and drilling information.
Though attempts were made in the early 20th century, the first viable systems that remarkably improved efforts to measure and log information while the drill was completed in the 1970s. Early technologies included wired pipe, mud pulse, acoustic, and electromagnetic systems. These systems gathered measurement while drilling (MWD) data and saw rapid increases in effectiveness after World War 2.
By the 1980s MWD and logging while drilling (LWD) measurement technology included direction and resistivity, gamma, density, and more. Today’s Geosteering processes use these measurement tools in combination with petro-physicists, geologists, advanced modelling software, seismic data, image logs, MWD, and LWD to precisely and reliably create horizontally deviated wells. The most advanced drilling sites take these technologies to their next logical step: automation.
Today’s data integrated, highly automated, cutting-edge processes allow for the planning and installation of remote drilling sites (remotely operated) which require little to no personnel to function reliably. Despite the dynamic processes involved in on-site operations, these sites have been tested throughout the last decade. Shell Upstream Americas tested pilot systems in the Haynesville Shale in North America early this decade to surprising success. Deployments of this technology, despite the difficulties, have gained significant ground, such as those used in 2018 by Baker Hughes in the Appalachian Basin.
These remote direction drilling facilities promise several benefits over traditional sites, particularly when factored into large scale strategic considerations for producers. The most prominent reasons for pioneering this technology include:
Operationally, it is quite clear that the benefits of operating remote sites have every likelihood of overtaking large crews operating on site. The business case for remote drilling sites became clear as companies realized the need to address the “big crew change,” where an entire generation of oilfield experts would retire without proper replacement from upcoming generations.
Producers determined that leveraging competent and experienced staff over numerous operations would provide the most ideal solution for this situation. Additionally, if their experts could use their skills from a centralized location, several key benefits could be gained, particularly:
While the business and operational case for remote drilling sites have long been established, the technological infrastructure required to remotely operate sites was underdeveloped by the early 2000s, when Shell and others began to experiment with more automated solutions. The Drilling Automation and Remote Technology (DART) centres deployed by Shell in 2010 were a milestone in the development of remotely operated drilling sites whose capabilities included directional drilling as well as data communication and storage through cloud-based systems. The first operations conducted by these remote sites in Eagle Ford Shale benchmarked in the top quartile for performance compared to competitors.
These early experiments with remotely operated sites showed 90% increases interpretation and decision-making speed, allowing near-real-time, proactive Geosteering. This significantly improved wellbore quality, tripping times, and case-running times, producing highly consistent increases in drilling performance. DART operations within Haynesville and Eagle Ford Shale were able to stay within the target zone 100% of the time while drilling directional wells, a feat unaccomplished until DARTs application. DART programs provided a remarkable return on investment to Shell throughout its early trials.
Producers around the globe have adopted many of these automated processes to develop their own remotely operated sites. Most commonly they may be found in harsh environments or locations best suited to their strengths. Remotely operated sites remain a rapidly growing practice that is being adopted for a wider variety of scenarios across industries that use drilling rigs.
Central to many of today’s drilling projects are custom-engineered drilling rigs capable of effective and reliable operation at remotely located sites. These operations, particularly those related to mining and hydrocarbon projects, rely on water control for their effective execution. For these projects to remain commercially viable, skilled geologists and petro-physicists use a broad range of tools and software to precisely guide the wellbore to target zones where they are the most effective and productive.
Though these processes have undergone continual refinement since the early 20th century, the last two decades have dramatically improved the capabilities of drilling rigs. Only recently have producers been able to consistently drill horizontal wells with accuracy and precision. Though applying these techniques to custom-designed or mobile drilling rigs can be demanding. Successfully applied, producers may feasibly access high-quality resources from the most demanding environments.
The most challenging environments present designers with the opportunity to pilot state-of-the-art technology designed to automate drilling sites. These remotely operated sites function with little or no crew. Once established, these remote sites are nearly autonomous, relying on centrally located experts as decision-makers.
Remote drilling sites have been tested in harsh environments with complex on-site requirements. These sites have been largely successful. Data indicates a remarkable improvement in drilling consistency and well production. Such sites provide producers with possible solutions for several key issues facing the rapidly changing, tech-heavy energy industry.
Horizontal Directional Drilling for Oil and Natural Gas
Drilling Rigs, Engines, & Fuels
In March 2011, an earthquake-generated tsunami devastated large lengths of the region’s coast. The disaster caused a meltdown at the Fukushima nuclear power plant, with Japan’s reaction being the shutting down of all of its nuclear reactors. Until then, nuclear supplied nearly one-third of the country’s electricity needs, which had to be taken over by oil and gas generation to sustain the low supply levels. Ironically, the mountainous island nation had few locations for fossil-fuel power plants safe against earthquakes and tsunamis, so this was not a feasible option for the country. Moreover, people don’t want to have a power station in their backyards, and backyards in Japan are small. The country faced clear challenges.

Source: www.eia.gov/

Source: https://politicsofpoverty.oxfamamerica.org/
Closer to home in Africa, power generation is arguably the biggest problem holding the continent back in its quest for growth and development, resulting in a vicious cycle of low investment, little public spending, poor growth, little job creation resulting a low tax base for governments to attract further investment. In general, power generation capacity in Africa is small, and numerous problems are caused by old and ageing infrastructure as well as large maintenance backlogs. These issues continually result in power supply interruptions that damage GDP and hinder economic development. Part of the problem in increasing capacity is time to get power projects producing power; delays in land acquisition, approvals, environmental challenges and a host of others result in low power generation capacity.
With the enormity of its hinterland in the arctic regions under its possession, Russia has been battling with the provision of power in numerous locations where large power plants are either too difficult to build, too expensive or not needed for long periods. Their main objective is the provision of power for oil and gas exploration. Other objectives include the supply of electricity and heat to the most remote regions, with the main objective of supporting growth and sustainable development.

www.wartsilia.com
There are power supply issues in many parts of the world in various contexts. Floating power plants (FPP) offer a means to solve these problems in the first and third worlds. Placed in a marine environment, they don’t need land. They can be plugged into local grids, and from the point of arrival of the FPP at the site, they can provide power within weeks, far quicker than land-based power plants. By their nature, they are temporary and are highly advantageous in instances where short-term demand exists. Cost-benefit analyses work in their favour, but only under very specific circumstances.

www.marketresearchfuture.com
Furthermore, the demand for their services is growing. According to a new report by Market Research Future (MRFR), the global floating power plant market is projected to experience growth at a rate of 10.3% from 2017 to 2023. Factors driving the market demand include rising populations, rapid urbanization, rising demand for uninterrupted power supply, and lack of adequate lands to construct renewable energy plants. They estimate the market size to be USD 1,7 billion by 2023. Today, over 100 FPPs are deployed and operating around the world. The utilization rate of floating power plants is around 95%, with only one or two power barges available in the global market at any time. There is no oversupply of FPP’s, which indicates a potential for profitability from the FPP operator’s business perspective.
The capacity of individual ships and barges ranges from 45MW to 500MW. They can be run off various fuels, including LNG, LPG, diesel, HFO and others, depending on the plant installed onboard. Current designs for new builds include fuels such as petcoke and nuclear fuels. This variation in fuel types makes them ideal to match fuel requirements with the host country’s. Owing to the high demand for low-cost flexibility, floating power plants have seen a resurgence since their early days. Developments on the horizon suggest the future fleet could be far more diverse and include nuclear plants, combined cycle gas turbines, and liquefied natural gas (LNG) facilities. The use of LNG has cost advantages of other heavier fuels and emits fewer greenhouse gasses than coal and heavy oil. This is an advantage for some countries. Some FPP are equipped with fuel storage onboard to maintain generation availability, which is arguably the most important attribute FPPs can have. The power plant would be operated similarly to any land-based combined-cycle generating facility, with onboard operators performing similar functions. The multiple turbines, gas compressors, and transformers built into the design provide a high degree of redundancy, which increases electricity availability. LNG FPs can be coupled with or equipped with onboard FSRUs. FSRUs have serval advantages over land-based regasification and storage facilities, namely faster to market, more flexible, and, In most cases, more cost-efficient. Again, the selection of the right piece of plant is very dependent on the client’s needs and the location. Small FSRUs, suitable for the application of FPP, are becoming more available today.

http://www.cimc-raffles.com
There are several new builds currently underway, a large number of which have nuclear-generating capability. China and Russia seem to be leading the way on the nuclear front. There are fewer new builds with fossil fuel generators. In June 2019, Kawasaki obtained approval in principle from DNV GL a newly developed LNG floating power plant based on its 2018 “Gas Power Plant” rules. Chiyoda is currently offering LNG-powered floating plants in the small-scale range using a Gas/Diesel dual-fuel engines as well as a larger mid-scale Gas Turbine combined cycle. The technology appears then to be improving. Costs for nuclear driven FPPs are in the order of US$250m – US$450m for 50-150MW installed capacity, while costs for fossil fuel-generated FPPs are approximately 50% more expensive.

*variety of sources
In some instances, existing ships are converted into FPPs. There are cost advantages, which are overshadowed by longer construction timeframes. Converting a bulk carrier into a power station is a major undertaking and involves, among other extensive works, placing several generators into the cargo hold. Surveyors verify the conversion process, trials and testing phase, which enables them to deliver certification to applicable classification rules. FPP lifespans are generally between 25 and 50 years, with a payback period of between 4 and 12 years. Financially, they provide reasonable returns to owners. In general, FPP’s are more expensive than other forms of electrical generation, hence cost per kWh is usually not their strong point. However, in certain instances, it is far cheaper than building large power stations in remotely accessed areas, specifically where either short-term or immediate solutions are needed.

www.siemens.com
Where their a long-term demand for a constant power supply, the FPP will be permanently located at one site over usually up to 3-5 years, in these circumstances, the facility will have a power purchase agreement between the FPP owner and the client. FPP owners sometimes rely on the threat of moving their barges to another country as a means of extracting payments from customers who are reluctant to pay, which gives incentives to keep the contract alive for both parties.

www.gastechevent.com
FPPs can be permanently moored alongside wharves, jetties, and quays and, while still being floating vessel, will not move from this location. Such barges are, therefore, exposed to wave movement and potential impact from other vessels. Several studies can be undertaken to determine the movements of the vessels under the wave and current action, as well as the requirements for moorings and the mooring specification. In some instances, special moorings have been created where the FPP is protected from passing marine traffic. An example of a special mooring is where a permanent “wet berth” is created with a locked gate enabling the power barge to be floated into the mooring; a dock is excavated, the barge is floated in and then sealed off from the watercourse, water is pumped out, and the dock is filled to create a permanent land-based generating station, which can be refloated in the future and relocated to another site. The water level within the perimeter is then maintained to protect the barge from fluctuations.

www.engadget.com
The surrounding structure also protects from the impact of other vessels. This setup achieves a more stable operating environment than, say, floating within a harbour basin and eliminates most of the insurance risks of ‘perils of sea or water’. Most FPs in operation today are power barges and, as such, do not have their propulsion systems. These, of course, would have to be towed to the site. The selection of the power plant’s location also has to consider other factors such as fisheries, mariculture, and main shipping lanes.
Rather than providing advantages and disadvantages to support the case for FPPs, decision-making is driven very clearly and simply by one of the following three key requirements:
The case for FPPS seems, therefore, to be a very simple and strong one in the right circumstances. However, in our imperfect world, there are challenges to be overcome:
These challenges have been overcome in each country where FPPs are currently operational. FPPs, therefore, lend themselves to solving several serious problems. The case for FPPs is clear: operators can make profits while countries can obtain solutions to highly specific power supply problems.
Measurement and regulation form the groundwork of business and, more fundamentally, any exchange. Within the oil and gas industry, the foundation of measurement lies in metering and regulator stations. Without measurement or regulation, customers and producers alike would have no basis for conducting business or exchanging goods. As critical mediators from late upstream production to midstream processing and refinement, down to individuals heating their homes and cooking their food, metering and regulating stations must be as accurate and consistent as possible.
If their measurements are inaccurate, tens of millions of USD can be lost annually with as little as 0.1% error. On many pipelines, tens, even hundreds of thousands of dollars would be lost daily.
Since these gateways often handle hundreds of thousands or millions of dollars in hydrocarbon resources daily, their accuracy and reliability are crucial. Expert design and planning are necessary to ensure these elements of exchange and regulation within the supply chain remain intact. The impact of failure, even if the errors are marginal, has dramatic consequences on short—and long-term profits. Legal liabilities, loss of customers, and the resulting publicity would be virtual fallout. Lasting damage would be incurred on the reputations of those involved.
For these reasons, mitigating errors in metering is a priority. As custody exchange success and failure hinge on these metering stations, strict documentation of and adherence to proper standards is just as essential as proper design and maintenance.

Natural gas exploration and production are transporting, refining, storing, marketing, metering, and delivery. Gas gathering systems first separate liquid condensate with separators to produce single-phase gas, which is promptly measured and sorted from condensate. Here, condensate takes a separate journey to another processing facility. This process generates intermediate products (condensates among them) and the finished product of transmission quality natural gas.
Gas is metered again upon exiting the processing facility. Compressors move gas under pressure through pipelines to LNG facilities or midstream facilities and move it toward downstream users. Typically, these compressors are powered by a combustion engine or turbine, using natural gas from the lines as a fuel source.
Pipeline infrastructures that frequently span countries or continents transport the gas further down the supply chain. Intervals of compressors, established roughly 50 miles apart, ensure the continuous transmission of natural gas.
Touching aspects of the upstream and downstream value chain, midstream processes begin to use metering stations for various mid and downstream processes, whether supercooled at an LNG facility or used to power industrial processes, power plants, or serve other ends. Midstream or transmission pipelines are referred to as mains. These mains transmit natural gas at significantly higher pressures than localized downstream areas.
A useful analogy to midstream value chain operations is that of a national interstate system where high rates of speed are permitted for travel. Once an exit is taken, a significant speed (pressure) change and the operating procedure is required. In the case of natural gas transmission, the segue to surface-roads mired in potential hazards. This is where metering stations display their tremendous value in the natural gas supply chain (or interstate system).
Downstream processes (distribution) encompass the end-users of natural gas products closest to the end-user. Distribution pipelines often become smaller and less pressurized as they approach the consumer. As discussed below, a classification of ‘gateway’ or tiered metering and regulator stations awaits the pressurized gas.
The first of these ‘gateway’ metering stations is often called a ‘city gate’ or simply a gate metering station. This station meters and reduces the pressure of transmitted gas from midstream transmission pressure to a more palatable level for high-pressure customer metering stations. These high-pressure metering stations are typically used for custody transfer, power plants, industrial processes, and other large-scale applications.
The design of distribution pipelines begins to differ more significantly the further downstream we follow the process. Distribution lines may change in dimension, materials, elemental exposure, or other ways. Subsequent ‘gateway’ metering and regulator stations are encountered.
Further pressure reductions are made for mid-pressure applications or continuation further downstream. District regulator stations are the final ‘gateway’ meters between consumers and affordable, effective natural gas. Commercial, industrial, and residential customers can use the numerous transmission systems designed to reach them.
Great care and planning are given to each aspect of these value chain phases, yet everywhere you may look, metering and pressure regulator stations provide exact, highly replicable services.

Among the most stringent requirements of any metering station are the measurements for custody transfer. Errors in these measurements can be extremely costly. Most countries strictly regulate fiscal metering. Several industry associations and standards institutes, including the American Gas Institute, American Petroleum Institute, US National Institute for Standards and Technology, and others, are involved in creating and maintaining these requirements.
To obtain these metrics accurately and reliably, master meters on site, parallel meters, flow computers, and other sensors and quality measurements are employed. Eliminating or reducing uncertainty is paramount for collecting this data. Flow provers, metering skids, expert planning, and flow meters are pivotal in reducing measurement uncertainty.
The quality of natural gas can significantly impact the operation of regulating and metering stations. The gas should be pipeline quality and free of most impurities and condensates. Natural gas conditioning is the set of techniques used to remove any remaining or subsequently formed liquids, condensates, or solids from gas flows. Using indirect heaters and separators to achieve and maintain necessary gas temperatures prevents operators from incurring damage to metering and regulator stations.
Accurate and precise, repeatable measurement is the basis of any metering system used in the oil and gas industry. Regardless of the sensor (meter) type, measurement systems are based on mass measurement. Thus, based on the principle of the conservation of mass.
Flow meters also rely on the law of similarity, which is a dynamic and geometric similarity, to minimize the risk of errors between flow meter calibration and field conditions. Violating the law of similarity frequently results in inaccurate measures, which can produce inaccurate measurements and generate loss at facilities.
Flowmeter assemblies are precisely calibrated instruments whose primary device is the flow meter itself. They are ideally comprised of high-performing flow conditioners on upstream pipe sections, flow meters, and subsequent downstream pipe sections.
Secondary devices measure gas composition, pressure, temperature, and other metrics. Auxiliary or tertiary devices are flow computers, SCADA systems, or other components that receive process, and store collected data. Complex, proprietary algorithms are programmed into these auxiliary devices for flow calculation within designated parameters. These devices also provide a detailed data trail that may be audited for analysis.
The primary goal of regulating operations is achieving and maintaining the desired system pressure (control). Each metering station is designed to measure and monitor pressure and flow. Filters, heaters, reducers, regulators, drains (for condensate collection and disposal), storage tanks, and metering skids aid in the pressure-regulating efforts at these stations.
Filter units are designed to sort and remove entrained liquids and solids that form in the natural gas flow stream. They often use cyclonic elements to trap particles and liquids along the sides of pressure vessels designed for holding condensates. These sumps may be emptied as required.
Heaters help prevent the formation of hydrates and liquids during pressure reduction. Indirect gas-fired water bath heaters are designed to safely and efficiently maintain gas temperatures above the dew point while maintaining desired flow rates.
Each regulator system maintains a minimum of two trains of pressure reduction. While one operates, the other stands by as a contingency. Two valves, an active and a monitor valve, each equipped with a controller, operate the valve at predetermined discharge pressure values.
Gate stations mentioned above resemble speed limit signs for interstates, surface roads, and school zones. These stations are designed to regulate pressure-infirm, categorical steps from one pressure to another. Each speed limit, step, or pressure level has distinct operating concerns, often reflected in the changes in pipeline size and materials (metal, plastic, etc.), if not location.
In most instances, city gate stations are among the first pressure reduction and metering stations encountered by natural gas flowing through pipelines. Transmission pipelines frequently operate between 200 and 1,500 pounds per square inch (PSIG). Distribution pipelines operate anywhere from a quarter pound to 200 PSIG, a transition of pressure made by gate stations (city gate stations).
High-pressure customer metering stations operate above 60 PSIG to the required specifications. They are used for custody transfer metering, gas conditioning and treatment, industrial applications, power plants, and other specialized applications.

While city gate metering stations distribute large volumes of natural gas to whole areas or for industrial purposes, town border stations distribute gas to city areas.
These metering and regulator stations operate from 15 PSIG to 60 PSIG on average, though some mid-pressure stations operate from 2 PSIG to 15 PSIG. If odorants are not added before these stations, they are mixed with the natural gas for leak detection purposes.

District regulator stations operate with the least transmission pressures. Typically, these regulator and metering stations function at service levels of pressure or less than 2 PSIG.
Low-pressure metering stations provide natural gas to individual residences or buildings. Natural gas utility companies maintain and operate the supply line to the residential or business meter. Once metered at the residence, the pressure is frequently reduced to less than one-quarter PSIG, allowing easy customer access.

Separators (discussed below) help collect and store liquid hydrocarbons and water within the condensate tank. These tanks are equipped with the necessary safety valves to prevent overpressure. High-level alarms are installed to indicate excessive pressure levels. Condensate tanks may be manually emptied as necessary.
Perhaps underestimated as a form of record-keeping, manual chart recorders are sometimes employed to measure and record pressures and temperature. Often, they are used in conjunction with digital technologies as an inexpensive and valuable addition to record-keeping practices. They serve as a straightforward and reliable means of recording at-a-glance information.
Gas heating systems or heat exchangers indirectly increase the temperature of natural gas. Usually, the gas goes through a filter and is heated before pressure reduction occurs. These systems are designed to keep natural gas above the condensation or dew point to prevent the formation of hydrates due to the Joule-Thompson effect.
Gas-fired water bath heaters are a type of indirect heater used to prevent hydrate formation as pressure drops. Indirect water bath heaters utilize tubular elements immersed in a heated liquid to maintain gas temperatures above the hydrate point.
Electric immersion heaters may serve the same purpose by being placed in smaller gas stream flows within a pressure vessel. Low-input piping may be insulated on the exterior and wrapped with heating tape to prevent condensate formation.
These connections are designed to keep pipeline velocity and noise at desirable levels. As each pipeline requires tailor-made solutions, inlet and outlet connections should be designed around calculated pipe velocities to achieve desired noise levels. Noise regarding metering stations can severely disrupt accurate measurements from some metering devices.
These joints are designed to prevent damage to the metering and regulating stations due to eddy currents. Frequently located at the inlets and outlets of stations.
Emergency shut-down valves (ESD) are designed to isolate the station immediately in case of a high alarm or emergency scenario.
Liquid separation systems filter liquid condensate from the gas stream to accommodate the station’s maximum flow rate. There is often a second, identical filter awaiting deployment, should it become necessary. Manually operated valves are generally used to engage these filters.
Whether automatic or manually operated, valves serve the vital function of opening, obstructing, or sealing passageways. Ball, butterfly, check, diaphragm, gate, globe, and plug valves are all used in various flow resistance environments.
These valves are intended to protect the station from high pressure. Unexpected pressure increases can be cut off to prevent downstream damage. Slam-shut valves may be automatically activated when low-pressure or high-pressure conditions are met.
Relief valves are designed to mitigate internal overpressure. These valves, created with a specific pressure value, prevent excess inlet pressure rise. They are pilot-operated or directly engaged.
Pneumatic logic systems utilize this type of valve for two or three-way switching. This allows the direction of inlet pressure between outlet ports at preset pressure limits.
Though many advanced pressure measuring instruments are available, a pressure gauge is simplest. The Bourdon tube pressure gauge remains the most commonly used. It employs a thin, thin Bourdon tube closed on one end. When pressure is internally applied to the tube, the closed end moves linearly, allowing for measurement. Some of these pressure gauges may reach accuracies of 0.25%.
Regardless of the scale used, many common temperature gauges are available. Among the most frequently used are:
Changes in electrical resistance, volume or pressure of the gas, radiation emissions, and the contraction or expansion of liquids (or metals) are most often used to gauge temperature. Sensor selection will always depend on the unique advantages conferred and constraints levied on operators in a given circumstance. Some stations require the greatest sensitivity levels and can afford the necessary cost to acquire them. Maintenance and power requirements may be weighty choices for another station.

Two standard classifications for flow meters are designated as (energy) additive or extractive. Additive meters are a class of flow meters which supply energy into the gas flow for flow rate measurements. Extractive meters function with energy from the flow stream to determine flow rate measurements. Subsequent flow meter delineations are either inferential or discrete. The former infers flow rate measurements by dynamic properties within the gas flow stream, while the latter separates the flow stream, counting individual portions.
Flow meters are instruments used for measuring the volumetric flow of gas or liquid moving through a pipeline or station. These sensors measure linear and nonlinear mass using different means. Some are ideally suited to high-pressure metering stations, while others function best in low-pressure circumstances. The merit of one meter over another largely depends on the needs of a particular station. However, the performance of a particular flowmeter should be among the primary considerations when choosing which meters to install.
Specializing in direct mass flow measurement, Coriolis flow meters are more than half a century old in the oil and gas industry. Despite their accuracy, early Coriolis meters suffered from vibrations caused by design flaws. The continual refinement of this meter type—a typical sight within the heavily tech-invested oil and gas industry—eliminated these issues. Capable of measuring liquids and gases with high degrees of accuracy, they require less maintenance but command higher initial expenses.
The Coriolis principle measures natural gas by observing the twist created from flow moving through two oscillating tubes. The twist generated varies proportionally to the mass flow rate, which is measured and analyzed to determine a linear flow signal.
Widely regarded as the oldest pressure regulator and metering device—invented by the Romans—the orifice flowmeter is a primary device, further classified as an energy extractive, inferential meter. Appropriate filters, separators, and the like should be installed to mitigate condensate or hydrate interference with flow measurement. Particles, if not properly accounted for, may wear the plate seal rings and edges.
Until recently, orifice flowmeters designed with concentric, flanged, square-edged features were the most widely used primary device upstream of gas processing plants. This is due to their inexpensive nature (both CAPEX and OPEX) and lack of sensitivity to flow composition.
Frequently accompanying secondary devices include:
Commonly used in gas transmission lines, thermal meters are designed to sense the heat dissipation rate within a flowing stream. Once transferred into the stream, the speed at which heat dissipates indicates the composition and temperature of the gas, providing the meter with mass flow data.
Thermal mass flow meters are simple, inexpensive, and low maintenance. They have no moving parts. However, these meters suffer accuracy when the natural gas composition is unknown or varied from what is expected. With proper adjustments, the mass flow may be determined accurately once more.
Turbine flow meters are primary devices composed of bearings, an electronic rotor speed sensor, a flowmeter body, a rotor, and a stator. When lacking a high-performance flow conditioner, they are further defined as energy-extractive, inferential meters. When paired with an adequate flow conditioner, this type of flowmeter is used downstream of gas processing plants (condensate risk). The latter configuration is widely adopted as a primary device.
Mounted within the pipeline, turbine flowmeters combine magnetic sensors and rotor movement to accurately determine volume within gas lines. Magnets on the blades provide external sensors with accurate data in steady flow conditions. These flow meters can provide mass flow data if the gas composition is known.
Their mechanical parts are moderately expensive and require replacement or repair once worn. Turbine flow meters can be adapted for various circumstances, particularly when operating conditions are well accounted for.
Frequently accompanying secondary devices include:
6.1.5 Ultrasonic Flow Meter
This primary device type comprises a flowmeter body, electronics, and transducers. Transit time technology is employed to determine mass volume with ultrasonic flowmeters. Transit times are affected by the turbulent structures within a flowing stream, the flow profile, mean velocity and the speed of sound along the chordal path. Chordal velocity measurements may prove unreliable depending on the path length, transmitted acoustic pulse form, electronic timing and gating performance, the configuration and radial position of the acoustic path, and the calculations involved in reducing measurements to the mean chordal velocity.
Transducers can be mounted externally or internally along transmission lines. Each instalment may further classify this primary device depending on how the transducers are mounted. When internally mounted, ultrasonic flowmeters are considered intruding or non-intruding if the transducer intrudes into the gas flow. Acoustic paths can be arranged in a reflective, non-reflective, or hybrid geometry and vary by commercial designs. Combined with a high-performing flow conditioner, this primary device is considered an energy extractive, inferential flow meter. It is a widely employed inflow stream measurement downstream of natural gas processing facilities.
These secondary devices frequently accompany rotary displacement flow meters:
Due to their use of ultrasonic pulses, outside noise can significantly disrupt accurate metering. Buildup within the pipeline can also interfere with accuracy and are more costly than other meters. Notwithstanding, ultrasonic meters are evaluated as durable and low-maintenance.

6.1.6 Rotary Displacement Flow Meter
The measurement method employed by this primary device requires a particulate filter to maintain flowmeter accuracy. Given enough time, oil deposits may develop an unwanted, accumulated presence, exaggerating measured flow quantities. Exceptionally precise machining of a rotary displacement flow meter is required for optimal performance. Underreporting of flow quantities can occur due to internal friction and slippage.
Proper installation design of rotary displacement flow meters requires considering potential stresses incurred on the primary device caused by connecting piping. If installers fail to account for this, abnormal stresses on the housing of this primary device may develop. Rotary displacement flowmeters are further classified as energy extractive and discrete meters.
Comprised of two lobe impellers rotating in opposite directions, these elements maintain a fixed relationship with one another within the cylindrical housing of the meter. The impellers are held fast by precise timing gears, while the housing maintains flat end plates on both the inlet and outlet. Natural gas flows turn the impellers. As a result, a measurement chamber is created between the cylinder, head plate, and impeller. This primary device is best used in conjunction with electronic impellor sensors to totalize displaced volume most accurately. Combined with a particular filter, this primary device is routinely employed in metering stations found downstream of gas processing facilities.
These secondary devices frequently accompany rotary displacement flow meters:
A host of secondary devices are available in metering and regulator stations. Their principal function is to provide inputs for tertiary devices. Generally, they analyze pressure (differential and static), temperature, gas composition, and other metrics.
Chromatography sensors allow for detailed analysis of gas quality. Sophisticated gas chromatographs greatly aid in measuring calorific value, process control, quality control, and several other important functions.
Modern designs are compact and modular, allowing relatively simple installation at sample points.
Auxiliary devices are electronic devices programmed to calculate flow properly within narrowly defined parameters. They receive information from primary (flow meters) and secondary devices. Flow computers, SCADA systems, and other devices that gather store, and process data are classified as auxiliary devices for metering and regulator stations.
Algorithmic calculations performed by these tertiary components are frequently proprietary by nature, though generally known within the industry. Output signals originating from primary and secondary devices are fed into the algorithms. Auxiliary devices receive these signals as input and address them according to their programming.
An electronic volume corrector (EVC) is an auxiliary device that records signal, pressure, and temperature data from the gas flow. It is employed with the diaphragm, rotary, and turbine meters. Including an EVC increases the accuracy and precision of data gathering beyond what flow meters alone could achieve.
Similar to yet more sensitive than an EVC, flow computers are capable of advanced programming and calculation. They possess various alarm settings, are reprogrammable, and can control odorant injection systems. This power and versatility make them desirable for differential pressure meters (introduced below), as they provide the necessary tracking of multiple flow variables. Though they are undoubtedly more powerful than EVCs, they are infrequently used in hazardous environments.
Supervisory Control and Data Acquisition Systems (SCADA) provide station operators with several advantages. They act as a remote control, data gathering, monitoring, and processing system. Some improvements SCADA systems offer include responding to unexpected events, overseeing operations regardless of location, maximizing resources, monitoring data, and generating reports.
Along the oil and natural gas supply chain, an odorant is added to natural gas, typically as it nears its destination. Natural gas is predominantly odourless until an odorant is incorporated. This practice arose from incidents where gas leaks went undetected, resulting in fires or explosions.
THT (tetrahydrothiophene), mercaptan, or non-sulfur odorants are added for their distinctive smell, resembling certain cooked vegetables (cabbage, leeks, onions).
All pipelines that could exceed their determined maximum allowed operating pressure (MAOP) must have reliving or limiting devices that meet international standards. These regulating devices must meet the load, pressure, and other service condition requirements. Overpressure protection devices must be designed to prevent accidental overpressuring and accurately limit during normal and no-flow conditions.
Metering stations have steadily incorporated new technologies and manufacturing processes throughout the decades. Automated systems, electronic sensors, and data collection were just the beginning. Modular systems, skids, and turnkey projects have become part of developing metering and regulator solutions within the oil and gas value chain.
These systems are continually improving, adopting smarter, more interconnected data analysis—capable of being viewed in real-time and analyzed in depth. The growing interest in Biogenic gas and the ability to effectively meter quality biogas (sans CO2) into distribution networks will promote interest in metering stations that perform this function. Specialized, niche modular metering stations are garnering increased levels of attention as the ability to provide tailor-made solutions is improving within the industry.
Far from simple gateways, metering and regulator stations are at the core of the oil and natural gas sectors. Metering and regulator stations not only symbolize voluntary exchange and reliable service, but they also embody the very principles. Reiterating a salient point, these stations are the hinges of the entire oil and gas value chain. Their ability to precisely and accurately make measurements affects everyone, from stakeholders to end users, should they fail even marginally in their efforts. Many companies keenly know their central role and invest in expert design, installation, and operation.
Natural gas metering and regulator stations are rapidly becoming tailor-made, modular solutions highly adapted to the specific needs of distributors and customers throughout the oil and natural gas value chain. The oil and natural gas distribution system could not meet demand without these efficient, meticulously designed stations.
Metering and regulator stations are the essential link in the oil and gas supply chain. As such, they are gaining prominence as the demand for inexpensive, reliable, and life-improving natural gas grows.
Modularization for Hydrocarbon Pipelines in Africa
Where Natural Gas Is Found and How It is Obtained
The practice of inserting a device into a pipeline without interrupting a product’s transmission is called pigging. The backronym ‘pipeline inspection gauge’ is sometimes used to describe these devices, whose name originates from the squealing sound emitted from primitive in-line maintenance and inspection devices. These models were made from simple materials wrapped in barbed wire, leather, or other materials to clean and scrape the interior pipeline. Modern in-line pigging devices scarcely resemble these early ad-hoc creations.
In-line inspection pigs are versatile in their designs. Ranging from humble polymers, gels, or sophisticated detection rigs, these devices boast remarkable variability. Employing pigging devices for several operations is standard industry practice to maintain the integrity and efficiency of a functioning pipeline.
A true understanding of why a pipeline requires one type of pigging schedule as opposed to another makes all the difference between an effective, efficient pipeline and one that imposes exorbitant costs on its operators. Proper planning and understanding upfront are essential to pipeline operations.
If a pipeline problem suddenly appears on the horizon, it is simply too late. A once efficient method of transporting valuable resources has been halted. An investment of millions or even billions of USD is jeopardized. Assets are lost. Environmental damage is incurred. Avoiding catastrophes and minor disruptions is paramount.

Properly selected pigs and an ideal pigging pipeline program have a tremendous impact on the integrity of pipeline systems. Pipelines are the most cost-effective and efficient method of transporting a wide variety of fluid and gaseous materials. Though cost-effective, the capital and operating costs are significant (often increasing with pipe diameter and length). Other pipelines are constructed for their ability to traverse terrain strategically, facilitate international trade, or foster political growth between countries.
Regardless of its role, a pipeline must maintain two operating principles: the continuous flow of products and minimal overall cost. Pigs are critical to both fundamental principles of pipeline operation, though they are used throughout the lifetime of a pipeline.
They maintain a constant flow of products by:
Pigs also address the second principle of pipeline operation, efficiency, by:
The correct pig and pigging schedule varies significantly from one pipeline to another. A singular pigging solution for all pipelines does not exist. Each pipeline must be evaluated for the unique circumstances, constraints, and variables acting upon it.
A basic way of envisioning the effects of deposits is to consider throughput loss resulting from common deposits. A reduction of no more than 5% in diameter can reduce throughput by 10-15%. The resultant pressure increase necessary to generate original throughput levels would be nearly half (150%) of the original operating pressure. It is commonplace for friction to increase by several percentage points daily in a line if pigging is not conducted.
Primitive pigs of the early application were utilized solely to remove large deposits as needed. Modern pigging schedules can be considered when planning a system, as the process plays an essential role in all phases of the modern pipeline. Some of the most common uses for pigs occur during these phases:
Construction
Operating
Inspection
Maintenance
Rehabilitation
Decommissioning
The way each of these operations is conducted will vary from one system to another. The physical variances of a pipeline system, compliance codes, statutes, and the construction and operating procedures must be considered when establishing pigging schedules and pigs. Without these crucial considerations, the effectiveness of pigging operations is far from guaranteed.
Developing a pipeline entirely around pigging is ludicrous. The form and dimensions of a pipeline ideal for pigging operations resemble a straight line, precludes valves and outlets, and would require several other optimizations. Designing a pipeline to accommodate several dozen types of pigs makes more sense. Accommodating pigs through pipeline design is required in many parts of the world, though it varies from country to country. Hydrocarbon pipelines are typically designed using the largest and heaviest of pigs in mind, the non-destructive test (NDT) oriented in-line inspection devices known as smart pigs. Among the many elements that play a significant role in the effectiveness of pipeline design in pigging are:
The pipeline construction and design materials are classified as primary materials, internal linings, and external coatings. These materials are fundamental considerations that impact the necessary accommodations for continuous product flow and efficient operation.
Primary materials for pipelines vary widely. Cement, concrete, plastic, metals, and other materials are routinely used in systems around the world. The most common primary material for pipelines is steel, typically carbon steel, for lengthy pipeline construction. Considering the product, the type of steel required for a given line is always chosen. Customized solutions involving combinations of materials are used to achieve maximal effectiveness and efficiency.
Interior linings are designed for dual purposes. They protect the line from interactions with the product while reducing flow resistance. Frequently coated at the factory, linings may also be applied after the system has been constructed. The materials that comprise these linings are usually epoxy-based, so choosing the correct pig for cleaning is required.
A pipeline system’s exterior is just as crucial as the interior. Proper coatings greatly aid the prevention of corrosion from the soil and other materials. Failure to properly plan or execute external coatings results in corrosion that can require significant investment or temporary shutdown, in worst-case scenarios, to account for. Precisely controlled conditions and execution are required to avoid unnecessary delays, costly expenses, and environmental and site safety.
When considering pipeline design, the elements of diameter, the length between traps, and wall thickness are among the most essential and costly. Bends in the line are often necessary to traverse certain terrains. Though necessary, these bends should operate within constraints designed to accommodate the use of pigs.

The pipeline diameter is determined by the system’s required throughput. Wall thickness is an interrelated factor in this consideration; both are balanced by the cost of compressors and pumps. Generally, the efficiency of throughput in each pipeline increases with pipeline diameter.
Local conditions concerning transportation infrastructure, population density, and other factors may require adjustments to wall thickness. Lines are commonly constructed to retain the external diameter and vary the internal dimensions, a less-than-ideal configuration for pigging. Customized pipelines can be constructed with externally varying diameters, increasing the effectiveness of pigging operations (though often requiring specialized equipment to construct and modify).
Another aspect of pipeline dimensions is the length or approximate distance between pig traps and stations. Variations are the pipeline rule, as conditional requirements can change dramatically for any system. The product a pipeline carries is often a determining factor in the length a pig is expected to travel. Materials and coatings within a pipeline are chosen as a result of product requirements. The materials in gas pipelines tend to require traps within 100 miles, approximately 150 miles apart, and nearly 200 miles apart for crude oil pipelines. Exceptions to these general rules include placing traps up to 600 or more miles apart.
Finally, as pipelines are established along the desired path, it is sometimes necessary to follow the lay of the land. Benders or bending machines are familiar with on-site machining operations, as are the services of expert onsite welders who may properly fit joints of the mating pipe section. Bends that maintain a short radius are often factory-forged to standard radii. The dimensions of all bends must be supplied to providers of pigging services to accommodate proper procedures and pig selection.

Junctions are Y-shaped divergences that allow products and pigs to travel through and converge several connected branches of a pipeline system as needed. Essential to the operations of many modern pipeline systems, junctions require considering convergence angles, bores, and diverters to function properly with necessary pigging schedules and pig types.
Typical convergence angles are between 22 and 30 degrees, with 30 degrees being the primary convergence angle. Several methods exist for traversing pigs through wye junctures without causing damage to either the pipeline or the pig. Creating a shallower angle or a parallel bore produces variations in the navigation method and can alter the cost of creating junctures. Caution should be taken to consider the variables best suited to pig a pipeline system effectively.

Subsea junctions are common and exceedingly necessary phenomena in the conditions native to that environment. These junctions are typically equipped with a diverter, a mechanism that guides the pig through a junction. Many of these are mechanical designs, acting as a non-sealing gate, while others magnetically divert the pig to the desired branch.
Outlets and valves, whether installed before the operation or during operations via hot tapping, are known as potential problem spots for pigs.
Outlets (offtakes) are installed using tees. These tees are specially forged or fabricated to fit around a pipeline, creating a valid point of entry for tapping. Outlets must be placed at an appropriate distance from one another to avoid certain feature interactions. A minimum of three diameters of the continuous line is required between fittings. Additionally, a ratio of pipeline diameter to outlet size should guide the placement of guide bars parallel to the axis of the pigging run.

It is recommended that off-takes greater than 12” in diameter add perpendicular reinforcing bars to the above arrangement. Typically, parallel guiding bars and right-angled reinforcement bars may be installed with the same hot-tapping machine after the tap has been successfully created.
Lateral intakes or outlets are defined as intersecting a pipeline at any angle other than a perpendicular one. In this instance, the opening is always greater in length than the diameter of the lateral. Preventing the pig’s entry into these offtakes requires the seals to exceed the length of this opening.

Valve systems are central to many operations in a pipeline system. Despite their essential nature, valves maintain perhaps the greatest likelihood of a pig run’s disruption. Many types of valves are used on lines. All valves used on pipelines must aim to mitigate features capable of interfering with pig runs. Often, this means full-bore ball or gate valves equal in diameter to the pipeline itself.
In cases where valves are difficult for pigs to navigate, a sacrifice of performance may be required to navigate the line unless steps are taken to remove this difficulty. Beginning a pigging operation when mainline valves are not fully open can cause a disastrous scenario. Extensive damage to the equipment, line, and valve could result.
Prevalent in offshore operations, bundled pipeline configurations and flexible pipelines serve as versatile means for drilling and product transportation endeavours. Given their significantly differing nature from standard pipelines, these subsea-specialized systems require pigging considerations suited to their environment.
Pipeline bundles appear initially complex, though they bear some striking similarities to bundled utility or electric wires. This type of pipeline configuration is widely used because it effectively combines complex elements into a convenient and efficient package. Furthermore, onshore assembly and ease of towing make for remarkably versatile installations.

Bundled pipelines are often accessible to the same variety of pigging approaches as ground-based pipeline systems. The most notable exception is inspection using Magnetic Flux Leakage testing (MFL). MFL is a type of nondestructive examination conducted by an inline inspection (ILI) tool known as a smart pig. This testing method examines magnetic fields that spacers within the bundled pipeline may affect if they are made of similar materials to the carbon steel pipeline being tested.
Flexible pipelines are commonly employed in offshore operations. They are commonly found for floating production systems (FSO, FPSO, TLPS, etc.) and dynamic risers from a subsea pipeline end manifold (PLEM). Flexible pipelines are well established for deepwater operations, serving over a dozen operations.
Depending on whether the internal finish is rough or smooth, it may or may not be pigged. Manufacturers generally suggest avoiding metal-on-metal contact between the pluggable and rough bore varieties. Therefore, ILI, metal-brush-equipped pigs and similar metal pigs are discouraged. Pigging procedures should never proceed on rough bore pipe if the damage is suspected. Due to the construction of these pipelines, a pigging run after the damage is incurred could have disastrous consequences. Pigging a damaged flexible pipeline would likely unravel the line, resulting in a massive loss of product and functionality.
This element of pipeline design is entirely preventable if enough consideration is given to pigging operations. However, given the requirements of some line systems, these feature interactions are occasionally unavoidable. Certain pipeline features, such as successive welded bends or two tees installed equidistant to pig seals, can stall or potentially damage themselves and the pipeline.
Where possible, consideration should be given to the distance of a straight pipe between two tees and similar scenarios. If these scenarios are unavoidable in a system, they must be adequately described to pigging operators to mitigate risks.
Several key conditions of operation demand scrutiny when selecting the correct pig for a pipeline:
Each of these components offers significant operational challenges. Addressing them accordingly is the only viable approach to consistently effective pigging operations.
The product itself is likely to determine the type of pig used. If a type of pig is necessary for the desired operation (e.g. ILI MFL testing), the materials comprising various parts or seals may require adjustment. Refined hydrocarbon pipeline systems frequently adapt or select pigs to function properly with detergent or other additives. Failing to adapt the type of pig used can permanently damage the equipment or contribute to hazardous storage scenarios.
Pigging runs often proceed at the native flow rate of a pipeline. If the flow rate is steadily maintained, pigs produce or exceed desired levels of effectiveness. Loss of flow rate, stalling, hydroplaning, and high-velocity accelerations negatively impact pigging operations. While these speed changes disrupt cleaning and maintenance operations, they severely limit ILI pigs. ILI tools utilize highly sensitive equipment and display significant decreases in data collection when negatively impacted by flow rate.

The majority of pigs are largely unimpeded by native pipeline pressures. ILI instruments are, however, adversely affected by pressure within pipelines. Smart pigs use pressure and product-sensitive equipment, which must be properly protected. The primary concern of operating pressures revolves around low-pressure pipelines. These pipelines can stall on minor obstacles, lacking the necessary differential pressure to continue. In such cases, pressure may build to extremely high levels, causing a sudden, rapid acceleration. Speed excursions such as these can reach nearly 200 mph in less than 250 feet. Downstream venting and pressurizing the pipeline can mitigate the occurrence of this dangerous scenario.
Temperature ranges most impact ILI devices as with the above operating conditions. The electronic components inside ILI tools are sensitive compared to other pigging materials. The polyurethane seals present on pigs are capable of enduring operating temperature ranges found inside most pipelines.
Keeping with the primary operating goals of a pipeline, pig stations use valves and ‘traps’ to maintain continuous product flow. Pig stations may have launchers or receivers for beginning or ending a pigging run. Pig traps, or barrels, are oversized loading or receiving sections which taper to the pipeline diameter. Barrels are sealed by trap isolation valves designed to capture or release a pig.

Pig launching traps are designed to function solely with utility pigs or for ILI smart pigs and utility pigs. Barrel designs for launchers using only utility pigs are typically one and a half times the length of the longest utility pig. Barrel designs for launchers using ILI devices are considerably longer. Typical ILI tools are comprised of several jointed sections and require additional length. ILI-friendly traps require at least one pipeline diameter of extra length.

Pig-receiving traps are designed with additional concerns for those launching traps. The barrel length of receiving traps is of primary concern. Occasionally, a pig may get stuck on the run. When this occurs, a second pig may be sent downline to retrieve the initial pig. Receiving two pigs requires a minimum barrel length of two and a half times the longest pig length. As with launching traps, pig receiving traps require additional room for ILI devices employed in NDT exercises.

Pig designs vary widely according to circumstances. Utility pigs are often simple and durable, while ILI devices are more complex and more likely to suffer difficulties navigating a pipeline. Early pigs were often constructed without due consideration to their specific task. Modern materials are chosen for their durability, weight, and ability to perform a task or function most effectively during a pigging run.
Rather than cobbling together at-hand materials, pig designers look at each aspect of a pig and optimize it for usability in a specific environment. Among the hundreds of pig designs used for pigging programs, each has an ideal application. The utility pig is perhaps the most widely used variety and remains among the simplest in design.
Initial utility pigs evolved rapidly from their original form. Designers experimented with creating lightweight and even hollow bodies. Hollow bodies proved largely ineffective over lightweight bodies. Along with other design elements, the weight of a pig determines how concentric it remains during a run. Remaining close to absolute centricity is an important performance metric for pigs. While travelling within pipelines, forces act on the nose of the pig, turning it slightly downwards. Pigs commonly display more wear at the southern-most 6’oclock position, primarily on the driving or front seal.

The body of pigs is often distinctive in appearance. The material, shape, seals, and cleaning elements are indicators of a pig’s operating environment. Utility pigs take several common forms; some are modular and easily altered for task specialization. Other pigs may be cast or inflatable to suit their operating conditions better. Among the most common utility pigs is the mandrel pig.
Mandrel pig bodies are simple, cylindrical steel tubes. Their straightforward design makes them a versatile mounting platform for seals, brushes, and other equipment. These components can be bolted, clamped, or threaded snugly onto the pig. The design of this body allows for another ingenious advantage: optional bypass flow.
Bypasses allow pipeline flow to continue through the pig and may be used to aid cleaning efforts significantly. Though operators vary in their approach, bypasses are generally avoided with sealing pigs. Depending on the differential pressure a cleaning pig generates, the flow volume can vary significantly. The flow must be carefully determined in low-pressure environments to avoid stalling the pig. Maintaining centricity can be aided by allowing bypass through rear seals. This arrangement forces propulsion onto the front seal, centring the pig and improving performance.
Seals are the components of a pig that induce effective action and propulsion within a pipeline. They are designed for functionality and durability, as they can remain in contact with the pipe wall for hundreds of miles. Materials vary, but they are primarily polyurethane. Several common seal shapes exist, including cups, conical, and disc shapes.

Cups are perhaps the most used seal shape. Their development originated from rapid wear, which was expressed in early shapes. These designs pressed seals harder against the pipe wall, resulting in rapid deterioration. Early seals were also made from inflexible materials, further contributing to their lack of durability. Initial variants on seal shape caused the seals to adhere strongly to the pipe wall, causing the pig to tear through and continue. Seal design shifted to shapes and materials, promoting necessary contact while avoiding excessive contact.
Designing seals for pigging relies primarily on two polyols to achieve diverse properties. Polyether and polyester have distinct operating advantages in certain conditions. Polyethers are typified by their resistance to water, while polyesters have greater degrees of physical and hydrocarbon resistance. These polyols can perform exceptionally and remain cost-effective under most circumstances. They can be further engineered at greater cost to serve in subsea or other specialized environments when necessary.
Whether built into seals or attached, cleaning elements are essential to maintaining pipelines’ continuous flow and cost-efficiency. These elements are most often made of steel or polyurethane. Consideration must be given to the placement of the cleaning devices on the pig. They must be arrayed in a formation to cover the pipe wall completely during pigging operations.
Traditional cleaning elements were sloping steel blades that resembled ploughshares. Tremendous variations in cleaning element designs are now widely available. As with the above elements of pig design, modern materials and engineering produce more consistent results with little risk of pipeline damage. Blade elements are often made with polyurethane or other plastics for modern pipelines.
Brush elements are similarly constructed from metals such as hardened or stainless steel, though they are frequently manufactured with polyurethane. Brushes of different shapes are made to accommodate pigs limited to mounting one or two rows of brushes. Configurations limited to one row may utilize wedge-shaped or trapezoidal brushes so that the overlapping dimensions ensure complete wall coverage. Pigs capable of two or more rows may simply stagger rectangular brushes to ensure overlap in the brush arrangement.

In some instances, cleaning elements built into disc seals are used. These elements may be moulded into the sealing edge of seals.
Discussed below are select pigs designed and optimized for specific tasks. Choosing the correct pig is essential to successful pigging operations.
Utility pigs are often subdivided into cleaning pigs and sealing pigs. Cleaning pigs are outfitted to meticulously remove debris or solid deposits while sealing pigs are equipped to remove unwanted or accumulated liquids. Regardless of category, each type of utility pig is outfitted to handle the unique environment of the specific pipeline designated for the operation.

As alluded to above, mandrel pigs can fulfil the role of cleaning or sealing pigs. Their modular design allows operators to plan and assemble a custom pig relatively easily and carefully. This variability makes the mandrel pig such a widely used pigging device. Virtually every aspect of a mandrel pig is customizable and may be modified to accommodate pipeline needs.
Durable, inexpensive, and requiring little to no maintenance, foam pigs boast several appealing advantages. Foam pigs are primarily employed to rehabilitate pipelines and can be tailored to dozens of specialized applications. Comprised of open-cell polyurethane foam, they can maintain their form when confronted with operating pipeline pressures. Due to their lightweight, foam pigs are easy to handle, but they absorb product during a run. This requires caution when handling after pipeline pigging is completed. Foam pigs vary in density and coating, so they may be designated for cleaning or sealing operations. These pigs may also be moulded to form a conical fore-shape and a flat or concave rear shape. Specialized descaling and decoking foam pigs are also manufactured. These heavy-duty foam pigs are ultra-dense and moulded to accommodate the insertion of hardened, threaded steel pins to aid in their cleaning operations.
Sphere pigs are categorically used as sealing pigs, with some exceptions. The use of spherical pigs is often relegated to pipelines void of potential stall points. Exceptions include pipelines that install flow tees to mitigate the risk of spheres losing their seal. Despite the initial drawbacks of using sphere pigs, they maintain significant pipeline handling advantages. Their ability to navigate short radius bends nets sphere pigs a niche advantage in complex pipeline systems. Pipelines that require very frequent pigging can automate sphere pigging. These automatic systems are frequently employed to remove condensates from gas-gathering lines or to meet similar pipeline requirements. Small sphere pigs used to navigate these lines can be gathered by releasing a larger sphere pig and returning to their original trap.
Cast pigs or solid cast pigs are typically used for sealing (sometimes referred to as batching or swabbing) operations, though they can be manufactured for cleaning runs. As with other elements of pigging operations, the use of cast pigs arose from cost-efficiency considerations. Smaller diameter pipelines traditionally used mandrel or other pig types. The drawbacks of using a mandrel pig for small pipelines rest in the cost of assembly and parts replacement. Small mandrel pigs from two to eight inches require similar amounts of time to assemble and repair compared to medium-sized mandrel pigs. Often, it is cheaper to replace the mandrel pig than to spend resources on maintaining it.
This dynamic results in cast pigs being very common in smaller sizes. Most cast pigs are sealing pigs, regularly employed at process plant facilities. Cast pigs designed for cleaning may be moulded with integral discs or have allowances for adding cleaning elements. Though not as common, larger designs are also available for some applications.
Intelligent pigs or smart pigs are inline inspection devices that perform non-destructive examinations (NDE) of pipeline systems’ interior and exterior. Several methods of NDE or NDT have been steadily pursued since the mid-20th century. Prominent methods feature NDT methods such as magnetic flux leakage (MFL) testing, ultrasonic testing (UT), geometry measurement, electromagnetic acoustic transducer technology (EMAT), and eddy currents. Smart pigs are, regardless of the NDT method used, more delicate instruments due to the sensor arrays, data collection, and data storage devices on board. Precisely tracking intelligent pigs (detailed below) is essential for properly mapping defects within a pipeline system. Often, relying on one method of tracking virtually guarantees inaccuracy. Small errors in tracking result in large errors later as the smart pig travels dozens or hundreds of miles.
MFL tools have an extensive history of detecting corrosion, cracks, and other anomalies found in various industrial settings. Applying the MFL principle to pipelines for these purposes is an area of intense, sophisticated, and continual research in modern pigging.

Summarized below, MFL testing is addressed in detail in our Magnetic Flux Leakage article.
In-line inspection tools that use the MFL principle magnetically saturate the pipeline walls and record the magnetic field’s flux lines generated in this process. Anomalies are detected when defects—usually small quantities of missing material—disrupt the field, creating flux leakage. Properly discerning the type of damage detected during MFL testing is a highly developed scientific endeavour. Complex models, statistical analysis, and artificial intelligence are applied with experienced technical experts to better articulate and detect pipeline defects. Though MFL testing began as a low-resolution, unrefined process, it has steadily evolved into an essential aspect of pipeline maintenance.
ILI devices also use ultrasonic inspection devices. UT tools use a transducer to emit ultrasonic pulses that travel at predetermined speeds into the pipeline wall. The reflected echo creates a direct reading of wall thickness, allowing precise mapping of pipelines. Limitations to UT operations include pipeline product; signal deflect due to dents or other features, false calls, and transducer alignment. As with MFL techniques, consistent development of technologies related to UT tools has significantly mitigated early limitations.
EMAT tools rely on electromagnetic acoustic transducers to detect cracks in a pipeline wall. Steel pipelines may be excited through electromagnetic waves to generate an ultrasonic pulse. The main advantage of ILI conducted with an EMAT device is that it can detect cracks in a non-liquid environment. Consequently, gas pipelines benefit significantly from using smart pigs equipped with EMAT technology.
Several types of ILI tools are designed to determine pipeline geometry accurately. This pigging process usually occurs before the metal loss or crack detection devices are employed. The benefit of using geometry pigs before metal loss detection rests in data triangulation. From cleaning and maintenance pigs, geometry pigs create an initial ‘rough mapping’ of pipeline systems. Operators can analyze the initial data to compare with later high-resolution ‘maps’ such as those created by MFL, UT, EMAT, or other ILI devices.
Gauging pigs are often the first low-resolution geometry pigs used to determine buckle, denting, ovality, or other deformations. Generally, the dimensions of a gauging pig are designed within 95% of a pipeline’s inside diameter. Operators can rule out deformations over anticipated amounts if this gauging pig successfully navigates a pipeline. Gauging plates attached to this type of pig frequently return damaged, allowing operators to determine the location and expected severity of defects. Further procedures use electro-mechanical geometry detection tools or induce alternating magnetic fields to inspect pipeline deformations.
Electro-mechanical pigs use seal-covered, spring-loaded arms to maintain pipe wall contact throughout the run. As the arms make contact, the mechanical movement generates dimensional data, which is recorded on a data storage device within the pig. Recorded diameter changes generate a higher-resolution map than simple gauging pigs.
Some geometry pigs are designed to detect electrical currents generated by inducing alternating magnetic fields into the pipe wall. Eddy current pigs can efficiently map several types of pipeline defects and have long been able to generate analyses in the field immediately following a pigging operation.

Gel pigs are versatile elements of pigging operations. Usually water-based, these gels originate from oil field uses, including hydraulic fracturing operations (see our articles on Hydraulic Fracturing and Horizontal Drilling for more information). Though composition varies, these gels may be used for batching or separating, sealing, cleaning, applying inhibitors, and flushing debris from pipelines.
Batching or separator gel pigs are often water-based and gelled with cross-linked polymer. These gels are designed to flow around objects and reform. They are also designed to be biodegradable and easily destroyed with chemical breakers if necessary. Circumstantially, these pigs may be used alone or with mechanical pigs, though they require consideration based on pipeline product.
Pick-up and cleaning gels are typical of a water-based variety. Designed to suspend debris within the gel, this pig type’s viscosity demands the accompaniment of mechanical pigs to function optimally. Batching gels are often placed on either end of cleaning gel pigs to prevent dispersal by water.
Carrier and inhibitor gel pigs are created when hydrocarbon-based fluids are gelled. These pigs are ideally suited to removing water or debris from pipelines and boast similar sealing properties to batching gel pigs. An added benefit of these pigs is that they may be used as applicators for corrosion inhibitors. Other forms of carrier pigs may be alcohol or methanol-based gels designed for dewatering and drying operations.
Aside from these broad categories, many specialized gel pigs can serve in several capacities. Plugging gels, valve-sealing pigs, and even foamed fluids are among the more specialized varieties.
Among the top priorities of pigging operators (particularly with ILI devices) is tracking or detection. Though many technological and manual methods exist for pig detection, most of these methods take place outside of the pipeline. Pigs are typically equipped with odometer wheels, subject to various forms of disruption. Many of the methods discussed below are intrinsically flawed and unreliable as single-source detection methods. Fortunately, these methods infrequently interfere with one another. Combining several available methods of pig tracking is a highly recommended practice. Available methods include:
Acoustic detectors
![]()
Pig detection and tracking methods always vary with the unique constraints of a given pipeline, such that geography, subsea, or other conditions often determine possible tracking methods.
The primary goal of pigging is to maintain operating efficiency and minimize pipeline capital and operating costs, so all pigging procedures must contribute to these ends.
Achieving ideal operating pipeline efficiency begins with correctly assessing and executing a pipeline’s pigging needs. To achieve this goal, operators are encouraged to meticulously document and record data regarding cost, power consumption, throughput, and effective pigging operations. Scrupulously analyzing this data allows pigging operators to develop ideal pigging procedures and schedules for each pipeline system.
Data collected on these metrics are often extensive. Combining the knowledge of expert operators, experienced technicians, complex statistics, and modern computational technology is perhaps the most effective means of consistently producing maximal results for pipeline operators.
As an industry practice, pigging has only grown in relevance to pipeline operators since its inception. The need for more effective and efficient pigging solutions has increased with time.
Not surprisingly, cutting-edge technologies are continually applied in academic and practical settings to advance every aspect of pigging operations. Materials sciences, ILI technologies, data modelling, and data analyses are among the most concentrated areas of improvement.
Case studies, research reports, and white papers are routinely published regarding the technologies employed and data collected in pigging operations. Pigging operators are highly encouraged to seek out and become acquainted with relevant journals and researchers to produce the best results on an ongoing basis.
Developing correct pigging schedules is essential for maintaining pipeline efficiency while reducing capital and operation costs associated with pipeline systems. To this end, operators must accurately evaluate each pipeline’s requirements.
Choosing the right pig and developing an effective pigging schedule is of primary concern. Maintaining successful pipeline efficiency and cost-effectiveness hinges on meticulous record-keeping and scrupulous data analysis. Additionally, pigging operators should maintain knowledge of and continually integrate the latest methods and technologies which enhance their operations.
Pipeline and Gas Journal — Pigging
Cordell, J.; Vanzant, H., The Pipeline Pigging Handbook. 2003
Hiltscher G.; Muhlthaler, J.; Smits, J., Industrial Pigging Technology. 2003
Adegboye, M.A.; Fung, W.; Karnik A., Recent Advances in Pipeline Monitoring and Oil Leakage Detection Technologies. 2019