Operations required to complete Pipeline Swab Pigging on 1 x 8” x 1km pipeline from near the Petromoc Discharge header towards the CFM Manifold and 1 x 12” x 1.2km pipeline from the CFM Manifold to the 12” – 8” reducer on the jetty. The pigging process will be aimed at removing the current contents of the line, and easily removable deposits on the pipe walls, prior to the flushing process.
Services Provided:
- Integrity Assessment
- Pipeline Pigging
Client
Augusta Energy
Location
Matola, Mozambique
Date
February 2019 – March 2019
Contract
Detailed engineering, procurement & construction (EPC)