The rediscovery of the tremendous value of naturally occurring gas for the modern age has ensured its place as the fastest-growing energy source for the next twenty years (2040) – and liquefied natural gas (LNG) is integral to this growth. LNG is natural gas supercooled to a liquid state at -260° Fahrenheit (-162 C°) for safe and efficient transport. Natural gas liquefied by cryogenic cooling takes up 600 times less space than its gaseous state and becomes non-flammable, non-explosive, and non-toxic. Humans have widely utilized natural gas in raw form for nearly 2,500 years. By the 4th century BCE, the Chinese drilled for and transported natural gas through crude pipelines constructed of bamboo; Asia, the Middle East, Greece, and others recorded the use of gas in the ancient past as a consummate energy source, mostly for heating and cooking. These naturally occurring hydrocarbon gases (primarily methane) are industrialized in the present day and serve to generate vast amounts of energy for electricity generation, manufacturing, vehicle fuel, heating, and cooking. By the late 18th century, Britain lit her homes and city streets using natural gas. However, the first real gas industrialisation took place in the 19th century, when scientists began to compress and liquefy natural gas.
James Joule, Michael Faraday, Lord Kelvin and several other 19th-century pioneering scientists raced to discover techniques for compressing and, particularly, liquefying natural gas. While compressed natural gas (CNG) and LNG share similarities, their differences are key to understanding each technology’s current and future uses. CNG is natural gas reduced to 1/200th the volume of its natural state, roughly 1 per cent of its natural atmospheric pressure. CNG is used as fuel for vehicles, mostly large trucks and buses, produces less emissions than standard gasoline or diesel fuels, requires less maintenance than other hydrocarbon-fueled transportation, and is safer overall when compared to gasoline-powered vehicles and considerably safer in the event of a spill (as the natural gas is lighter than air) mixing easily and dispersing quickly. The trade-off for these benefits is that CNG is much less energy dense (about ¼ the energy of gasoline per gallon) than gasoline and often requires large, bulky tanks for fuel storage. Despite these drawbacks, natural gas-powered vehicles – CNG and LNG – are making headway worldwide. Additionally, CNG locomotives operate around the globe.
Energy needs have evolved alongside civilization since the dawn of time. For thousands of years, wood was the dominant energy source, surpassed by coal in the 19th century and then dominated by oil. The affordability and availability of oil made it the logical successor in this evolutionary chain of energies. Natural gas maintains this evolutionary process by offering wide availability and affordability, among other distinct advantages. Natural gas is a notably cleaner energy source than coal and oil, producing almost no pollutants, only the same water and carbon dioxide that we exhale. Though pipelines remain the primary means of transporting natural gas, liquefying natural gas reduces its volume to 1/600th of its natural state’s volume, allowing for safer and less expensive transportation and storage. The advantages of LNG rest in its ability to connect producers and markets worldwide. This is achieved by short-range cryogenic pipeline transportation, vehicle transportation, and LNG vessels and carriers, all of which are specially designed for this purpose.
LNG is the bridge between natural gas production and its utilization as the world’s fastest-growing energy production source. Its place as a critical component of global, low-emission, low cost and high-efficiency energy is firmly established and growing at an astonishing rate. While capital costs are notoriously expensive, trends in the current LNG market suggest doubling market value over the next two decades. By March of 2015, Goldman Sachs noted that global trade in LNG could exceed $120 billion, making it the second most valuable commodity in the world, second only to oil. Inevitably, natural gas will supplant coal and oil as the preferred, cleaner transition fuel – while ever more renewable resources – such as biogenic gas, solar, wind, nuclear, and future energy production methods (theoretical or yet unimagined) bring us ever closer to complete renewability and greater degrees of efficient energy production. The companies that pioneered LNG are familiar names: Dutch Royal Shell, Exxon Mobil, Gazprom, Sinopec, Chevron, and many others. Large capital investments are highly valued in the LNG industry, as projects are often planned but rely extensively on solid investors. The LNG industry, both at facilities and particularly during transport, boasts the finest of safety and reliability records in large-scale energy industries, with only two incidents of serious note occurring anywhere in the LNG value chain (both at onshore LNG facilities) in nearly a century of operation, with no major incidents at all during transportation of LNG. A verdantly growing industry destined for great things, with safety and reliability at the pinnacle of all stages in the chain.
Comprised of carbon and hydrogen, natural gases such as methane are termed hydrocarbons; these hydrocarbon gases are a byproduct of long-dead organic matter, compressed and heated for millions of years, with little or no exposure to oxygen. The chemical bonds formed in this process maintain the solar energy originally obtained from sunlight. Conventionally, natural gas is found within oil reservoir deposits and can be produced by vertical wells and standard pumping techniques. Advancements in technology and methods allow for sourcing and producing natural gas from challenging environments, known largely as unconventional resources.
Where Natural Gas Is Found and How It Is Obtained
Conventional natural gas is straightforward to source and produce, uses standard, established procedures, and uses non-specialized technologies. It is also less expensive, making conventional natural gas the first resource pursued when possible.
Unconventional natural gas is more difficult to source and produce, requiring specialized equipment and extracting techniques. These unconventional gas resources present various circumstances, each offering a distinct set of challenges and considerations. Unconventional natural gas resources include shale gas, coalbed methane, tight gas limestone or sandstone, methane hydrates, and the renewable resource of biogenic gas.
Producing conventional or unconventional natural gas requires a team of exploration geologists, geophysicists, and accompanying specialists who drill to the appropriate depth and employ the relevant production techniques.
After the team locates an oil reservoir, a drilling rig creates a vertical shaft, and piping is inserted to facilitate oil and natural gas extraction. Initially, the reservoir’s pressure will naturally bring the resources to the surface; as the pressure equalizes, a pumping system is connected to continue production. Once the well has been produced to its full extent, it is cemented and capped to protect the area and prevent hydrocarbons from escaping.
Unconventional natural gas is a rapidly expanding field of possibility, promise, and versatility. With biogas and methane hydrates, it will stretch far into the future.
Biogenic gas or Biogas is a fully renewable resource composed of methane-rich gas produced by bacteria called methanogens. Essentially, any organic material is a potential source of bio-gas: food waste, livestock manure, and sewage. While the sources for biogenic gas are extremely varied, there are a few popular ways of producing biogas. An Anaerobic Digester takes the above-listed biogas sources in addition to fats, oils, and grease, breaks them down, and produces natural gas. The natural gas produced must undergo treatment and processing to remove impurities before it can be utilized.
Methane hydrate is a naturally occurring crystalline form of methane, largely found deep beneath the ocean floor (estimated 95%) and in sediments found in Arctic regions. Some estimate methane hydrates to be the most abundant source of unconventional gas worldwide, ranging from twice to ten times the current reserves of natural gas. However, extracting economically feasible amounts of methane from these crystalline formations is difficult. As of 2013, methods to extract methane from hydrates made significant progress, and as of May 2017, Japan and China announced a successful extraction of methane hydrate mined in the South China Sea. Despite these advances, it may be several years before this colossal energy source can be produced to scale.
Coal bed methane is a natural gas created during coal formation and produced by several means. The methods for extracting this variety of methane rely on technologies designed to produce a specific form of stimulation to the coal beds. First, a well is drilled into the coal seam (coal deposit); as the drill moves through layers of earth, pressures exerted on the well change, and measures are taken to ensure the well’s stability and isolate the surrounding environment. A steel casing is inserted into the well, and cement is poured through the steel using specialized equipment to form a steel interior and cement exterior. This process is repeated through each layer until the coalbed is reached, where the final casing is made; horizontal drilling may be used to reach more difficult coal seams. Drilling then proceeds into the coalbed, where water is removed, and natural gas begins to surface. One of the stimulation techniques for producing methane from coal beds is hydraulic fracturing. Fracturing involves creating small perforations in the well casing and pumping hydraulic fluid (containing 90% water, 9.5% sand, and chemical additives approximating 0.5% of the fluid) into the coal seam. The sand in the hydraulic fluid prop opens the fractured coal bed and allows the collection of the natural gas. Underground coal gasification involves injecting oxygen and water into the well(s), leading to the coal seam, and this is where the coal seam is located until an appropriate mixture for burning is reached. The partial ignition of the coal bed serves to produce natural gas, which can then be collected as it flows toward the surface.
Coal Seam Production
Tight gas is natural gas trapped within the unconnected pores of sandstone or limestone and is typically extracted using one or more horizontal wells. Hydraulic fracturing is the predominant method for producing natural gas from this type of formation, although deliquefying—pumping up all the water present in the well—and acidizing the well to dissolve sediments and limestone are also routinely employed techniques for tight gas production.
Shale gas is a variety of natural gas contained within shale formations, often absorbed into organic matter. Shale has a low permeability, which disallows the flow of fluids and gases. Natural gas production from shale is achieved through coal bed gas and tight gas production methods: horizontal drilling and hydraulic fracturing. Employing these methods speeds the flow of natural gas and makes the process economically viable. Once these energy-rich materials are produced, they must be treated and then processed before reaching the market.
Natural Gas from Shale
https://www.youtube.com/watch?v=BJsggzmgMI0&feature=youtu.be
As raw natural gas is produced, it travels to the nearest treatment facility to undergo several processes. These processes separate the raw gas (sometimes called wet, sour, or feed gas to delineate the primary accompanying components) and ready it for further use. The treatments applied to this gas will produce a dry gas composed of 85-99% methane.
Natural gas processing begins at the wellhead, where the gas is produced. The composition of this raw natural gas varies depending on the deposit’s type, depth, and location and the surrounding geology. Natural gas processing plants purify or dry the raw gas by removing common contaminants such as water, hydrogen sulfide, and carbon dioxide; these contaminants at an LNG plant could cause significant disruption to the liquefaction process or the liquefaction plant. Sweet gas, sour gas, and acid gas are all terms which denote content: relatively free of hydrogen sulfide, containing hydrogen sulfide, containing significant quantities of carbon dioxide, hydrogen sulfide, or similar acidic gases, respectively. Once common contaminants are removed, adsorption processes remove mercury, sometimes followed by nitrogen removal. Natural gas liquids (NGL) recovery typically concludes the processing, leaving a refined natural gas product fit for a spectacular array of industrial applications.
Liquefaction plants are typically proposed and constructed by oil production companies or corporations. These corporations generally focus on exploring, producing, refining, marketing, and transporting oil and natural gas products. Among them are familiar names such as Royal Dutch Shell, Exxon Mobil, Gazprom, Sinopec, Chevron, Total S. A., Lukoil, Reliance Industries Ltd., BP, and Equinor, though many others exist. These LNG facilities convert natural gas to its liquefied form, which is a colourless, odourless, non-flammable, non-explosive, non-toxic, highly transportable resource when maintained at the cryogenic temperature of –260° F (-160° C).
The continuously expanding LNG industry has liquefaction facilities (large scale) that are both proposed and under construction in double-digit numbers around the globe. All LNG plants are comprised of the experts and technologies required to process dry natural gas into a liquefied phase; they also contain the necessary, specialized storage equipment and cryogenic pipelines required to transport the LNG to nearby peak-shaving facilities, transport vehicles, or specialized maritime vessels designed to store and transport the cryogenic, liquefied natural gas safely. The construction of these central elements in the LNG value chain often takes several years to complete.
LNG Train
What is LNG? Turning Natural Gas Into Liquid
https://www.youtube.com/watch?v=QgtSoEJD9HE
Small-scale liquefaction (SSLNG) is a relatively small and new but growing aspect of the LNG industry, which has proven itself scalable, profitable, and brimming with potential. It can meet the fueling demands of shipping and trucking industries, which require more environmentally friendly and efficient fuel sources than diesel and oil. Small-scale liquefaction provides greater flexibility that larger facilities and fleet transport vessels may be unable to provide, such as bunkering fuel for marine vessels and off-grid power generation.
Small-Scale LNG: A Reality Today May Be A Game-Changer For Tomorrow
There are three basic methods of liquefaction: the classic cascade, mixed refrigerant cascade, and the expansion cycles (although several variations of these methods exist). Each of these processes requires a specialized arrangement of equipment and refrigerants, which will vary depending on the site conditions, production, and feedstock requirements. All liquefaction processes will require compressors, heat exchangers, and refrigerants to produce LNG.
Gas turbines are widely used to drive refrigeration compressors at LNG facilities. Powerful and efficient aero-derivative turbines are reliable, heavy-duty, and widely used, though conventional heavy-duty gas turbines are still the norm in the industry. LNG facilities went from having two compressor driver choices in the 1960s to seven or more by 2016. As with the other equipment choices, this choice depends on the LNG producer’s needs.
Coil-wound heat exchangers emerged from the technology of 19th-century locomotive boilers. Multiple layers of tubes are wound within a pressure vessel shell. Natural gas and high-pressure refrigerant both cool as they ascend the tubes. Very cold refrigerant descends around the tubes inside of the shell. The wound tubes can provide a heating surface area equivalent to tens of thousands of square meters. These units are compact but rather large and slightly resemble a Saturn rocket. Coil-wound heat exchangers can contain pressure nearing 250 times atmospheric pressure and can be made from different materials.
The plate-fin heat exchanger is lighter and smaller than coil-wound heat exchangers. Easily scaled from small to large sizes, they are comprised of alternating layers of corrugated fins separated by flat, aluminium plates which serve to transfer heat between the natural gas and refrigerants. The fins enhance heat transfer from the fluid and conduct more heat to the plates. Layers of fins and plates are arranged to optimize the process. The aluminum plates are brazed together, headers are attached to direct the flow of natural gas and refrigerants. This type of heat exchanger is stored inside a heavily insulated box, known as a cold box, allowing more flexibility during steady and changing conditions. Plate-fin exchangers transfer around six times more heat in a given space than coil-wound heat exchangers.
Some LNG plants use pure hydrocarbon refrigerants (methane, ethane, and propane individually), while others use a mixture of hydrocarbon refrigerants.
Technology and Methods of Liquefying Natural Gas
Australia Pacific LNG: An Overview of the LNG Facility
LNG is transferred cryogenically to specially insulated storage tanks in one of several facilities:, onshore and offshore import terminals, liquefaction facilities, and to a lesser extent at peak-shaving facilities[6]. Designed to minimize “boil-off gas” (evaporation) and maintain cryogenic temperatures, LNG storage is engineered with safety, containment, and efficiency in mind. Boil-off gas (BOG) is necessary to maintain the temperature by keeping the pressure constant; this gas is then captured and cycled back into the LNG facility or otherwise used. Storage facilities can employ venting if overpressure is a concern due to stratification within the tanks. Densitometers are utilized within the storage facilities to monitor such developments, and operators are trained to mix the LNG to break up any stratification. Various tanks exist to meet the needs of LNG producers: Single, Double, and Full containment tanks, membrane tanks, and in-ground tanks all serve in this endeavour according to the site conditions and production requirements.
Single containment tanks are composed of a self-supporting, nickel steel inner cylindrical container surrounded by an outer carbon steel tank that holds insulation in the annular space. Though the outer tank is incapable of holding cryogenic material, an external bund (i.e. dike, berm, dam) is always present to completely contain the material in the event of a total failure of the inner tank. Single containment tanks require a relatively large area of land and are the most commonly used tanks; they lay claim to an excellent track record for safety and reliability.
Double containment tanks are very similar in construction to a single containment tank. This type of LNG storage tank makes use of a post-stressed concrete wall (as opposed to a dyke) which will contain the liquefied natural gas should the inner tank fail. Though this type of storage tank is more expensive, it requires less land to store LNG than a single containment tank.
Full containment tanks are a variety of double containment tanks that fill the annular gap between the first and second containers, creating a vapour and liquid-tight operation around the clock. A metal or concrete roof will cap the wall surrounding this storage tank. Many of the tanks built in the last decade were constructed as full containment tanks.
Membrane tanks are built from post-stressed concrete with an inner, load-bearing insulation thinly covered by a stainless-steel corrugated membrane. This design allows the concrete tank to support the weight of the LNG by transferring that weight through the membrane (which expands and shrinks with changing temperature) and insulation.
In-ground tanks are generally more expensive and time-consuming to construct than their above-ground counterparts (4-5 yrs. on average, compared to 3 yrs.) because specifications prioritize site conditions, surroundings, and safety. Naturally, these tanks have no need for containment dykes or walls, which allows for a lesser required degree of separation from adjacent lands. Often, these tanks are constructed where both land and space are at a premium (e.g. Japan or Korea). The safety of in-ground tanks is best evidenced by more than 45 years of incident-free operation.
Cryogenic pipelines, tanker trucks, and railway tankers are the primary means of transportation for LNG over land. LNG pipelines are used for transportation over short distances due to the cost of maintaining the -260°F cryogenic temperatures. Tanker trucks are most often used in mid-range and regional transportation of LNG to areas that lack LNG pipeline access. LNG by rail is a promising, viable land-based form of transportation which is most effectively utilized at ranges exceeding 150 miles (200-250 km); while this form of transportation over land is not widely in use outside of Japan, efforts are underway in the United States and other countries to implement LNG transport by rail. While land-based transportation of LNG plays an important role and is capable of much growth, the bulk of LNG transportation and trade is conducted via LNG carriers and a variety of sea-going vessels.
A revolution in modern energy transportation began in 1959 as the world’s first LNG carrier left the Louisiana Gulf coast to complete a successful delivery to the UK. The staggering growth rate and subsequent demands have catapulted the worldwide LNG fleet to a tremendous 500 carriers with a further 100 on order [1.][4.]. LNG carriers are an absolute marvel of engineering, gargantuan in size and capacity, these carriers range up to one third of a mile in length (350m or more), longer than the Eiffel or Petronas towers are tall. A single shipment from an LNG carrier of this class can power an astonishing 70,000 homes for an entire year. The capacity of over-water LNG ships varies from 1,000 cubic meters to nearly 270,000 cubic meters in the largest of carriers. Most LNG carriers are designed to transport LNG in either geometric membrane tanks or spherical tanks (Moss sphere design). LNG is carried aboard double-hulled vessels in specially insulated storage tanks near atmospheric pressure within the inner hull. Principles of LNG storage persist aboard these vessels and are put to ingenious use; the boil-off gas produced on many of these ships not only refrigerates and maintains the chilly –260° Fahrenheit (-160° C) temperature required for liquid natural gas, it provides the fuel which powers the engines on board. Though these vessels are among the most technologically advanced in existence, they meet the highest regulatory standards in the world.
LNG The Facts Video
The smaller variety of LNG carriers (1,000 – 25,000 up to 40,000 cubic meters capacity) is designed to fill specialized roles such as short-distance coastal and river trading, delivery to various land-based industries, power plants, and LNG suppliers for fueling vehicles or maritime vessels. This niche market is expected to grow as the ever-increasing demand for cleaner-burning, readily accessible natural gas rises. These smaller vessels allow greater degrees of flexibility in the overall value chain for LNG and can make excellent use of ship-to-ship LNG transfer or a floating storage and regasification unit (FSRU).
Often secured by a type of jetty or Single Point Mooring (SPM) buoy, floating storage and regasification units (FSRUs) are either adapted LNG carriers or floating installations which act as versatile LNG terminals for storage and regasification. These marine-based terminals store the LNG before converting it back to gaseous form, although floating regasification units (FRU) may be used to simply convert LNG to its gaseous state if storage is not necessary. At these terminals, LNG is transferred from the carriers via unloading arms or hoses through a cryogenic pipeline into a storage tank and stored or processed further. Low-pressure LNG pumps transfer the liquid gas to higher-pressure pumps and through an LNG vaporizer, where it is warmed back to its gaseous state. FSRUs use several methods for heat exchange and can vary in other aspects. Once the transition is completed from liquid to gas, the natural gas undergoes several treatments before it is sent to market. Offshore regasification facilities provide the LNG industry with additional versatility by further reducing risks, expense, and environmental impact while supplying a mobile (by towing) regasification unit. An FSRU is particularly suitable when near-shore access is difficult or limited due to environmental considerations, densely populated areas, or prohibitively costly land. The use of FLNG assets such as FSRUs and floating production, storage, and offloading units (FPSOs) are an increasingly desirable trend as an effective use of capital expenditure (CAPEX) in the LNG industry, as it is considerably less fixed, and therefore significantly reduces the potential risk that may be associated with a landed terminal[9]. FPSOs are capable of producing and processing both oil and natural gas, storing this cargo, and then offloading it to an oil tanker or LNG carrier for pickup, often dispensing entirely of pipelines (and onshore facilities) in the process.
Single Point Mooring (SPM) Calm Buoy Systems – The Ultimate Guide
While FSRUs boast many benefits, particularly in short-term projects, onshore import and regasification terminals or plants are typically more economical for endeavours with lifespans exceeding ten years. If additional land is available, onshore regasification plants are readily adaptable in terms of storage and regasification volumes. Onshore regasification plants consist primarily of storage, processing, distribution, and receiving installations. Once a carrier is berthed at the jetty, LNG is unloaded to storage containers. After storage is completed, the LNG cis regas regasified or sent to loading facilities, which may have installations for truck, railcar, container loading, barge loading, or ship bunkering. Suppose regasification is the next step after storage. In that case, there are several available vaporizers for converting LNG to a gaseous state in preparation for the market, the choice of which depends on the project’s overall needs.
Once regasification is complete, the natural gas undergoes additional treatment either at the regasification terminal or at another facility a short distance from the terminal. Due to natural gas’s colourless and odourless properties, its presence is undetectable without proper equipment. Before the natural gas is distributed to the market, an odorant is added, and finally, the gas is metered and sent by pipeline to both industrial and residential customers.
Natural gas production and consumption is on the rise, with natural gas in second place behind coal, making up a quarter of the total electricity generation worldwide. This output is largely achieved by utilizing natural gas power plants, of which there are two primary types. Simple (sometimes open) cycle gas plants and combined cycle gas plants. The simple cycle gas plant develops energy by heating and propelling gas through a turbine, thereby generating electricity. This process generates waste heat, which simple cycle plants do not make use of. These plants are ideal for handling the peak hours and seasons due to their dispatchability or the ease at which they can turn on and off or increase their output. Combined cycle gas plants generate power in a similar manner and can also contribute peaking power; the combined cycle plant makes use of its waste heat by heating and boiling water to produce steam, which drives an additional turbine, greatly increasing the overall efficiency of the plant’s energy operations. Modern combined cycle plants can achieve upwards of 60% efficiency.
Though LNG carriers have long used their cargo as a source of highly efficient propulsion, the environmentally cognizant market is increasingly adopting LNG as a cleaner source of bunkering fuel that presents the additional benefit of a decrease in operating costs. This LNG powered fleet includes a diverse range of vessels: ferries, patrol ships, tug boats, oil and chemical tankers, as well as platform supply vessels. The long-term benefits of converting existing oil-powered ships to LNG are clear, particularly considering emission regulations, but initial investment costs are high. Scrubbers and other technology can reduce emissions while increasing operational costs significantly. Vessels purpose-built to fully operate on LNG fuel will play a vital role in moving towards an environmentally friendly transportation and trade industry. The world’s largest cruise ship operator, Carnival Corporation, made history in December of 2018 with the first fully LNG-fueled cruise ship; seven more of these ships are set to follow between now and 2022[11].
LNG As Marine Bunkering Fuel
Nearly 27 million natural gas vehicles (NGV) are operating worldwide; most are engaged in commercial and fleet operations – with sound reason [14]. LNG and CNG (Compressed Natural Gas)fueled vehicles advance a sizeable list of benefits for commercial operations. CNG and LNG-fueled vehicles share the advantages of considerably lower particulate and greenhouse gas emissions, reduced engine wear, increased safety and theft prevention, up to 50 per cent noise reduction, comparable or less expense than diesel, and simple gasoline or diesel to natural gas engine conversions (or bi-fuel engine conversions). There are, however, tremendous differences in these technologies: fuel cost, fueling equipment, capital cost, tanks, pumps, and hazards. Some key differences as a fuel for commercial vehicles rest on the nature of these two technologies. LNG, for instance, is more than twice as energy-dense as CNG and can travel up to 2.4 times the distance than a CNG-fueled truck, allowing for a much greater range of transportation. While CNG-fueled vehicles have made some headway with fleet vehicles in the inner city, extra-urban use is stymied by the limited energy storage volume. Most data regarding LNG trucks in the commercial market comes from Asian countries and North America; currently, more than 3,600 LNG-fueled trucks operate in North America, and upwards of 100,000 LNG vehicles are in use throughout China. Evaluations of the performances of various types of trucks, including dump trucks, buses, freight transporters, and others, have been conducted in these countries, demonstrating variables such as travel range to tank size ratios, recharging time, and weight saving capacity of LNG-fueled trucks in contrast to CNG fueled trucks. A dump truck, BelAZ-75485, with an LNG 560-litre fuel tank, stores the LNG equivalent of nearly 27 CNG cylinders, saving over 2,000 kgs of carrying capacity. An LNG bus operating in Beijing with a 335-litre fuel tank routinely travels 450 km without stopping to refuel.
Similarly, an LNG-fueled freighter truck travelling between the U.S. and Canada with a 680-litre fuel tank could travel 800km before refuelling [10]. The refuelling time of LNG is roughly 1/3 to 1/5 compared to CNG-fueled vehicles. Currently, manufacturers of LNG trucks offer such vehicles with operating ranges of over 1100 km. The use of LNG-powered commercial vehicles is increasing worldwide as emission standards improve and more effective energy methods are pursued.
While the spotlight for LNG-fueled vehicles is on heavy-duty trucks, the potential it represents for the domestic market is not easily dismissed. The same advantages for NGV vs. gasoline-fueled vehicles apply to the domestic market. The domestic market has mostly experimented with bi-fuel CNG vehicles, which only partially run on natural gas. As with diesel engines, standard gasoline engines can be easily converted to run entirely on CNG or LNG. LNG has a few distinct advantages regarding the future of automobile fuels. Commercial fueling stations for each technology create unique demands which are highly strenuous for CNG. Utility infrastructure, capital, electricity, and the expensive, high-pressure tank requirements for CNG stations would be prohibitive in establishing the necessary availability of commercial stations in addition to the fact that refuel times range from hours (fast fuel systems) to days (slow or home fuel systems) [16]. Slow-fill stations would be economically competitive (in an operational sense) with LNG fuel stations but would require many hours to fill a CNG tank. Theoretically, CNG filling stations could be connected to city gas lines to allow home fueling of a CNG-powered vehicle using a gas compressor (with the vehicle tank acting as a home energy storage device). As developments further biogas production, natural gas (LNG) is assured to play a crucial role in developing renewable, green energy resources.
Business Case for LNG As Vehicle Fuel
LNG-fueled trains have been in developers’ sights worldwide for many decades, but could not manage the feat until November of 2017 when Florida East Coast Railway unveiled their fleet of 24 locomotives that had been converted to run on LNG. The long decades of testing, debating, and engineering are over, and the pursuit of cleaner, more efficient, and less expensive transportation by rail has finally been realized. This extraordinary breakthrough will profoundly impact the future of long-range transportation over land, particularly in transitioning from diesel to LNG-fueled locomotives, as the global LNG industry charges forward[11].
Natural gas is, without question, a fossil fuel; when burned, it produces carbon dioxide in the least amount of any hydrocarbon energy source, 50 to 60 per cent less than coal and 30 per cent less than oil, while producing negligible amounts of particulate matter[12]. The implications of these facts are staggering; as the natural gas industry grows, replacing coal and oil, global emissions of greenhouse gases will fall dramatically. This directly translates to public health benefits as well, given that reducing these harmful particulate emissions associated with coal plants reduces cases of asthma, lung cancer, bronchitis, inflammation, and heart disease[12].
The rise of LNG within the last decade has made natural gas the only true rival of coal electricity generation as power generation moves away from coal and oil and towards natural gas. This shift was made possible by advancements in natural gas collection and LNG, which is the principal way such vast quantities of natural gas were made viable for energy production. The unique ability of LNG to effectively and economically power trains, vehicles, and seagoing vessels and generate cleaner electricity places it in an ideal position for transitioning global energy away from archaic forms of energy production and toward a new age of possibility.
As we strive for ever greener, more renewable resources, the role of natural gas and the vital processes to make it a cleaner, viable resource cannot be overstated. LNG is an invaluable asset as industries transition to greener technologies. As mentioned above, biogenic methane gas is a boundless, renewable source of natural gas that represents the frontier of tomorrow’s energy needs; biogas produced in the present-day uses existing LNG technology to provide the safest, economically sound transportation and distribution available.
Safety considerations are primary in the modern LNG industry, demonstrated by rigorously employed systems of procedures, codes, equipment and regulations dedicated, at every step of the process. All LNG facilities and terminals make use of liquid and gas vapour leak detection equipment, multiple layers of containment, and monitoring equipment (often control rooms), as well as a veritable panoply of technologies to gauge pressure, prevent, detect, and extinguish the fire or any other possible contingency[2.6]. These strict precautions permeate the entirety of the LNG industry. Though accidents at LNG facilities have occurred since the inception of large-scale natural gas liquefaction, only two incidents have occurred since LNG production began 82 years ago.
On the afternoon of Friday, October 22nd, 1944, above-ground storage tank No. 4, containing liquefied natural gas belonging to the East Ohio Gas Company, began to discharge vapour from a seam on the side of the tank. Carried by the wind, the vapour entered the sewer system, mixed with sewer gas and air, igniting an explosion. The initial explosion was thought to be a single event; with firemen present, onlookers returned home. Within half an hour, a second above-ground tank exploded, leading to yet more fire and explosions, which travelled through sewers and into drains located in nearby houses. When the disaster concluded and order was restored, a total of 130 lives were lost, and many hundreds were left homeless[13]. The magnitude of this disaster created a lasting impact on both the producers and users of natural gas. The Cleveland East Ohio Gas Explosion served as a major catalyst for change in the nascent natural gas industry and continues to drive those involved in the gas industry to maintain the highest industry safety standards, with an ardent commitment to painstaking risk management.
Regardless of the type of LNG facility, multiple layers of protection are exercised, from siting and design to control and monitoring, prevention, protection, facility emergency response, and community emergency response. These layers are designed meticulously, with great planning, preparation, and disciplined practice of responses and protocols[2.6].
Around 6:40 p.m. on Jan. 19, 2004, Unit 40 at the Skikda LNG plant in Algeria exploded, mere seconds later the nearby units, 20 and 30, exploded in a chain reaction. The blast damaged nearby structures, including a power plant, a harbour berth, numerous homes, and community buildings. In total, 29 lives were lost, and nearly $1 billion worth of damage was caused. Various sources reported that Unit 40 at Skikda had not been renovated since its commission date in 1978, also frequent technical issues indicated that the unit operated only intermittently from May 2003, until the accident. Maintenance and security workers cited Unit 40 as requiring significant technical intervention bi-weekly for nearly six years, noting deficiencies in the cryogenic units, which were allegedly leaking gas[15]. Outdated and ageing steam-based equipment made production targets difficult to reach, putting pressure on the plant managers to push their equipment too far. The disaster at Skikda was the first and only LNG facility disaster to occur in 60 years following the 1944 tragedy in Ohio.
LNG transportation maintains a sterling safety record over the course of 60 years, from the first LNG carrier voyage to the present day. Over 100,000 LNG deliveries have embarked with cargo and arrived at their destinations without major accidents, safety problems, security issues, or loss of cargo containment[17]. LNG is notably not carried under pressure, as it is simply natural gas cooled to a liquid state and maintained at the necessary temperature for liquefaction. In a liquid state, it is non-toxic, non-flammable, and non-explosive. Should the highly unlikely event of a loss of containment occur, the LNG would revert to its gaseous state and dissipate without impacting water or land.
LNG The Facts Video
What’s Cool About LNG? Everything!
Over the last decade, the volume of global LNG trade has nearly doubled from 227 billion to over 400 billion cubic meters. Much of the rapid increase in production and trade of natural gas is driven by a need for cleaner fuel, technological advancements in producing natural gas resources, the discovery and development of bountiful natural gas fields, and the increasing interest of countries around the world in LNG. The Shale Revolution, a combination of horizontal drilling and hydraulic fracturing techniques, allowed the United States to dramatically increase its production of natural gas from formations virtually inaccessible in the past. This development has caused a shift in worldwide imports of LNG and will continue to influence the future trends in the LNG industry. The largest LNG trade flow route continues to be intra-Pacific trade, with high demand growth continuing in China. Demand for LNG continues to grow in Europe.
The LNG market is a dynamic and flourishing environment, with many projects for various LNG facilities and resource production in development worldwide.
Major liquefaction plant projects are under proposal in Eastern Australia, Offshore Australia, Western and Eastern Canada, Alaska, the U.S. Lower 48, Mozambique, Nigeria, Tanzania, Djibouti, Equatorial Guinea, Congo (Republic), Papua New Guinea, and Russia.
Liquefaction plants are under construction in several countries. Nine plants will start construction in the U.S. in 2019, with a tenth starting in 2020. Russia will construct three plants in 2019, while construction of a plant in Malaysia and Indonesia will start in 2020. Mozambique will begin construction of a liquefaction facility in 2022 (with approx. 75 Tcf. of recoverable natural gas).
Several receiving terminals began construction in China and India in 2018, and more are planned to start in 2019 and 2020.
No fewer than ten European countries without an existing large-scale LNG import terminal propose to construct terminals, five of which have start dates set for 2019.
While proposals may be delayed or, in some cases, not pursued, these proposals and construction projects illustrate a vibrant, developing future for the LNG industry, which will continue to grow for decades to come.
For a further look into these developing frontiers of LNG, investigate these videos and articles:
Africa:
Anadarko: Mozambique LNG Project Overview 2018
https://www.youtube.com/watch?v=ShniplHWZ-I
$500 million mini LNG plant in the works for Rivers State (Nigeria)
Block 2 LNG project, Tanzania: Introduction
Ethiopia, Djibouti sign gas pipeline deal
Equatorial Guinea thinks big on LNG
NewAge taps opportunity in African FLNG
Asia:
Liquefied Natural Gas: the Yamal LNG Project
https://www.youtube.com/watch?v=SJdvcINRlJM&feature=youtu.be
Novatek plans Murmansk LNG terminal
Project for LNG supplies to Kaliningrad Region
Australia:
LNG Changes Everything For Australia’s East Coast Gas Market
INPEX Ichthys LNG Project
PNG LNG Project | Overview
https://www.youtube.com/watch?v=_RDWD1o71c0&feature=youtu.be
Current trends in LNG, particularly niches in the global market, such as FLNG concepts, which allow increased flexibility as LNG sales contracts move towards shorter terms, play an important role in the overall future outlook of the LNG market. Medium- and small-scale LNG has yet to find a definite place as a value solution for the long term or as a bridge solution awaiting the development of larger production and consumption. While LNG FSRUs have a proven track record and high momentum, FPSOs have had less success following trends of the last several years in the LNG industry, though they may prove ideal for risk-averse international investors in countries such as Angola and Nigeria, where onshore facilities may be considered a risk. The Indian subcontinent is increasing its LNG import capacity as the export capacity of the U.S. is set to more than double by the end of 2019 (reaching 8.9bcf/d), making it the 3rd largest exporter in the world behind Australia and Qatar. Canada will begin exports from the West Coast, which may greatly impact Gulf Coast projects. The LNG fleet of 513 ships continues to grow, with the order book listing 99 additional vessels; nearly 40 vessels will arrive in 2019 and 2020. As the LNG trade has quadrupled over the last two decades and is set to double over the next two, the LNG market has an incredible amount of room to continue to grow as the future unfolds.
FLNG market surges
Before jumping into the specifics about LPG storage, the article will discuss the basics about LPG. LPG is a gas obtained from the refining of crude oil and natural gas processing. LPG is mainly used for cooking, heating and auto fuels. LPG or LP gas is an abbreviation for liquefied petroleum gas. The term LPG is most commonly used to refer to the common grouping/mixture of two of the “light hydrocarbon” family, Propane (C3H8) and Butane (C4H10). Both of these hydrocarbons are gasses under normal atmospheric conditions (1 atm. pressure and ±15 °C). LPG furthermore actually refers to hydrocarbons that can be liquefied under moderate pressure at normal temperatures and include the aforementioned gasses as well as propylene, butylene and isobutane (Green, 2008). The liquefaction process of these gasses generally involves the compression of the gaseous state mixture to condense the gases (Hahn, 2018).
The gaseous, natural state of LPG takes up 250 times the volume of the liquefied product. This allows for efficient and economical transport of LPG via various types of transport methods, including:
This, in turn, allows LPG to easily reach rural areas with inadequate electrical infrastructure (Ezzel, 2016).
As previously mentioned, LPG mainly consists of mixtures of propane and butane. The following table indicates the chemical properties of propane, butane, and a common mixture of 60% propane and 40% butane.
Table 1: Properties of Propane, Butane and a 60:40 Mixture (AFROX)
| Property |
Propane |
Butane |
60:40 Mixture |
| Molecular weight |
44.09 |
58.12 |
49.7 (Avg.) |
| Carbon content (wt%) |
81.72 |
82.66 |
82.15 |
| Hydrogen content (wt%) |
18.28 |
17.34 |
17.85 |
| Carbon: hydrogen ratio by weight |
4.47 |
4.77 |
4.6 |
| The density of the liquid at 15 °C (kg/l) |
0.510 |
0.575 |
0.536 |
| The boiling point of the liquid at atm. Pres. (°C) |
-42.1 |
-0.5 |
-42.1/-0.5 |
| The density of gas at 15 °C and atm. Pres. (kg/m3) |
1.86 |
2.46 |
2.10 |
| The volume ratio of gas: liquid at STP* |
274:1 |
233:1 |
258:1 |
| The volume of gas from 1 kg of liquid at STP (l) |
537 |
405 |
484 |
| The mass ratio of gas: air at 15 °C & atm. Pres. |
1.52:1 |
2.01:1 |
1.716:1 |
| Latent heat of vapourisation at 15 °C (kJ/kg) |
20.43 |
21.27 |
20.77 |
| Vapour pressure at 20 °C (kPa abs.) |
710 |
110 |
500 |
| Sp. The heat of vapour at atm. Pres. (cal/g⋅°C) |
0.388 |
0.397 |
0.392 |
| Net calorific value at 25 °C (MJ/kg) |
46.0 |
45.6 |
45.8 |
| Gross calorific value at 25 °C (MJ/kg) |
49.8 |
49.4 |
49.6 |
| Wobbe number (kcal/Nm3) |
19 000 |
21 600 |
– |
| Limits of flammability in the air (vol% gas) |
2.2 – 10 |
1.8 – 9 |
1.8 – 10 |
| Limits of flammability in oxygen (vol% gas) |
2 – 50 |
2 – 50 |
2 – 50 |
| Max. the flame temperature in air (°C) |
1 930 |
1 900 |
1 900 |
| Max. the flame temperature in oxygen (°C) |
2 740 |
2 700 |
2 700 |
| Max. flame speed in 25 mm tube (cm/sec) |
82 |
82 |
82 |
| The air required for combustion at STP (m3/kg LPG) |
12.1 |
11.93 |
12.03 |
| Air: gas vol. the ratio for combustion at STP |
22.5 |
29.5 |
24.9 |
| O2 vol. for combustion at STP (m3/kg fuel) |
2.56 |
2.51 |
2.54 |
*STP refers to Standard Temperature & Pressure (0 °C and 100 kPa absolute)
A few key influences need to be considered when constructing a bulk storage facility for LPG, which can be safely and effectively stored in a bulk installation.
The location of the facility can, in some cases, greatly influence the properties of the LPG being stored due to the ambient conditions on-site. The vapour pressure of LPG varies according to the temperature of the surroundings, and in areas of higher ambient temperatures, a higher pressure will be required to liquefy the LPG. Figure 1 indicates a graphical presentation of the changes in vapour pressure for propane due to temperature. The graph is derived from the available vapour pressure data (Green, 2008).

Figure 1: Vapour Pressure of Propane at Various Temperatures
As can be seen in the figure above, the difference in vapour pressure between 300K (26.85°C) and 315K (41.85°C) is 10 and 14.3 bar, respectively. Therefore, close consideration should be taken regarding ambient temperatures, as this can be hazardous to the chosen design pressures of the vessels. In other words, higher ambient temperatures will require higher design pressures to ensure a safe design.
Logistics regarding site access and transportability of materials can be another hurdle that has to be overcome when designing bulk facilities. Larger vessels might be challenging to transport as prefabricated since the road, rail, or port facilities might not be able to accommodate them.
These vessels will have to be transported in either prefabricated sections or as material sheets that must be assembled or bent on site. Both options, however, require on-site construction, and therefore, certain allowances regarding plot space allocation will have to be considered for construction of the vessels on site.
Due to their complex design, Horton spheres are usually constructed on-site once they reach a certain size, while bullets can be transported in units or sections and installed or assembled on-site.
In conjunction with the aforementioned logistical constraints, constructability should be taken into account when deciding to build the vessels on-site, whether in sections or from the ground up.
For on-site construction, adequate room for the necessary construction and facilities should be allowed and considered before the decision is made to complete on-site construction. Smaller vessels can be used, for example, like in the case of multiple smaller bullets, but this will, in turn, lead to much more piping and connection materials, whilst the total storage allowable will also decrease to more sections with additional safety distances to adhere to.
When constructing an LPG facility, strong emphasis should be placed on designing it according to the correct and applicable codes and standards in the area/country of construction. These standards will provide an engineer with the correct information and guidance to design an LPG bulk storage facility correctly and, more importantly, safely.
One of the key concerns when designing an LPG bulk storage facility is the correct implementation of safety distances. These govern the required safety distances between storage (pressurized) vessels and other storage vessels, whether it is another LPG storage vessel or another chemical storage vessel. These safety distances also govern the allowable minimum distance between an LPG pressure vessel and the plot borders, roads, etc.
The safety distances limit the overall storage that can be safely stored at a certain facility. Therefore, the use of an internationally accepted standard is very important during the feasibility stages and estimations of possible storage on site. In South Africa, codes like the SANS 10087 and NFPA 58 codes are adequate, and proper sound engineering judgement should be practised when implementing the codes.
When designing the facility, proper investigations should be made regarding the typical composition/ratio of propane to butane should be done to establish the correct design solution for the facility. Table 1 indicates the large difference between the vapour pressures of propane and butane. Should the actual LPG being stored contain more propane than anticipated during the design stage, the vessels could fail due to insufficient design pressures and cause major safety hazards, whilst overdesign could increase the CAPEX of the facility when the propane content of the LPG gas stored is much lower than designed for.
However, during operation, it shall be the operators’ responsibility to ensure that the incoming LPG conforms to the propane/butane ratio according to which the facility has been designed.
The first spherical LPG storage vessels (‘Hortonspheres’) were constructed in 1923 by Chicago Bridge & Iron Company (CBI) and allowed for effective large-volume storage of LPG. (Ezzel, 2016)
The largest benefit with regards to the sphere is its ability to store very large amounts of LPG in proportionally small areas. This ability arises because an LPG sphere has a very large volume-to-surface area ratio. Furthermore, the required wall thickness of an LPG sphere of the same diameter as that of a bullet is much less. LPG bullets can, however, reach extreme lengths (up to 70m), allowing for higher storage volumes.
Large spheres, however, have a large concentrated load (point load) on a small section of the earth, leading to higher groundwork design constraints. Spheres can also not be moved once constructed as they lose integrity during deconstruction (due to a high number of welding points) compared to a bullet that can be split into fewer sections (BNH Gas Tanks, n.d.).
Spheres’ complex designing procedures usually also extend the construction period, but in turn, spheres allow for less piping and connections than multiple bullets (BNH Gas Tanks, n.d.).
Another form of storage (and probably the most common) is the LPG bullet.
Aboveground storage in bullet form is similar to that of spheres. Bullets, however, are usually installed pre-fabricated in smaller units with cases of large (50+m) in length. These have been done in various locations across the world, with some reaching lengths of 70m as in the case of Sunrise Energy LPG Import Terminal (Engineering News, 2014).
Bullets have the advantage of being able to be moved in sections as well as having a more uniformly distributed load across the ground surface due to multiple supports and often multiple (smaller) bullets. Settling occurs less readily, and bullets are, therefore, a safer option in locations with more severe weather conditions (Ezzel, 2016) or challenging geotechnical areas. Bullets can also be transported should it be necessary via minimal sections after vessel deconstruction leading to minimal welded seams and possible weak points after reconstruction.
Regular maintenance can also be completed much more readily in the case of bullets compared to a large sphere, with the possibility of some of the bullets staying in operation during scheduled maintenance, while the use of a large sphere will shut down all operations until maintenance is complete (BNH Gas Tanks, n.d.).
Mounded bullets are bullets that are buried beneath a mound, typically trapezoidal, consisting of sand/ground and a cover of a binding material like asphalt. The mounding is usually also fitted with walls at two opposing ends, with some cases being surrounded by a wall. Mounded or buried bullets are a trade-off between available storage and the necessity to allocate extra civil and mechanical work to accommodate the actual mounding. The use of mounded bullets allows for narrower spacing between adjacent LPG bullets as well as less strict safety distances with regard to other properties in close proximity.
This, in turn, allows for more plot space for the actual storage of LPG. When constructing mounded bullets, however, it is important to consider the gravitational force that the mound material exerts on the bullet’s shell and also on the vessel’s supports. Connections on underground tanks should be located in positions that are easily accessible to operate and maintain.
Plot space constraints (due to safety distances), ambient conditions, site access, tie-in points, and client requirements are important considerations before commencing the design. The available plot space will determine the maximum storage volume of LPG due to the safety distances and applicable standards, as mentioned earlier.
Further considerations will include the other decisions mentioned earlier in this article. These will include practicalities regarding construction and typical incoming gas composition and location.
Once all of the aforementioned and other project-specific decisions have been made and sound engineering practice and judgement have been exercised by experienced professionals, the decision can be made on the type of storage vessel and the amount of LPG that the facility can accommodate. Each design will, therefore, be unique, based on specific site requirements, and not based on previous projects and/or designs.
Ezzel, G. (2016, November 14). LPG Storage Bullet Tanks vs. LPG Storage Spheres / ‘Hortonspheres’. Retrieved from TRANSTECH ENERGY: https://www.transtechenergy.com/lpg-ngl-storage-news/lpg-storage-bullet-tanks-vs.-lpg-storage-spheres-/-hortonspheres
Hahn, E. (2018, July 05). What is LPG? Liquefied Petroleum Gas – Propane. Retrieved from ELGAS: https://www.elgas.com.au/blog/492-what-is-lpg-lpg-gas-lp-gas
AFROX. (n.d.). Liquefied Petroleum Gas. Retrieved from AWS Group: http://www.awsgroup.co.za/data/L.P.G.pdf
Green, D. &. (2008). Perry’s Chemical Engineer’s Handbook, 8th Edition. Kansas: McGraw Hill.
BNH Gas Tanks. (n.d.). LPG Horton Spheres. Retrieved from BNH Gas Tanks: file:///Volumes/GoogleDrive/My%20Drive/EPCM%20-%20Gerhardo/Articles/LPG%20Comparison%20Research/LPG%20Horton%20Sphere.webarchive
Ezzell, G. (2016, November 14). NGL & LPG Storage Infrastructure News. Retrieved from Transtech Energy: https://www.transtechenergy.com/lpg-ngl-storage-news/lpg-storage-bullet-tanks-vs.-lpg-storage-spheres-/-hortonspheres#
One of EPCM’s major focus areas is modularization for African hydrocarbon pipelines. As a company, EPCM services the whole African continent. From the beautiful beaches of Cape Town in the South to the rocky outcrops and rift valley as far north as Djibouti.
Being very experienced in delivering projects in Africa, EPCM also understands how to make our lives easier in these areas. One of the major ways this can be done is to understand modularization. Although it sometimes costs a little bit more from a CAPEX perspective to skid mount certain equipment, it saves all this and more during construction.
EPCM started as an oil and gas business and has recently expanded into other chemical and industrial process plants. Its core is built on years of cross-country oil and gas pipelines and tank farms. Thus, EPCM is very familiar with remote locations, changing construction environments, and stranded infrastructure that needs to be supported.
When considering modularization for hydrocarbon pipelines, EPCM developed three levels to better define and understand the process.
The first level of modularization is where the complete unit can be supplied in modular format—the unit is completely prefabricated in the workshop and delivered as a single unit to the site. From a modularization perspective, this is complete modularization. However, this is not always possible, as location and logistics play a major role.
The second level of modularization involves skids made up of a certain facility. The skids are then shipped to the site and assembled to create the final unit. Although this is not complete modularization, it also works well and considers logistics and location.
Level 3 of modularization is where no skids are manufactured. The equipment and materials are sent to the site individually and assembled on-site. The level of modularization does, however, have certain OEM (original equipment manufacturers) components skid mounted and supplied to them from the OEMs in this format.
In this article, EPCM will discuss the major items that can be supplied in modular format for hydrocarbon pipelines.
One of the major components of any hydrocarbon pipeline is the pump stations. These stations move the product from point A to point B. Although it sounds like a simple task, there’s much more to it. Depending on the pipeline’s length and diameter, several pump stations might work together to move the liquid fuel through the pipeline. In most cases, a pump station would consist of at least two large pumps; one would always be running, and the other would be on standby. Where two pumps cannot meet the demand of the pipeline, it can be increased to 3 pumps, with two running and one on standby. For the pumps to have the correct inlet pressure called NPSH (Net Positive Suction Head), the pump station would either have small booster pumps feeding them, or the static head of the tanks would be enough to provide the larger pumps with enough pressure. Another important component of a pump station is understanding what drives the pumps. When the pump station has electricity nearby, it would be the cheapest option to connect to the existing power grid. This will then require large electric motors to be fitted to the pumps and connected to the power grid. The typical electric power needed for large pipeline pumps would be 1MW per pump. Even with electricity, the pump station would still need backup power; in this case, one or two backup generators would be included in the pump station design. These generators would be designed to start automatically if the pump stations have a power trip. In very remote areas without power, pump stations can be designed to run directly from diesel motors. Thus, the pumps are not connected to an electric motor powered by the generator but directly to a diesel-fired engine. This would reduce energy losses but would then be very limited to future power connections as the utility companies expand to cover the remote areas.
Although pump stations have a few more components, this article focuses more on their modularization and will thus only discuss the major components.
When we look at the pump station design, you have a few levels of modularization. Level one would be a complete modular pump station with all its components. You would have a plinth, electrical, and pipeline connection points available on site. The pump station would arrive as a complete skid or even a containerized solution on-site and would then get connected. This would be the perfect world of modularization, and in many cases, it can happen exactly in this fashion. Typical examples of pump stations that work this way are smaller ones that can fit everything into a container (or, worst case, an abnormal load). Larger pump stations can also be used – these are usually situated directly next to the ocean, where a large vessel could transport the station and drop it into position without driving on any roads. Unfortunately, in Africa, you do not find many of these perfect locations. When level one modularization does not work, you can move on to level two. 
Level 1: Complete modular pump station
In level two cases, you split your pump station into multiple skids. So, you would, for instance, have the pump already connected to the electric motor skid mounted and ready to slot into its position on site. One of your pumps and its motor would be skid mounted and fit on the back of the truck delivering the pump. Your inlet piping and booster pumps would be another skid already welded and assembled in the workshop. Your outlet piping and metering would form another skid that can be assembled with the rest of the pump station. The skids would be delivered and fitted like Lego blocks to assemble the pump station. This is a very practical solution for Africa and is used regularly on cross-country multi-product pipelines. In certain cases where pump stations are close to existing towns with skilled resources, a level 3 modularization could also work.
Level 3 modularization is the least amount of modularization. This is mostly done where skills exist around the facility where the pump station would be installed. Most items would be bought as separate loose-standing items installed on-site. A skilled workforce would have to assemble and build this pump station. The area where modularization would still occur would be, for instance, the generator sets – the contractor on-site would get a complete generator with the engine and generator already assembled. He would probably not try to fit actuators to valves, and the pumps would already be fitted to the electric motors and laser-aligned by the OEM (Original Equipment Manufacturer). He would thus do most of the assembly and even welding on site as part of his construction and not have skids that he would assemble.

Level 3: Modularization.
All three levels of modularization can work for pump stations in Africa, but the strategy would have to be decided during the design and planning phase of the project. Using BIM (bill information modelling) principles during the design of these stations would help the team identify the level of modularization needed.
Compressor stations are very similar to pump stations but are used to move gas from one point in a pipeline to the next. The big difference between gas and liquid is that liquids cannot compress, and gas can. In gas hydraulics, the compression factor thus needs to be taken into consideration. From an infrastructure point of view, compression stations are very similar to pump stations and have the same general layout. The gas that enters the compressors needs to be clean to prevent damage to its structural integrity.
Furthermore, when gas is compressed and the pressure increases, the gas’s temperature rises. This means that, usually, after the gas has passed through a compressor, it has to be cooled down to a temperature that falls within the system’s design limits. Compressors can be electrical, diesel, or gas-driven, but gas is usually preferred owing to its cheaper burning costs.
As discussed in the pump station section, gas compression stations could also be executed using either of the three levels of modularization. Level one would be the best for small stations that can fit on the back of a truck, whereas levels 2 and 3 would be applied to larger stations depending on the location and the skilled resources in the area.

Level 2 and 3 combined: Compressors to be skid-based, etc., piping to be installed onsite
Customer metering stations are most commonly used in distribution networks. You would have the large transmission pipelines with their metering systems used for leak detection and billing purposes. Then, you would have a distribution network with hundreds of small users all using gas, for instance. The gas would thus be taken from the transmission pipeline, the pressure dropped using a pressure-reducing station (PRS) and then fed into a distribution network running at a lower pressure. At each of the customer sites of the distribution network, you would have CMS stations that measure the amount of gas the customer uses, and the gas company bills them accordingly. These small CMS stations could have one or two legs depending on the client’s availability requirements. CMS stations can easily be skid-mounted or containerized and shipped to the site. From a gas company perspective, standardising these units makes a lot of sense as they often have to maintain meters and exchange spares.
CMS stations could thus be modularized using level 1 or level 2. In some cases, contractors still prefer to build them on-site, but this is becoming less common as technology and logistics improve. One thing to consider during these installations is that the meters sometimes have a long lead and might have to be slotted in at the end of the fabrication or even on-site.

Level 1: Skid base metering installation

Level 2: Spool piece metering installation
As with CMS stations, the PRS station is used in transmission and distribution networks. It can be used for any product, but most of the time, it’s used for gas networks. When a gas pipeline needs to drop the pressure, they install a pressure-reducing station. As with a CMS station, it can have a single or double leg. Most customers prefer to have double-leg stations to improve availability. These stations are usually designed to have a control valve in each leg with a shutoff valve downstream from the control valve. The shutoff valve is set at a pressure slightly higher than the bottom end of the control valve – if it reads at a higher pressure, the shutoff valves close, and the gas is directed to the alternative leg. This way, the problem in the original leg can be sorted out before it’s used again.
Depending on the gas pipeline, PRS stations can be large installations. In many cases, the gas needs to be heated before the pressure can be dropped. This is due to the Joule Thomson effect, which reduces the temperature of the gas when the gas pressure is reduced.
From a modularization point of view, the small PRS stations can most certainly be skid-mounted or even containerized and sent to the site. Thus, level one would work very well for the small gas pressure-reducing stations.

Level 1: Skid mounted PRS installation
As the size of the PRS station increases, it might be necessary to move towards levels 2 and 3 of the modularization process. In two-leg stations, each leg could be spool pieced and sent to the site. On-site, the two legs get assembled and connected to the rest of the installation. It might be that the heating skid would have to be installed separately and then connected to the whole system.
As with most of the skids discussed in the document, many factors will influence the level of modularization. But standardizing the design and trying to skid mount as much as possible makes a lot of sense for pressure-reducing stations.
Cathodic protection is a very specialized area of cross-country pipeline design. Many factors, such as soil resistivity, stray currents, proximity to existing power lines, pipe area and material, and pipeline coating, play an important role in designing a cathodic protection system for a pipeline. Two major cathodic protection systems can be installed when all factors are considered. The first one is called ICCP (Impressed Current Cathodic Protection). The ICCP system uses electricity from the grid, solar or generators to drive a current through a TRU (Transformer Rectifier Unit). The TRU converts the AC power to DC and decreases the voltage to the required voltage. The current then flows from the TRU to silicon iron anodes installed into deep wells that will be drilled close to the TRU location. The typical depth of a deep well is about 60-100m. The electrodes then move from the silicon iron anodes through the soil towards the pipeline. If the pipeline has any damage to the coating, the electrodes will collect on the pipeline and prevent it from rusting.
The second cathodic protection system used in pipeline design and construction is the sacrificial system. In this particular case, magnesium anodes would be installed and connected to the pipeline every few hundred meters. They have no electricity connected to them and depend on the natural flow of electrodes from the magnesium anode to the steel pipe. If the pipeline coating gets damaged, the electrode will flow towards the steel, thus protecting the pipe from rusting.
Both systems have positives and negatives depending on the location and specific pipeline design.
From a modularization point of view, both systems can be supplied in modular form to pipelines.
ICCP stations could be supplied as level 1 modularization. However, the complete system would probably be level 2 modularization, as the deep wells and anodes would have to be separately delivered and installed. The whole power supply, TRU, and monitoring device can be containerized and supplied as a complete container or skid. The deep wells would have to be drilled separately, and then the anode tails with silicon iron anodes could be a module that fits into the deep wells.
When we consider the sacrificial system, it would probably have to be installed as a level 3 system, with each sacrificial anode system installed separately. However, you will have a certain amount of modularization, with the test points that can be assembled in the workshop and the anode tails that can be fitted before installation.

Complete installation of the CP system. Combination of level 1 – level 3
When designing a hydrocarbon pipeline, the placement of valve stations is very important. In general, the design codes give good guidance, although they don’t all agree on the distance between valve stations. In the American code, the maximum distance between valve stations for a gas pipeline is about 32km. In the Australian code, they leave it open to the engineer, but in some cases, they go as far as 100 km from each other. In ASME 31.4 that governs multi-product fuel pipelines, they also only give guidance, with authority given to the engineer to make the final decision. They do, however, explain why you have valve stations and where you should look at installing mainline valves.
In summary, the most important reason mainline valves are installed for cross-country pipelines is to keep the amount of product that can be lost during rupture to a minimum. Safety is a major driver when considering valve station placement, and ASME 31.8 gives you classes based on the population around the pipeline. If the area is densely populated, you need to have more valve stations compared to when the area is not populated. Environmental impact is another major driver of mainline valve placement. For multi-product pipelines, ASME 31.4 requires mainline valve stations to be placed on either side of a river crossing or wetland to ensure minimal spill if a rupture occurs.
The normal design of a mainline valve station usually has a large full-bore ball valve installed in the line. This allows the pipelines to still be pigged but shut off can easily and quickly be obtained by closing the ball valve. Depending on the location and control philosophy, the mainline valve can be activated or not. If the valve is actuated, it can be done electrically, hydraulically or pneumatically. Again, this depends on the product, location and utilities available at the valve station. Another component of mainline valve stations is the bypass line and valve. When commissioning pipelines or sections of pipelines, the bypass valves are used to equalize the system. If the pressure difference is too high between the two pipeline sections, the torque needed to open the mainline valve will be very high, and operators will battle to open the valve. In gas pipelines, when they commission sections and one section has high pressure, and the other is still low, the Joule Thomson effect causes a major temperature to drop in the gas. They thus use the bypass lines to regulate the pressure and flow to prevent damage to the mainline valve.
Mainline valve stations can be buried under the ground with extended spindles, installed into a valve pit, or raised above the ground with 5D elbows as needed. The pipeline engineer selects the correct layout for a mainline valve station and should consider several factors when designing it.
Modularization of mainline valve stations would always be a good idea. The remoteness and size of these installations make them a perfect fit for modular fabrication. Depending on the size of the bypass line, mainline valve stations could either be modularized at level 1 or level 2.
When the level 1 modularization principle is used, the complete valve station, including the bypass line, actuator, and instrumentation, would be installed in the workshop, and the complete assembly would be transported to the site and installed.
Level 2 would allow the mainline valve station to be installed using a few spools that get welded together on-site. Most of the assembly would be done in the workshop, with some final welds done in the field.
In certain cases, the contractors might choose to use level 3 modularization, but we would not recommend this unless they have a specific reason this works better for the exact location.

Valve station
The control room of a pipeline forms the heart of the operations. From this room, the pipeline owner can inspect the pipeline’s operations and control various items on the pipeline. The control rooms work with the fibre network to control all pumps, compressors, valves, and storage facilities. It has several alarms and warnings to ensure the system is functioning as it should. A lot of development is going into improving the user interface, and recent developments include mobile applications to control pipelines and plants. With the movement from voice to data, data centres are becoming increasingly popular to lump with control rooms. These data centres thus store and process all the pipeline data. With clever tools like Watson, the data can now be processed into meaningful patterns to improve pipeline operation and maintenance.
Depending on the size and location of the control room or data centre, these items are regularly modularized. Both data centres and control rooms are made up of hundreds of small electronic components talking to each other. It would thus be very difficult to assemble all these components on-site.
Although control rooms are mostly in existing buildings, the bulk of the components are assembled in workshops, and modules are sent to the site to fit into existing buildings.
This market is mostly dominated by large international companies that offer a complete solution to the problem and all their equipment.
Control room and data centre equipment would mostly be installed using level 1 or level 2 modularization, and we would also not recommend using level 3 modularization for these systems.
Pig launchers and receivers must be installed to clean, commission, or inspect pipelines. Pig launchers and receivers are usually installed at pump stations or compressor stations. The norm is to have a pig launcher and/or receiver for every 100km of pipeline. However, these days, the latest intelligent pigging technology seems to collect up to 200 km of pipeline inspection information in one run. Intelligent pigging is governed by the design codes and the laws of the country where the pipeline is installed. In most cases, pipelines must be pigged every 5 years to inspect wall thickness and ensure they are still safe to operate. If pipeline companies find defects during the pig runs, they have to repair them to ensure the integrity of their pipeline is still intact.
The physical pigging station is not very complex but forms an important part of the pipeline. Pigging facilities are usually above-ground installations, and, in many cases, especially at intermediate pump/compression stations, the launcher and receiver are fenced in the same facility. The way a pig launcher works is it uses the product in the pipeline to propel the pig, pig stations thus have a barrel-like a rifle that has a door on the one side and is connected to the pipeline on the other side with a double block and bleed valve between the barrel and the pipeline. It then has a kicker pipeline that directs some of the product behind the pig to propel it forward. Once the door is closed with the pig inside the barrel, the valve at the kicker line opens, and the product propels the pig into the pipeline.
Pig launchers and receivers are perfectly suited as modular components in pipeline construction. In many cases, pipeline companies choose to have the launchers and receivers mobile, moving them from one scraper station to the next. Quick-opening doors are also a very nice extra, and if the budget allows it, we would recommend adding them to the design.
In most cases, pig launchers and receivers are supplied as level 1 modules that the pipeline contractor can install as a whole.
You can, however, also do a pig launcher as a level 2 modularization. The best split between the two skids would probably be to do the launcher barrel, door and valve as one skid, have the kicker line and its valves as the second skid, and assemble the skids on site.
If the project wants to investigate a level 3 modularization, it would probably be the best option to completely fabricate the launcher on site as it does not have many components that will fall into a level 3 modularization.

Level 1: Skid-mounted pig launchers and receivers

Level 2: On-site assembly of launcher/receiver
Communication has always been a challenge for cross-country pipelines. In the early years of pipeline design and construction, they would only dream of having all the ends of the pipeline talking to each other. As technology improved, pipelines started pushing towards different communication methods, from standard telephone communication to radio to fibre optic. These days, most pipelines either have fibre optic installed or are busy looking into retrofitting fibre optic lines into the pipelines. The fibre optic cable is installed in a duct on top of the pipe. The cable usually has about 32 fibres that can be used for communication. In general, a pipeline communication only uses a few of these fibres; the remainder then gets sold to the telecom companies, and the fibre line becomes a second income for the pipeline company. The fibre optic cable uses light signals sent via the fibre to give signals as needed between the ends of the pipeline. By using fibre optics, the pipeline operator can give signals to open and close valves, shut down pumps, and provide a time of arrival for products, for example. The latest technology with fibre optics is called intrusion detection. The fibre uses acoustic sensing to detect interference in the pipeline and can pinpoint where the intruder is digging or driving over the pipeline. This is especially helpful in areas where 3rd party intrusion is high, like West Africa and Mexico.
The fibre optic system will run for the full length of the pipeline. The duct that houses the fibre is installed during the construction, and the fibre is blown in afterwards. This way reduces the damage caused to the fibre during the pipeline installation. Inspection pits are installed every few hundred meters. When the intrusion detection systems are installed, a black box gets added to the fibre installation every few kilometres. This handles the acoustic sensing of the fibre system.
Although fibre is essential to ensure communication on pipelines now and into the future, it’s not a very modular installation, and most fibre optic systems would probably be installed using level 2 or 3 of the modularization process.
Filter skids are used widely in the hydrocarbon pipeline industry. In certain industries, like the aviation industry, the cleanliness of the product must be maintained. In general, most pipeline systems are designed to have a filtering system before they enter a facility and as they move to the next portion of the facility. Filter systems are also very common in protecting specialist equipment. In gas pipelines, for instance, the gas is filtered to less than 2 microns before it can power the gas turbines, as any large particles can damage the turbines. Filter skids are often seen before compressor stations to ensure compressors are not damaged. During pigging operations, most of the dust and debris in the pipelines are removed utilizing a pig, which needs to be removed from the system at some stage. Filter skids are perfect for this, and as part of the pigging exercise, they are usually connected to the kicker lines at the pig receiving facilities. When gas is found at wells drilled in the ground, it’s usually wet and has particles trapped in it as part of the stream. Filtering and dehydration skids work perfectly to clean up the gas before moving it into the gas-gathering network. The most common filter skids use cyclone filters to remove the larger particles and then use candle-type filters to remove the smaller particles. When dehydration is needed, desiccant dryers are often employed to remove the water from the system.
Filter skids are perfect for modular fabrication and installation. Although they can also get relatively big, most of the time, a typical filter skid can fit onto a truck and be transported to the site. Thus, level 1 modularization would work very well when it comes to filter and dehydration skids. In some cases, contractors might choose to go with level 2 modularization due to size or location, but you would seldom see a level 3 modularization approach taken on remote filter skids.
Heating skids are most commonly used in gas applications, heavy fuel oil, and crude oil applications. When the pressure of a natural gas pipeline or system is dropped, the Joule Thomson effect also drops the system’s temperature. The rule of thumb for these calculations is 0,5 degC for every 1 Bar pressure dropped. Heating skids are thus very often used before pressure reduction stations are installed. The most common heating skids use water bath heaters that get heated by burning the gas or using electricity. The water bath heater heats the gas to the required temperature before the pressure drop reduces the temperature again. In some of the latest PRS (pressure reduction station) designs, the energy from the pressure drop is converted into electricity, which is then used to power the heating system. Another application where heating skids are frequently used is HFO (heavy fuel oil) installations. As with crude oil, the product does not flow easily, and if it’s not heated, the viscosity blocks the pumps and filters. Heating skids are used in this particular application to keep the product at the correct flowing temperature. With certain pipelines that transport waxy crude, the whole pipeline must have heating pads or stations to ensure the product can flow as required. Heating skids play an important role in the oil and gas industry and should be engineered correctly to ensure the system’s integrity.
Modular heating skids are very common and can be skid-mounted or containerized. Thus, heating skids would be great for level 1 modularization but could also be modularized up to levels 2 and 3 as needed.
During the compression of natural gas, the reverse Joule Thomson process occurs, and the natural gas is heated as the pressure increases. Usually, aftercoolers are installed downstream from gas compressors. These aftercoolers are usually part and parcel of the compressor skid you purchase from the OEM compressor supplier, and they specify the outlet temperature from their skid. It’s thus already modularized as part of the compressor package you purchase. Aftercoolers are also used to exhaust the gas of engines or burners. Burners often have waste heat that is then recovered by boilers or condensers. Condensers or boilers are also basically aftercoolers; they take the heat produced by something and convert it into a different phase by cooling it down.
An additional cooling technology, cryogenics, takes cooling to the next level. Cryogenics occurs when products are taken below 0 degrees C. At a temperature of -161 degrees C, natural gas changes from gas to liquid in atmospheric conditions. The latest trend in gas pipelines is to install small liquefaction plants on the pipeline that liquefies the gas. Once the gas is liquefied, it’s moved to different locations where pipelines cannot reach. LNG (liquid natural gas) is the process of liquefying natural gas. LNG consists of the liquefaction process, where gas is turned into LNG, and the regas phase, where the LNG is turned back into natural gas. The liquefaction and regas skid work perfectly in the modular form.
When cooling and cryogenic skids are evaluated, both work well with level 1 and level 2 modularization. Level 3 could work for certain applications, but it would overcomplicate the site construction process and potentially delay the project.
From a very young age, we meet a large number of new people. It starts as early as pre-school, when small children get enrolled and suddenly have to remember names, including all their new-found friends or enemies’ names…
As the years tick over, it’s primary school, high school, university and eventually the workplace. The reality is that many people arrive to start their working careers and still do not have a process for remembering the names of people they meet.
Have you ever wondered why you can remember the names of your friends from primary school but cannot remember the name of the person you were introduced to five minutes ago? The reason for this is that your brain is a large network of connections. The more times you repeat a certain name or play with a certain friend, the better and longer you will remember that name.

In both personal and professional contexts, it is crucial to recognize the significance of a person’s name. While it may seem like just another name to you, it holds deep meaning for the individual you are meeting for the first time. By showing that you remember and respect their name, you can positively influence that person’s perception of you and potentially secure important business deals.
Seeing that we have now established the importance of remembering a person’s name, this article will strive to give you some basic techniques for remembering the names of people you meet.
When you meet a person for the first time, and they tell you their name or introduce you to somebody who pronounces the name of the person you are meeting, ensure you first focus on the name itself. Look the person directly in the eyes and clear your mind of anything other than the person you are meeting and their name.
Once you hear their name and see them in front of you, the easiest way to remember it is to connect it to another person with the same name you have known for years. For example, if the name of the new person you meet is John and you have known John for years, connect that person to John. If you can find any resemblance to John, even if it’s only the colour of their hair, try to focus on that and make the connection. After you have made the connection, try to repeat the connection in your head a few times and focus on the resemblance that makes you think about the other John you have known for a long time.
It could, however, happen that you are in a situation where you meet someone and do not know anybody with the same name. This often happens when you are in a new country where the common names you are used to are not used regularly. You would thus have to find a new way of remembering the name of the person you have just met. A good technique to use during these encounters would be to connect the name of the person you have just met to something that makes you think of the name. For instance, if you meet a person named Donald, you might think about Donald Duck. Pictures and photos are a lot easier to remember than words or names. Every time you see this person, think about the picture of Donald Duck and find a resemblance to Donald Duck somewhere on that person. Perhaps you imagine Donald Duck sitting on his head, or when you look at his face, you see something similar to Donald Duck. It could be anything when choosing something to connect this person to what reminds you of them. The more colourful and weird, the better your chances of remembering it. Another thing to remember is that this technique helps YOU remember – please don’t go and tell Donald that you imagine Donald Duck on his head every time you see him! This might not end well for you even though you remember his name…
Now that you have a technique to remember the name of the person you have just met, it’s important to strengthen the connection. If you only do the exercise once, the chances of remembering the person’s name for a long time would be small. It would help if you used repetition to strengthen the connection in your brain. The best way to do this is to use the name, and every time you see the person, greet him or her using that person’s name. Remember your connection to the person in your mind and repeat it every time you see the person. Even if you have just met the person, try to repeat his name a few times during the first encounter. This will strengthen the connection and help you remember his or her name for years.
You might also be in a meeting or lecture where you have many names to remember and cannot make your connections quickly enough. In this case, a good way to do it is to write down the names of all the people you meet in the order they are introduced to you. If they give you their business cards, you can also arrange them on the table when you meet them. Once you have gathered and recorded all the names, you can then take your time to follow the same process discussed above to form your connections.

Like everything in life, you might not perfect the techniques the first time, but you should get the hang of it after a few attempts. The best way to improve yourself in remembering names is to practice the techniques until you have a winning formula that works for you.
Now that you have a few tools to remember names, you can comfortably enter the industry and meet new people. You will also start to see how your new-found skill will impact securing and building long-term relationships.
LPG has dramatically impacted our world since its discovery in 1910 by Dr. Walter O. Snelling. It changed how we cook, heat our homes, drive our cars, and store our food in a cool environment. However, LPG can be destroyed if not properly handled, stored, and managed. To enable us to do all this safely, international and local codes and standards have been developed to provide legislation and guidance to designers, distributors, operators, etc. This article compares the site layout guidelines for bulk LPG storage between the NFPA (National Fire Protection Association) 58 and SANS (South African National Standards) 10087 3 codes and standards. This article only intends to indicate major differences when designing a system. Reference should be made to the original codes and standards. Specific project requirements were not included in this discussion.
NFPA (National Fire Protection Association) is a global non-profit organisation that has developed codes and standards for usage and adoption by governments and many institutions worldwide. Many of these codes and standards are also used by the South African government as part of the SANS suite of standards enforced to be used as a minimum requirement on South African installations. NFPA 58 has been developed as an industry benchmark for safe bulk LPG storage, handling, transportation, and use. NFPA 58 mitigates risks and ensures safe installation, preventing failures, leaks and tampering that could lead to fires and explosions.
The South African set of codes and standards for LPG installations is based on various British standards, NFPA publications, and international best practices.
SANS 10087 is divided into several different parts. Part 3 covers the bulk storage of LPG and will be compared with the NFPA 58 standard in relation to plant layout requirements.
When planning the layout of a bulk LPG storage facility or a single tank, the SANS 10087 part 3 and NFPA 58 standards can be used as a guideline for executing the design planning and layout of the facility correctly.
The location of the bulk storage containers is a major component that will guide the overall layout of the facility, as well as the safe maximum storage volumes that fit the plot area in terms of the standards. In this section, the placement of storage containers will be discussed. The layout constraints will prescribe the maximum container size and, therefore, the maximum quantity of LPG storage allowed on the site, subject to environmental impact and major hazardous installation constraints. Only the placement of the container is discussed below, along with other constraints outside of the scope of this article.

Figure 1: Comparison between NFPA58 and SANS 10087-3 for storage container locations.
The comparison was summarised to explain the differences between the codes. The code references in the brackets refer to NFPA 58 2014 Edition and SANS 10087-3 2008 (Edition 4).
Regarding bundled areas around the above-ground storage containers, a conflict in recommendations is perceived at first glance. When studying this, both codes recommend protecting adjacent areas from the accumulation of heavier-than-air explosive gasses and directing gases away from unprotected areas by using slopes or vapour barriers/dykes.
It is recommended that you consider both codes to ensure that you comply with safety regulations.
Spacing of storage containers is important for the safety of the container next to it and general facility safety. The following section will deal with the different types of LPG storage methods and which codes and standards are applied to each situation.
NFPA 58 Code specifies that ASME Containers are to be used as bulk storage containers. The SANS codes allow ASME-approved container design and PD 5500, formally a widely used British Standard BS 5500, in the design fabrication and inspection of (unfired, fusion welded) pressure vessels.
When considering aboveground/mounded tanks, both codes give similar distances to property boundaries (between 3m and 15m) depending on the container size.

Figure 2: Comparison between safety distances specified by NFPA58 and SANS 10087-3 for underground/mounded LPG containers.
As per the previous comparison in Figure 1, the safety distance comparison above also indicates similar requirements, and it is recommended that you follow both code recommendations for good engineering practice.

Figure 3: Example of a buried (underground) tank – as shown, the tank has a concrete barrier around it and should have proper ventilation and liquid gas collection, like at the bottom, following the standards and codes to remove any LPG spillage (for the prevention of fluid accumulation and volatile environment creation).

Figure 4: Example of mounded storage tanks—Compared with above-ground installation, safety distances are minimized. This method consists of semi-burying tanks so that a distance from the centre of the tank to a length above the tank is covered with either soil or concrete.
The following section deals with the codes and standards for above-ground storage tanks. Both codes and standards use safety separation (distances) methods related to the LPG bulk storage container size volume. NFPA is more conservative, with larger separation distances for containers larger than 114m3 increasing from 15m and specifying distances up to 122m for containers exceeding 3785m3. SANS codes limit the safety distances to 30m for containers exceeding 265m3.

Figure 5: Comparison between safety distances specified by NFPA58 and SANS 10087-3 for above-ground LPG containers.
While both codes give similar safety distances up to 265m3, SANS is more conservative with smaller containers, and NPFA is significantly more conservative with large containers.

Figure 6: depiction of an above-ground LPG storage container installation. In this case, the installation was an appropriate distance away from buildings, loading bay etc. hence why there are no bunds, dykes etc. installed.
The following section deals with LPG bulk storage grouping. Both NFPA 58 and SANS 10087 deal with safety separation distances and surrounding structures, such as dikes and curbs, that collect flammable liquids with a flash point below 200 °F (93.4°C). The code also limits the number of containers in a group, as depicted in Table 6.4.1.2. SANS 10087 has a similar requirement but includes a firewall if more than six vessels are used in the group.

Figure 7: Comparison between safety distances specified by NFPA58 and SANS 10087-3 for Groups of LPG containers.
Once again, some common rules apply in this comparison, but one standout is that SANS shows more detail on separation distances when you look at other fuels (Oxygen in particular). This eases the process by not jumping to different codes.
The table below was taken from page 33 of the NFPA 58 standards. The maximum number of above-ground containers in a group is limited by the type of fire protection provided. Each container has a size of 12,000 galloons (45m3 ) or more:

Figure 8: Table showing the maximum number of containers in a group and their separation distances.
The table below from page 32 of the NFPA 58 standard shows the separation distances between mounded, above-ground containers or between containers.

Figure 9: Table showing the storage container separation distances.
NFPA 58 contains no visual layouts, but the tables are easy to read.
In the following section, you will find most of the SANS separation distance layouts and tables. This makes it much easier to find the information needed to ensure the correct standards are followed with your new plant layout.

Figure 10: Table showing the separation distances for: “adjacent containers, important buildings, groups of buildings or adjoining property that can be built upon.”

Figure 11: Depiction of the minimum separation distances of LPG vessels below 200 tonnes. A firewall with a resistance rating of at least 2 hours interrupts the line of sight between the unprotected (uninsulated) section of the containers. Sources include Liquefied flammable gases, flammable liquids and oxygen storage (Page 17, SANS 10087-3).

Figure 12: Depiction of a storage facility plant layout section, with recommended safety distances for above-ground combined fuel/gas facilities (Page 36, SANS 10087-3).

Figure 12.1 shows the recommended safety distances for gas ONLY fuel installations.

Figure 12.2: Continuation of Figure 12.1.
Figures 10 through 12 show that using SANS 10087-3 is more user-friendly. Whether you are designing a plant layout consisting of white products and LPG or only an LPG site, there are enough safety distances to do so.
Please remember to refer to the latest codes to ensure you comply with the rules and regulations. Although much does not change from version to version, applying good engineering practice to any design will still be advantageous.
To ensure the safety of personnel and assets on site, careful planning should be taken into account when designing and installing piping correctly, using the recommended type of material following the standards and codes. This will reduce the piping’s failure during its life span/facility. NFPA 58 states that certain piping, either indoors or outdoors, has certain pressure requirements. SANS 10087 has a similar requirement but has an in-depth scope of the material that can be used compared to that of NFPA 58.

Figure 13: Comparison between NFPA58 and SANS 10087-3 regarding piping installation requirements.
The figure below is a continuation.

Figure 14: This is a continuation of Figure 13, which compares NFPA58 with SANS 10087-3 regarding piping installation requirements.
NFPA 58 standards and codes state that cargo tankers transporting flammable liquids must comply with federal DOT carrier safety regulations, including piping and fitments on the road tanker. The standards and codes also include certain safety measures to ensure that LPG is transported safely between the tanker and the container. SANS 10087 standards and codes only state that the tanker’s risk to the bulk storage facility must be addressed and that all truck tankers must carry powder fire extinguishers.

Figure 15: The Figure refers to the general design of an LPG transport tanker.

Figure 16: Comparison between NFPA58 and SANS 10087-3 regarding road tanker loading.
It is clear that NFPA 58, in this instance, has a more elaborate recommendation layout to follow compared to SANS 10087-3. SANS 10087-3 only refers to fire protection protocols, by indicating the hose reel etc. you will need to ensure safety (Figure 17).

Figure 17: SANS 10087-3 Fire protection details. Only firefighting recommendations are listed in the last row, and no mention is made of safety distances.
Each code states the following about rail tanker loading (transfer between containers). Both SANS 10087 and NFPA 58 codes state that a qualified person must always be present during connection, filling and disconnect from the rail tankers to the store facilities.

Figure 18: Comparison between NFPA58 and SANS 10087-3 of rail tanker loading.

Figure 19: Typical design of a rail tanker loading.
The table below was taken from page 34 of the NFPA 58 standard. It shows the point of transfer’s horizontal distances between containers and other buildings etc.

Figure 20: Indication of the safety distance from the transfer point and exposure area.
The original codes should still be read to form your opinion about correct engineering practice. Working with LPG can be dangerous, and to ensure the safety of the personnel on-site and the facility, the SANS and NFPA standards should be followed thoroughly before the bulk storage facility is designed.
The two compared codes and standards discussed in the article are NFPA (National Fire Protection Association) and SANS (South Africa National Standards). Both have similarities regarding the facility’s safety, but the separation distances in some departments could cause you to prefer one over the other. Using the codes and standards will not only help construct a safe bulk storage facility but will also assist with how it is utilized during its life span.
NFPA 58 – 2014 Edition
SANS 10087-3:2008 Edition 4
Micro-Scale Natural Gas Liquefaction Processes: Design and Optimisation: A Literature Study for the Design and Optimisation of Micro-Scale Natural Gas (NG) Liquefaction Processes has been undertaken for the basis of a Masters dissertation on the subject. The content of this report stipulates the design execution plan supporting the final Master’s dissertation.
The objectives of this execution plan were to:
A detailed research study has been completed on existing work specific to micro-scale (less than 275 tones per day or 5 million GJ per annum) liquefied natural gas (LNG) production facilities. Results were analysed, compared and summarised to serve as initial design conditions for proposed process designs.
Due to limited research being available on micro-scale LNG production plants and mixed preferences from different sources on which process technology is most suited for small- or “micro”-scale liquefaction, this work aims to establish what type of process (single mixed refrigeration (SMR) cycles or nitrogen expansion cycles) is most feasible considering production capacities between 13.5 and 275 tonnes per day (0.25 and 5 million gigajoules per annum). The design approach to be implemented is illustrated in Figure 1.

Figure 1: Block flow diagram illustration of the design approach
Optimal process models based on previous work have been identified for SMR and NEC cycles. Process models will be formulated using Aspen HYSYS. Process optimisation will then be applied with the main focus on minimising energy consumption. A cost analysis of operational and capital expenditures will follow to feed into a detailed economic model.
Financial and economic feasibility evaluations will be performed to determine optimal solutions for the production scales considered. Feasibility will be measured in terms of process simplicity, net present value (NPV) and accounting rate of return (ARR) on an identical basis.
The basic engineering design of the most feasible process for a 55 tonnes per day (approximately 1 million GJ per annum) facility will then be conducted. This will form the basis of a generic design that can be adjusted, detailed, and applied in the industry within the proposed production scale range.
The below-tabulated units will form the basis for all conversion factors to be used in the design.
Table 1: Unit Conversion Table
| Value | Mass (tonnes) | Energy (mmBtu) | The volume of LNG (m3) | The volume of NG (m3) | The volume of NG (ft3) | Energy (GJ) | |
| Mass (tonnes) | 1.00 | 1.00 | 53.38 | 2.22 | 1 300.00 | 45 909.00 | 56.32 |
| Energy (mmBtua) | 1.00 | 0.02 | 1.00 | 0.04 | 24.36 | 860.10 | 1.06 |
| The volume of LNG (m3) | 1.00 | 0.45 | 24.02 | 1.00 | 585.00 | 20 659.00 | 25.34 |
| The volume of NG (m3) | 1 000.00 | 0.77 | 41.10 | 1.70 | 1 000.00 | 35 310.00 | 43.36 |
| The volume of NG (ft3) | 1 000.00 | 0.02 | 1.17 | 0.05 | 28.30 | 1 000.00 | 1.23 |
a million British thermal units
The design battery limits are the inlet to the liquefaction process (known as the “cold box” of an LNG plant) and the outlet of the cryogenic heat exchanger(s)/expansion valve(s) before LNG storage. Figure 2 illustrates the design battery limits within the context of an LNG plant block flow diagram.
The battery limits were selected because the liquefaction process design does not significantly change with a change in feed gas conditions. The plant pre-treatment facilities ensure the feed gas is “cleaned” to meet required inlet conditions. Only when heavier hydrocarbons become significant in the feed gas must cryogenic distillation be designed for the liquefaction processes.

Figure 2: Process design boundary conditions (battery limit illustration)
The capacity of the designs will be based on a total available production time of 24/7, 330 days per calendar year (with an allowance of one month of maintenance per annum).
The equipment and valves will be designed for a 50% turndown ratio, allowing for flexibility during changes in market demands and initial ramp-ups.
The critical design conditions for the LNG product are summarised in Table 2. Required LNG product specifications following British Standard (BS EN 1160:1997 Installations and equipment for liquefied natural gas – general characteristics of liquefied natural gas) are listed in Table 3. Industry standards require the LNG product specifications to be within “lean” and “rich” given ranges.
Table 2: Required LNG product conditions
| LNG Product Condition | Unit | Specification |
| Flow low rate | Tonnes per day | 13.5 – 275 |
| Temperature | ºC | < -162 (or below dew point) |
| Pressure | Barg | < 16 barg |
Table 3: LNG product specification (as per BS EN 1160:1997)
| Composition (mol%) | LNG (Lean) | LNG (Average) | LNG (Rich) | |
| Nitrogen (N2) | 0.5 | 1.79 | 0.36 | |
| Methane (CH4) | 97.5 | 93.9 | 87.2 | |
| Ethane (C2H6) | 1.8 | 3.26 | 8.61 | |
| Propane (C3H8) | 0.2 | 0.69 | 2.74 | |
| i-Butane (i-C4H10) | – | 0.12 | 0.42 | |
| n-Butane (n-C4H10) | – | 0.15 | 0.65 | |
| Pentane (C5H12) | – | 0.09 | 0.02 | |
| Molecular Weight | (kg/kmol) | 16.41 | 17.07 | 18.52 |
| Bubble Point Temperature @ 101.325kPa | (ºC) | -162.9 | -166.5 | -161.5 |
| Density @ Bubble Point Temperature @ 101.325kPa | (kg/m3) | 432.7 | 449.5 | 464.9 |
| Higher Heating Value | (MJ/Sm3) | 38.22 | 38.76 | 42.59 |
| Lower Heating Value | (MJ/Sm3) | 34.43 | 34.95 | 38.51 |
| Wobbe Index | (MJ/Sm3) | 50.73 | 50.43 | 53.19 |
The following are general design water and electrical specifications for South African industry standards and will be assumed available.
Table 4: Electrical availability
| Volt | Phase | Frequency |
| 6.85kV | 3 | 50 Hz |
| 525V | 3 | 50 Hz |
Table 5: Conditions for available cooling water
| Cooling water | Value |
| Mechanical design pressure (kPag) | 700 (at grade) |
| Nominal supply pressure (kPag) | 450 (at grade) |
| Vacuum design pressure (kPag) | -85 |
| Maximum available exchanger ΔP (kPag) | 100 |
| Supply temperature (oC) | 27 |
| Max. allowable exchanger outlet temp. (oC) | 40 |
Table 6: Conditions for other available water streams
| Stream | Min Press @ Grade, (kPag) | Mech. Design Press, (kPag) | Low/High Temp’s, (oC) |
| Potable | 400 | 1000 | 10/40 |
| Hydrotest water | TBDa | TBD | TBD |
| Firewater | 800 | 1500 | 10/40 |
a TBD – to be determined
Table 7 specifies the air and inert gas (nitrogen) specifications that are industry standard and easily accessible. These are assumed to be available.
Table 7: Inert gas and air industry standard specifications
| Fluid | Noma Pressure (kPag) |
Normb Tempd (oC) |
Mechc Design Pressure (kPag) |
Mech Design Temp (oC) |
Dew Point (oC) |
| Instrument Air | 700 | 35 | 1000 | 60 | -20 |
| Utility Air | 700 | 35 | 1000 | 60 | 35 |
| Nitrogen (LPe) | 300 | 35 | 1000 | 60 |
a Nominal; b Normal; c Mechanical; d Temperature; e Low Pressure
Design regulations, codes and standards are project-specific and must be addressed during the detailed design of a plant. Site information concerning environmental and climatic conditions is a critical factor and must also be addressed during detailed design. Control and instrumentation design strategies are excluded from this work.
The SMR process, patented as the Prico Process (Fan & Oelschlegel, 1986), was selected as one of the investigated processes due to its simplicity (low number of equipment units and process variables) and popularity for small-scale LNG plants.
Previous work has focused on the design and optimisation of SMR cycles. Key decision variables were found to be the flow rate and composition of mixed refrigerants, partition temperature, and operating pressures before and after compressors. These variables determine the designs of the most important unit operations (compressors and heat exchangers).
A simplified process schematic under discussion is illustrated in Figure 3.

Figure 3: Simplified process schematic of the SMR cycle (Austbo, Wahl & Gundersen, 2013)
Generally, there is always a trade-off between the size of the heat exchanger(s) and the size of the compressor(s). If the heat exchanger size increases (increase in capital cost), the power requirements in the compressors decrease (decrease in operational and capital costs). If the size of the heat exchanger is decreased (lower capital cost), larger compressor(s) are required (increase in operational and capital cost). (Asepulund et al, 2009)
Asepulund et al. (2009) developed a gradient-free optimisation simulation for Aspen HYSYS. Processes were simulated, and the tool was applied to an SMR process to find the total refrigerant flow rate, composition, and refrigerant suction and condenser pressures that minimise the energy requirements.
Austbo et al. (2013) simulated and optimised an SMR process using adaptive simulated annealing techniques. They proposed a constraint handling function utilising process characteristics and compared it with static penalty function formulations. The results showed that the best solution exceeded the previously published results.
Chang, Lim, and Choe (2012) investigated the effect of multi-stream heat exchangers on natural gas SMR liquefaction cycle performance. The liquefaction performance was estimated using a minimum temperature approach (using Aspen HYSYS) and found to be overestimated by the Figure of Merit (FOM: the ratio of minimum work to actual work) value from Aspen HYSYS. Still, a proper heat exchanger design can closely achieve the desired result.
Nogal et al. (2008) developed a new design methodology for mixed refrigerant systems with multi-stage heat exchangers to optimise key decision variables. The method has successfully been applied to an SMR process to minimise shaft power demand for compression. The results showed an 8% improvement in power demand compared with previously published work.
Nogal et al. (2008) also described and illustrated the application of a new optimisation strategy for synthesising mixed refrigerant cycles. It considers single- and multi-stage refrigerant compression, full enforcement of the minimum temperature difference and temperature profiles, simultaneous variable optimisation, incorporation of capital costs in the objective function, and stochastic optimisation (genetic algorithm) to overcome local optima. The results illustrated improved and feasible solutions.
Jacobsen & Skogestad (2013) studied the optimal operation of an SMR LNG process considering disturbances in natural gas flow rate and ambient conditions. Compared with previous work, the compression power was minimised using UniSim for process modelling and fmincon in MATLAB for optimisation. The authors found that the compressor characteristics limit the variations in ambient conditions handled by the process.
Khan & Lee (2013) investigated an SMR process with four compression stages. They minimised and optimised power consumption using MATLAB and the particle swarm paradigm. UniSim was used for process modelling and simulation. The authors found that better results were obtained than when using a deterministic approach for the same process.
Khan, Lee & Lee (2011) minimised the total compression power for an SMR process with four compression stages. UniSim was used for process simulation, and the sequential quadratic programming (SQP) method fmincon in MATLAB was used for optimisation. A stochastic search method was applied to the same problem that Khan & Lee (2013) represented.
Khan et al. (2013) developed a knowledge-based decision-making algorithm based on thermodynamic knowledge and insight to improve the energy efficiency of mixed refrigerant LNG process concepts. The methodology proposes a simple and practical method for selecting the appropriate refrigerant composition. The method was applied to an SMR process and yielded optimised results.
Marmolejo-Correa and Gundersen (2012) discuss different definitions of exergy efficiency and apply them to an SMR process. The authors found significantly different results for various proposed definitions and stipulated the importance of decomposing the exergy into its components (temperature-based and pressure-based). This is important to develop exergy efficiency formulations that properly evaluate the thermodynamic performance of different process designs.
An SMR process using standard refrigeration components was proposed by Neksa et al. (2010) for re-liquefaction of boil-off gas from LNG tankers. Exergy analysis was performed, and process irreversibilities were minimised by manually improving the refrigerant composition. PRO/II was used for process modelling and experimentally verified on a laboratory scale and full scale. Also stated is that process optimisation has not been performed, which indicates room for improved results.
Mokarizadeh and Mowla (2010) used a genetic algorithm to minimise the compression power in an SMR process with two-stage compression. MATLAB was used for simulation and optimisation, while Aspen HYSYS was used to validate the results. An exergy analysis was also conducted to calculate the irreversibility of the individual components.
Xu et al. (2012) investigated the influence of ambient temperature on the optimal refrigerant composition for an SMR process assuming constant pressure levels. Aspen Plus was used for process simulations using a genetic algorithm to minimise the total power consumption. When the composition is not adjusted to account for changes in the ambient temperature, a limited temperature range can be covered without violating the design constraints. A model for the optimal refrigerant composition was proposed using linear regression of the optimised results.
He & Ju (2016) developed a dynamic model applicable to a multi-stage refrigeration cycle and investigated the dynamic behaviours of the process for disturbances in feed natural gas temperature, composition, pressure, flow rate and water cooler temperatures. LNG temperature and compressor power requirements were key criteria investigated. Results indicated that compressor power requirements varied with disturbances, where the LNG temperature returned quickly to the set point.
He and Ju (2011) proposed two different precooling cycles, including propane and R410a, to improve the performance of a simple NEC natural gas liquefaction process. These processes are illustrated in Figures 4, 5, and 6.

Figure 4: Nitrogen expansion cycle (NEC) liquefaction process (He & Ju, 2013)

Figure 5: NEC-Propane precooling liquefaction process (He & Ju, 2013)

Figure 6: NEC-R410a precooling liquefaction process (He & Ju, 2013)
Unit energy consumption was optimised in terms of several operating parameters. An exergy analysis also found that introducing R410a and propane pre-cooling reduces the base case NEC process by 22.74% and 20.02%, respectively.
He & Ju (2014) introduced a novel conceptual design of a parallel nitrogen expansion liquefaction process for the small-scale plant in skid-mounted packages. A thermodynamic analysis was conducted from where the process was optimised using a genetic algorithm.
Although there are some publications on the design and optimisation of NEC liquefaction processes, only a few exist regarding micro-scale processes due to the high energy consumption of the compressors. The Claude cycle refrigerator is commonly used in boil-off gas re-liquefaction applications. This cycle was not investigated as it comprises a three-stage compression unit, turbo expander and three heat exchanger units, resulting in a complex and expensive process. (Hoseyn, & Babaelahi, 2010; Moon et al, 2007)
Cao et al. (2005) compare the SMR and methane-nitrogen expander cycles by optimising the specific power requirements for small-scale LNG processes. Aspen HYSYS with the built-in original optimiser was used for simulation and optimisation. The expander process was found to be the most efficient.
Yin et al. (2008) optimised and compared two LNG processes, a multi-stage mixed refrigerant process and a reverse Brayton process, focusing on minimising the compression power under given conditions. They also studied the capital costs associated with the processes. The authors found that the mixed refrigerant process had the smallest capital and operating costs.
Yoon et al. (2012) applied a genetic algorithm to optimise an SMR process and a dual nitrogen expander cycle for natural gas liquefaction. Both processes use multi-stage compression. Aspen HYSYS was used for process simulation, and MATLAB was used for process optimisation.
He & Ju (2015) four configuration strategies of gas expansion liquefaction cycles (multi-stage expanders, single precooling cycle, regeneration and mixture working fluid) for the distributed scale LNG plant. Sixteen feasible cycles were found using FOM and optimised with a genetic algorithm. A cost analysis was applied to the optimal cases and found that a two-cycle R410a precooling and parallel nitrogen expansion cycles were the most feasible.
Previous research work discussed was analysed, and key process parameters contributing to this study are compared (listed in Table 8). The focus was placed on searching for resources with processes producing less than 500 tonnes per day LNG (the open literature for these micro-scale LNG processes is very limited).
There was a generally lower specific power consumption for mixed refrigerant cycles compared with gas expander cycles. Smaller-scale processes also exhibit a higher specific energy consumption compared with the large-scale processes represented by Asepulund et al. (2009) and Austbo et al. (2013).
Xu et al (2012) and Yin et al (2008) illustrate good specific power consumption for MRC compared with the large-scale processes. Yin et al (2008) and He & Ju (2015) showed good results for gas expansion cycles. Highlighted processes also have LNG production rates which fall well within the scale of this study.
Table 8: Literature findings key parameter comparisons
| Reference | Optimised specific power consumption (kWh x 10-2 /kg LNG) |
LNG flow rate for the optimised case (tonnes per daya) |
| Mixed Refrigerant Cycles (MRC) | ||
| Asepulund et al (2009) | 25.39 | 8640 |
| Austbo et al (2013) | 29.53 | 8640 |
| Khan & Lee (2013) | 38.07 | 0.024 |
| Khan et al (2011) | 42.44 | 86.4 |
| Khan et al (2013) | 43.24 | 0.024 |
| Neksa et al. (2010) | 49.00 | 20.1 |
| Mokarizadeh & Mowla (2010) | 30.33 | 75.24 |
| Xu et al (2012) | 28.15 | 86.4 |
| Cao et al (2005) | – | 1.824 |
| Yoon et al (2012) | 34.82 | 456 |
| Yin et al (2008) | 29.75 | 17.1 |
| He & Ju (2016) | 38.10 | 42.39 |
| Gas Expansion Cycles | ||
| He & Ju (2012) | ||
| NEC Cycle | 60.70 | 0.456 |
| NEC-R410a | 46.89 | 0.456 |
| NEC-Propane | 48.54 | 0.456 |
| Cao et al. (2005) | – | 1.824 |
| Yoon et al (2012) | – | 456 |
| Yin et al. (2008) | 44.91 | 17.1 |
| He & Ju (2014) | 67.05 | 34.88 |
| He & Ju (2015) | 48.83 | 38.36 |
a Daily operation assumed at 24 hours per day (hourly rates given in most literature cases)
The basic design process will be taken from the work of Xu et al. (2012) due to the lowest shaft power consumption found for an LNG production rate below 500 tonnes per day. The two-stage compressor and cooling process are illustrated below.

Figure 7: Two-stage compressor SMR LNG process (Xu et al., 2013)
After the first stage of compression and cooling, the mixed refrigerant stream is partly condensed and separated in a phase separation drum. Upon separation, the gas is compressed and the liquid pumped, where the streams are mixed and passed through the second water cooler before entering the cryogenic heat exchanger. (Xu et al, 2013)
In the cryogenic heat exchanger (or cold box), the high-pressure mixed refrigerant and natural gas are hot streams, while the throttled mixed refrigerant derived from the high pressure is the chill stream and supplies the cold energy for liquefaction (Xu et al., 2013).
Table 9 lists process constraints found for safe and stable operations. Table 10 shows the initial design process parameter specifications (taken from Xu et al. (2013)’s optimised results) to be applied. Other process constraints will be specified as lower and upper bounds during optimisation.
Table 9: Process constraints for the SMR process (Xu et al., 2013)

Initial process simulations will be conducted using the process simulation software package Aspen HYSYS. The objective of this exercise will be to establish the effect of key decision variables (flow rate and composition of mixed refrigerants, partition temperature, and operating pressures before and after compressors) on other process parameters for given constraints. This is envisioned to give insight into selecting process parameter search bounds and a better understanding of process operation before applying optimisation tools.
Table 10: Initial process parameter inputs (taken from Xu et al. (2013))
| Parameter | Unit | Value | |
| Feed flow rate | tonnes/day | 86.4 | |
| Feed pressure | bar | 50 | |
| Feed temperature | ºC | ||
| Feed composition | mol% | Nitrogen Methane Ethane Propane Isopentane |
14.59 20.21 32.94 18.00 14.25 |
| Compressor outlet pressure | bar | 40 | |
| Compressor inlet pressure | bar | 3 | |
| Hot MR temperature at HEX outlet | ºC | -160 | |
| NG temperature at HEX outlet | ºC | -160 | |
| Adiabatic compressor efficiency | % | 78 | |
| Superheat temperature at the inlet of first stage compressor | ºC |
greater or equal than 3 |
|
| Minimum temperature approach of HEX | ºC | 3 | |
| NG pressure drop in HEX | bar | 0.5 | |
| Hot MR pressure drop in HEX | bar | 0.5 | |
| Cold MR pressure drop in HEX | bar | 0.5 | |
| Heat leakage of HEX | % | 0 | |
The optimised case represented by He & Ju (2015) was selected as the basis of the process design for this study due to its low specific power requirement and lower number of equipment units compared with Yin et al. (2008). Figure 8 illustrates the R410a-precooling with a parallel nitrogen expansion cycle process.

Figure 8: Process flow diagram of R410a precooling-nitrogen expansion liquefaction cycle (He & Ju, 2015)
Natural gas flows through two heat exchangers; the first HEX cools the gas down from ambient conditions to -44ºC, whereas the second cryogenic HEX produces LNG at -160ºC. The gas’s pressure is reduced to 2 bar upon exit of the throttling valve. The optimal operating conditions found (therefore, the initial process conditions for this study) are listed in Table 11.
There are two refrigeration cycles. The first, utilising R410a, passes through a two-stage compression cycle with water inter-cooling. Then, the refrigerant passes through an expansion valve to reduce the temperature and pressure. The cold
Table 11: Initial process parameter inputs (He & Ju, 2015)
| Parameter | Unit | Value | |
| Feed flow rate | tonnes/day | ||
| Feed pressure | bar | 50 | |
| Feed temperature | ºC | 20 | |
| Feed composition | mol% | Methane Ethane Propane Iso-butane Na-butane Iso-pentane N-pentane C6-C9b Nitrogen |
92.9 3.54 1.49 0.28 0.34 0.06 0.05 0.03 2.1 |
| Pressure drops in HEXs | bar | 0.1 | |
| Pressure drop in water coolers | bar | 0.1 | |
| Outlet temperature after water coolers | ºC | 40 | |
| Adiabatic efficiency of compressors | % | 80 | |
| Adiabatic efficiency of expanders | % | 85 | |
| LNG storage pressure and temperature | bar / ºC | 2 / -158.2 | |
| Minimum temperature approach in HEXs | ºC | 3 | |
a Normal; b Hydrocarbons with 6 – 9 carbon atoms
R410a goes through a precooler to provide feed gas and nitrogen stream cooling capacity. (He & Ju, 2015)
The second (nitrogen) cycle consists of two compressors (C-1 & C-2) and two water coolers (WC-1 & WC-2), which are then divided into two parts. Each part is booster-compressed (B-1 & B-2), followed by cooling water (WC-5 & WC-6)
to reduce the high-pressure stream temperatures. These streams exiting WC-5 and WC-6 are mixed and cooled in HEX-1 to -44ºC. After that, the nitrogen is divided into two parts again. The stream’s major part (207) enters the first stage expander to reduce its pressure and temperature. The minor part (203) passes through HEX-2 and exits at -110ºC. Then, this low-temperature nitrogen stream enters the expander (E-2) and provides cold energy for HEX-2. Stream 206 from HEX-2 mixes with stream 208. The nitrogen provides cold energy for HEX-2 and HEX-1 subsequently. Compressors B-1 and B-2 are driven by expanders E-1 and E-2, respectively. (Hu & Ju, 2015)
R410a as a refrigerant was proposed by He & Ju (2015) and selected for two reasons: R410a is a common refrigerant, widely available, and the dew point of R410a is lower than that of propane (also a common refrigerant). An R410a-precooling cycle can provide more cold energy for expansion in high-temperature ranges than propane (He & Ju, 2015).
The process has several constraints that ensure safe and stable operation. Key constraints to be applied are summarised in Table 12. Initial process simulations will also be conducted using Aspen HYSYS to investigate the effect key process decision variables have on other process parameters for given constraints. This will give a better understanding of what parameters must be fixed and which must be varied before formulating the optimisation framework.
Various optimisation methods have been applied to design and operate LNG plants. In most published work, the optimisation of LNG processes is either solved using local search methods for a rigorous process model or using an advanced global optimisation algorithm combined with a simplified process model. (Austbo, Lovseth & Gundersen, 2014)
Table 12: Process constraints for the R140a-NEC (He & Ju, 2015)

Figure 9 represents optimisation problem formulation methods and the different algorithms used. Genetic algorithms are most commonly applied for LNG processes among non-deterministic search methods, also known as stochastic search methods. Hybrid approaches have also been developed, and a combination of deterministic and non-deterministic search methods has been used.

Figure 9: Breakdown of optimisation problem formulation methods and algorithms
Alternative approach analysis methods (exergy and pinch analysis) based on thermodynamic principles have also been applied to improve designs or reduce the search space for optimisation approaches (Austbo et al., 2014).
The optimisation will be applied to proposed SMR and R410a-NEC processes, first conducting a Genetic Algorithm (GA) search, followed by a pinch-and-exergy analysis. Heuristics developed for the selection of MRC composition will also be applied.
GA is a global optimisation method. It utilises a search heuristic that mimics the process of natural selection. This heuristic is routinely used to generate useful solutions to optimisation problems. The proposed liquefaction processes to be optimised are highly non-linear programs with many local optima. (He & Ju, 2015)
Figure 10 illustrates the optimisation process framework by applying GA search. The method starts to work by producing an initialisation population. There are several constraints during optimisation that ensure the process operates safely and stably. GA decides whether the constraints are satisfied or not. If the constraints are satisfied, GA calculates the objective function; otherwise, the penalty function is applied. The best population is found when the objective function reaches the maximum or minimum values. The tuning parameters of the GA, given by He & Ju (2015), to be used are listed in Table 13.
Key variables that need to be optimised are compressor in- and outlet pressures, outlet pressures of expanders/throttling valves, refrigerant flow rates and compositions, and split ratio of mass flow rate in parallel expander (NEC cycle). Lower and upper bounds of variables will be developed upon running the first process simulations for given initial process parameters. After understanding the process operation and the effect change in manipulated variables has on process outcomes, search-bound criteria will be established.
The objective functions to be optimised are minimum power/utility consumption and maximum exergy efficiency for a given range of LNG production capacities (13.5 – 275 tonnes/day). Objective functions will be developed during the optimisation. To compare results fairly, simulation criteria will be similar for both SMR and R410a-NEC processes.

Figure 10: Process optimisation framework with GA (He & Ju, 2015)
An exergy-and-pinch analysis will also be applied to proposed processes to establish the the lowest power consumption cycles. The theoretical background on these principals has been discussed in an earlier separate submission (Literature Study).
Table 13: Tuning parameters of genetic algorithm
| Tuning Parameters | Value |
| Population size | 100 |
| Maximum numbers of generation | 300 |
| Probability of crossover | 0.5 |
| Probability of mutation | 0.05 |
| Number of crossover points | 2 |
| Selection method | Tournament |
| Tournament size | 4 |
A knowledge-based decision-making method for selecting mixed refrigerant systems for LNG processes developed by Khan et al. (2013) will be applied as an alternative approach to selecting refrigerant compositions. The effect of variations in refrigerant compositions on the process will be investigated.
Aspen HYSYS (modelling package developed by Aspen Technology), one of the most rigorous simulators for chemical plants and oil refineries, will be used to perform optimisation. This software utilises extensive thermodynamic libraries and robustness in property calculations and is most commonly used in the LNG industry for process modelling and optimisation (Austbo et al., 2014).
Aspen HYSYS also has built-in optimisation tools with global convergence characteristics and better robustness to starting point dependence compared to other schemes available (Hatcher, Khalilpour & Abbas, 2012).
Fourteen scenarios will be considered in determining the capital costs for the designs:
Table 14: Cases to be considered for economic modelling
| Case | Production Capacity (TPD) | Production Capacity (mmGJ/aa) | Process |
| 1 | 13.5 | 0.25 | SMR |
| 2 | 25 | 0.5 | SMR |
| 3 | 55 | 1 | SMR |
| 4 | 110 | 2 | SMR |
| 5 | 165 | 3 | SMR |
| 6 | 220 | 4 | SMR |
| 7 | 275 | 5 | SMR |
| 8 | 13.5 | 0.25 | NEC |
| 9 | 25 | 0.5 | NEC |
| 10 | 55 | 1 | NEC |
| 11 | 110 | 2 | NEC |
| 12 | 165 | 3 | NEC |
| 13 | 220 | 4 | NEC |
| 14 | 275 | 5 | NEC |
an mmGJ/a – million gigajoules per annum (330 days per annum operability)
LNG plant equipment suppliers will be approached to determine large process unit costs (including utilities). Budget cost estimations with a +/- 30% accuracy will be determined.
Operating costs for given scenarios to be determined will include electricity costs, make-up cooling water, make-up nitrogen, and annual chemical fills (mixed refrigerant, lubrication oil, etc.). Labour, maintenance, security, land and other operating costs will be excluded as these are assumed to be similar for both processes.
Preliminary financial modelling and calculation of project returns will be performed based on assumptions in Table 15. South African rates will be used for this study. NPVs and ACCs will be key criteria in evaluating the most feasible designs between two processes for given scale ranges.
After completing financial and economic modelling, the most feasible design for the 55 TPD scenario will be selected. A generic basic engineering package design will follow, which will include the following items:
Table 15: Economic modelling assumptions
| Identifier | Quantity |
| Exchange rates | TBD on modelling execution dates |
| Inflation (“CPI”) | 6.1% |
| Debt repayment period | 5 to 10 years (depending on CAPEXa) |
| Plant useful life | 15 years |
| CAPEX term (for manufacturing) | 18 months |
| Depreciation (100/15) | 6.67% |
| Wear and tear percentage – first year | 40% |
| Wear and tear percentage – following three years | 20% |
| OPEXb | TBD during operating cost estimates |
| Annual gas cost escalation | 6.1% |
| Annual LNG selling price escalation | 5.6% |
| Debt funding ratio | 50% |
| Equity funding ratio | 50% |
| Cost of debt (pre-tax) | 13.5% |
| Cost of debt (post-tax) | 9.72% |
| Cost of equity | 24.37% |
| Project risk | TBD during design (vary with plant size) |
| The weighted average cost of capital | 17.05% |
| Tax rate | 28% |
| Gas cost | TBD on modelling date (market-related) |
| LNG selling price | TBD on modelling date (market-related) |
a CAPEX – capital expenditure; b OPEX – operating expenditure
The above listed can be incorporated into the overall plant design (gas pretreatment and storage facilities) applicable to a specific project in the industry. Gas pretreatment designs vary according to gas source compositions (wellhead, pipeline, microbial, biomass, flare gas, etc.). This design excludes overall plant plot layout drawings, civil- and structural drawings, a detailed construction schedule, detailed project cost estimates (for the overall plant), a health and safety plan, and a decommissioning plan, which are all project-specific.
Asepuland, A, Gundersen, T, Myklebust, J, Nowak, MP and Tomasgard, A (2009), “An optimization-simulation model for a simple LNG process”, Computers and Chemical Engineering, 34, 1606-1617.
Austbo, B, Lovseth, SW and Gundersen, T (2014), “Annotated bibliography – Use of optimization in LNG process design and operation”, Computers and Chemical Engineering, 71, 391-414.
Austbo, B, Wahl, PE & Gundersen, T (2013), “Constraint handling in stochastic optimization algorithms for natural gas liquefaction processes”, Proceedings of the 23rd European Symposium on Computer-Aided Process Engineering – ESCAPE 23, June 9-12, Lappeenranta, Finland.
Cao, W, Lu, X, Lin, W and Gu, A. (2005), “Parameter comparison of two small-scale natural gas liquefaction processes in skid-mounted packages”, Applied Thermal Engineering, 26, 898-904.
Chang, Lim & Choe (2012), “Effect of the multi-stream heat exchanger on the performance of natural gas liquefaction with mixed refrigerant”, Cryogenics, 52, 642-647.
Fan, CT and Oelschlegel, H (1986), “Process and apparatus for the liquefaction of natural gas stream utilizing a single mixed refrigerant”, US Patent 4,901,533, assigned to Linde Aktiengesellschaft, Wiesbaden, Fed. Rep. of Germany.
Hatcher, P, Khalilpour, R and Abbas, A (2012), “Optimisation of LNG mixed-refrigerant processes considering operation and design objectives”, Computers and Chemical Engineering, 41, 123-133.
He, T and Ju, Y (2016), “Dynamic simulation of a mixed refrigerant process for small-scale LNG plant in skid mount packages”, Energy, 97, 350-358.
He, T and Ju, Y (2015), “Optimal synthesis of expansion liquefaction cycle for distributed-scale LNG (liquefied natural gas) plant”, Energy, 88, 268-280.
He, T and Ju, Y (2014), “A novel conceptual design of parallel nitrogen expansion liquefaction process for small-scale LNG (liquefied natural gas) plant in skid-mount packages”, Energy, 75, 349-359.
He, TB and Ju, YL (2013), “Performance improvement of nitrogen expansion liquefaction process for small-scale LNG plant”, Cryogenics, 61, 111-119.
Jacobsen, MG and Skogestad, S (2013), “Active constraint regions for a natural gas liquefaction process”, Journal of Natural Gas and Engineering, 10, 8-13.
Hoseyn, S and Babaelahi, M (2010), “Exergetic Optimization of a Refrigeration cycle for Re-Liquefaction of LNG Boil-Off Gas”, Int. J. of Thermodynamics, 13 (4), 127-133.
Khan, MS and Lee, M (2013), “Design optimization of a single mixed refrigerant natural gas liquefaction process using the particle swarm paradigm with nonlinear constraints”, Energy, 49, 146-155.
Khan, MS, Lee, S, Rangaiah, GP and Lee, M (2013), “Knowledge-based decision-making method for the selection of mixed refrigerant systems for energy-efficient LNG processes”, Applied Energy, 111, 1018-1031.
Khan, MS, Lee, S & Lee M (2011), “Optimization of single mixed refrigerant natural gas liquefaction plant with nonlinear programming”, Asia-Pacific Journal of Chemical Engineering, 7, S62-S70.
Marmolejo-Correa, D and Gundersen, T (2012), “A comparison of exergy efficiency definitions with focus on low-temperature processes”, Energy, 44, 477-489.
Mokarizadeh Haghighi Shirazi, M and Mowla, D (2010), “Energy optimization for liquefaction process of natural gas in peak shaving plant”, Energy, 35, 2878-2885.
Moon, JW, Lee, YP, Jin, Y, Hong, S and Chang, HM (2007), “Cryogenic Refrigeration Cycle for Re-Liquefaction of LNG Boil-Off Gas”, Cryocoolers, 14, 629-635.
Neksa, P, Brendeng, E, Drescher, M and Norberg, B (2010), “Development and analysis of a natural gas reliquefaction plant for small gas carriers”, Journal of Natural Gas Science and Engineering, 2, 143-149.
Nogal, DF, Kim, J, Perry, S and Smith, R (2008), “Synthesis of Cryogenic Energy Systems”, 18th European Symposium on Computer-Aided Process Engineering – ESCAPE 18.
Nogal, DF, Kim, J, Perry, S and Smith, R (2008), “Optimal Design of Mixed Refrigerant Cycles”, Ind. Eng. Chem. Res., 47, 8724-9740.
Xu, X, Liu, J, Jiang, C and Cao, L (2012), “The correlation between mixed refrigerant composition and ambient conditions in the PRICO LNG process”, Applied Energy, 102, 1127-1136.
Yin, QS, Li, HY, Fan, QH and Jia, LX (2008), “Economic analysis of mixed refrigerant cycle and nitrogen expander cycle in small scale natural gas liquefier”, AIP Conference Proceedings, 985, 1159.
Yoon, S, Cho, H, Lim, D and Kim, J (2012), “Process Design and Optimization of Natural Gas Liquefaction Processes”, Chemical Engineering Transactions, Vol 29, ISBN 978-88-95608-20-4, ISSN 1974-9791.
In many cases, keeping pipelines online and producing is crucial for production lines and plants. However, it also becomes necessary to reroute, tie in additional lines or do maintenance on pipelines. This is where hot tapping can provide critical and much-needed support to keep the product flowing in the line while doing work. For more insights, read more on the EPCM experience.
In short, this process involves welding a stub to your pipe, installing a valve, opening the valve, drilling through the open valve, retrieving the cut-out piece and closing your valve for future extensions.

Start by identifying the part of the pipeline where the new tie-in will be placed. All coatings must be removed at that location to ensure a perfect weld to the pipeline. If a complete size-to-size tie-in is being done, the whole circumference of the pipe needs to be cleaned.
When a complete size-to-size tie-in is done, a split T-piece is welded over the pipeline. This is also true when hot tapping is greater than half of the parent pipe diameter. If doing smaller taps, you can weld on a compensation plate and the stub. Always ensure that the stub length is as short as possible, seeing that your tapping machine has a limited travel distance.

Once the T piece is welded on, it is a good idea to pressure test your welding since X-ray NDT is not usually possible. Depending on the client’s specifications, they might request dye penetrating tests on the welds. Install the valve on the stub now. It is advisable to install a sandwich valve for very long taps to save some travel distance. Other full-size valves will also work for this application but are usually very large.
You can now move to the hot-tapping machine. The tapping adapter on your hot tapping machine should match the flange size of your stub that is welded to the pipe. The cutter in the machine will always be one size smaller than the adapter. This will ensure that there is enough clearance to pass through the valve and get most of the shavings out. Install a pilot drill that protrudes past the cutter onto the machine. The pilot drill should have at least one catch wire installed that also protrudes past the cutter teeth by a margin greater than your pipe wall thickness. THIS IS CRITICAL! It will ensure that the catches drill through before the cutter is through; thus, you can retrieve the coupon.
Before placing the machine on the valve it is important to measure and record all internals of the operation. When the machine is installed, you will only rely on your measurements for a successful tap. Critical measurements include:
The tapping machine is now installed on the valve. While the valve is open, feed the machine down to the pipe until it stops on the pipe surface. In this position, you can record your starting measurement for cutting. By considering the pipe diameter and wall thickness, you can now determine the depth at which you need to cut into the pipe. Do not, under any circumstances, cut deeper into the pipe than the base of the cutter. This might cause the cutter to jam into the pipe, and the machine cannot complete the tap.

The machine can now be switched on, and the cutting process started. It usually has an automatic feed and must be stopped when you reach your predetermined cutting distance. While the machine is operating, you will also hear it moving freely once the cutter is through, and the pressure will drop significantly.
Once through, you can stop the machine and reverse-feed it past the valve. The main valve can now be closed. The tapping adapter has a relief valve on it. This valve must be opened before the machine is removed to release the internal pressure. The machine can now be removed from the valve, and the coupon can be retrieved.

With the valve successfully installed, you can now add additional piping to your network without stopping the flow of your pipeline. Two hot taps and stopples are performed to do pipeline maintenance, and a bypass line is installed. This allows you to maintain or cut out a piece of your line while your processes are never interrupted.

Cathodic Protection Case Study: Padma Bangladesh. Corrosion is usually defined as the deterioration of a metal or its properties caused by a reaction with its environment. Most metals occur naturally in the form of oxides and are usually chemically stable. When exposed to oxygen and other oxidizing agents, the refined metal will try to revert to its natural oxide state. In the case of iron, the oxides will be in the form of ferrous or ferric oxide, commonly known as rust. Metallic corrosion generally involves the loss of metal at a particular location on an exposed surface. Corrosion occurs in various forms, ranging from a generalised attack over the entire surface to a severe concentrated attack. In most cases, it is impossible or economically impractical to completely arrest the corrosion process; however, it is usually possible to control the process to acceptable levels. The basic terms and definitions of corrosion are covered under ISO 8044:1999, “Corrosion of metals and alloys — Basic terms and definitions“.
Read more about EPCM
Metallic corrosion is caused by the flow of direct current from one part of the metal surface to another. This flow of direct current causes the loss of metal at the point where current discharges into the environment (oxidation or anodic reaction). Protection occurs at the point where current returns to the metal surface (reduction or cathodic reaction). The rate of corrosion is proportional to the magnitude of the corrosion current. One ampere of direct current removes approximately nine kilograms of steel in one year. Where corrosion occurs and to what extent depends upon the environment the metal is exposed to. Read more on EPCM’s Cathodic Protection.
Four conditions must be met for corrosion to occur. Eliminating any of them will halt the corrosion reaction.
BS EN 12501-1
Protection of metallic materials against corrosion. Corrosion likelihood in soil. General
BS EN 12501-2
Protection of metallic materials against corrosion. Corrosion likelihood in soil. Low alloyed and non-alloyed ferrous materials
DIN 50292-3
The probability of corrosion of metallic materials when subjected to corrosion from the outside, Buried and underwater pipelines and structural components.
Corrosion exhibits itself in several ways. Below is a brief description of certain forms of corrosion.
Corrosion is a natural process. The primary driving force of corrosion is the transformation of iron from its natural state to steel. The refining of iron ore into steel requires the addition of energy. Steel is essentially an unstable state of iron, and corrosion is the process of iron returning to its natural state. The energy used in the refining process is the driving force of corrosion.
Corrosion cells are established on underground pipelines for a variety of causes. A primary cause of corrosion is due to an effect known as galvanic corrosion. All metals have different natural electrical potentials. When two metals with different potentials are connected in a common environment, the current will flow, causing corrosion. The latter form of corrosion will occur when the same material is located in a different environment, for example, a steel pipeline buried in aerated and unaerated soil.
Another classic example is pipelines connected to the reinforcing steel of thrust blocks and chambers. The coupling of steel to a different metal, such as copper (earthing material), will cause a corrosion circuit to be established. Direct coupling of copper to steel will cause the steel to corrode much faster than normal. Another form of this is coupling a rusty pipe to new, clean steel. The natural difference in potential causes the new steel to corrode more rapidly than the old steel. Other causes of pipeline corrosion cells include the effect of different soil types, oxygen availability, stray current interference and microbiological growth.
Two other unique causes (and sometimes related) are stress and hydrogen, but these are not applicable to the steel grades to be used on this project.
The five general methods used in the control of corrosion are ;
Control of underground corrosion is primarily achieved by combining two of the aforementioned methods: a coating system and CP. An effective external coating can provide corrosion protection to over 99% of the exposed pipe surface. The protective coating is usually applied to the pipe before burial.
The coating electrically insulates the metal from the soil. If the metal could be completely isolated, then the establishment of corrosion cells would be prevented, and no corrosion current would flow. However, no coating can be considered perfect. Damage to the coating due to handling, transportation, installation, thermal stress, and soil stress will eventually create defects or “holidays” that expose the underlying steel to the environment.
Cathodic protection is an electrochemical technique for preventing corrosion of a metal exposed to an electrolyte. The process involves the application of DC electrical current from an external source to the metal surface. By forcing the metal surface to accept current from the environment, the underground metal becomes a cathode, and protection occurs. The external source can use outside AC power through a rectifier and ground bed or by attaching sacrificial metals such as magnesium or aluminium to protect the structure. It is used extensively to prevent corrosion in underground and submerged steel structures such as pipelines, production well casings, and tanks.
Effective cathodic protection can completely protect any exposed areas for the structure’s life. Combining an external coating and cathodic protection provides the most economical and effective choice for protecting underground and submerged pipelines. For bare or ineffectively coated existing pipeline systems, cathodic protection often becomes the only practical alternative for corrosion protection on the proviso that the pipe bedding, padding and backfill permit the adequate flow of CP currents. Stones, rock and other poor backfills often permit the ingress of water and bacteria onto the exposed steel but obviate the flow of CP currents, exacerbating the corrosion process.
Therefore, correctly sized selective material must be used for the bedding and padding so that the exposed steel can receive CP and mitigate corrosion.
The protective coating is fundamentally the most important aspect of buried pipeline corrosion protection; hence, it is referred to as the primary corrosion protection system.
Pipeline anti-corrosion applications represent the market with probably the largest volume of coating products worldwide. This market potential naturally draws the focus of every coatings manufacturer, distributor and applicator. For these companies, the successful penetration of this market segment represents large product sales and volume increases over an extended period of time. Since large volume sales are the primary goal of every manufacturer, the end-user is bombarded with product marketing information, all claiming that their product alone is best suited for pipeline anti-corrosion applications. The sheer volume of information available on this subject can be overwhelming for the end-user who decides to select a specific product that is difficult to reach.
The ISO 21809-1 system and mill needs to be qualified, as per Clause 9. The latter qualification considers the various coating systems available, the skill levels regarding the application, environmental and mill/site-specific conditions controlling its application, and its efficacy regarding Cathodic Protection and its resilience to Cathodic Disbondment.
The Field Joint Coating (FJC) also needs to be duly qualified; otherwise, the FJC repair becomes the weakest link and the highest risk of corrosion due to the welding and Heat Affected Zones (HAZ)
Pipeline production and coating may not occur without a client-approved Inspection and Testing Plan (ITP) document providing an overview of the sequence of inspections and tests, including appropriate resources and procedures. The client shall approve the ITP and Quality Control Procedure (QCP) in writing before coating production begins.
A Procedure Qualification Trial (PQT) should take place after the approval of the documentation detailed above. It should be witnessed by the client or the duly appointed and authorised person appointed by the client to witness the application of the coating and subsequent inspection/testing of its properties to confirm that the Application Procedure Specification (APS) is adequate to produce a coating with the specified properties, carried out before the start of production.
CP is an electrochemical technique for preventing corrosion of a metal exposed to the electrolyte.
CP is covered by numerous international specifications, which most would apply to the 8″ and 6″ MI-BAF-SAIA pipeline project, such as;
To many people unfamiliar with the principles of corrosion, Cathodic Protection (CP) is a rather dubious method of corrosion control that has been commercialised since the 1920s. CP essentially means reducing or eliminating corrosion on a metal surface by forcing the metal to become a cathode.
The two general types of cathodic protection systems are impressed current and sacrificial. Both systems can effectively transfer the corrosion reaction (oxidation) from the metal surface to an external anode. If all exposed parts of a structure become cathodic concerning the electrolyte, corrosion of the structure is eliminated. Cathodic Protection is by no means new or of doubtful effectiveness in controlling corrosion.
The CP system is generally required to operate effectively and efficiently for 30 years.
Coatings (e.g. paints) applied to metal surfaces can be extremely effective in containing the corrosion of the steel substrate in many environments. However, no freshly applied coating is entirely free from defects, so there will always be small steel areas exposed directly to the corrosive environment. It is possible to reduce, but not eliminate, these defects by paying attention to workmanship. In practice, it becomes increasingly expensive to achieve fewer and fewer defects due to the need for high-quality inspection, detection and repair of individual defects.
The coating provides the initial barrier against the corrosive environment, and cathodic Protection protects against coating defects. Ideally, this complementary behaviour occurs due to the defects’ low resistance path, as opposed to the coating’s high resistance path.
A coating will deteriorate chemically and mechanically during its lifetime. This results in an increase in the number of defects and the current required to protect the newly exposed steel surface areas (defects).
The defects will once again provide a low path of resistance, and the cathodic protection current will flow to it and provide protection, provided that it is of sufficient magnitude. This naturally implies that the Cathodic Protection system must be designed with sufficient reserve to provide the necessary additional current.
Cathodic Protection (CP) may be achieved using Impressed Current Cathodic Protection (ICCP) or Sacrificial Anode Cathodic Protection (SACP). The choice of system is based on technical and economic factors.
Several frequently used CP definitions are detailed below :
Cathodic Protection: Reduction of corrosion rate by shifting the corrosion potential of the electrode toward a less oxidizing potential by applying an external electromotive force.
Sacrificial/Galvanic Anode: A metal which, because of its relative position in the galvanic series, provides sacrificial protection to metals that are nobler in the series when coupled in an electrolyte.
Sacrificial Anode Cathodic Protection (SACP): A cathodic protection system in which a galvanic anode supplies the external electromotive force.
Impressed Current Cathodic Protection (ICCP): A cathodic protection system in which an external DC power source provides the external electromotive force.
Anode Groundbed: One or more anodes installed below the earth’s surface to supply the protective CP current
Transformer Rectifier Unit (TRU): A device which converts alternating current to direct current.
Horizontal Groundbed: A group of anodes installed close (2 to 5m) together and installed in a long trench (structure) some 2,5m deep and located far from the structure requiring protection (pipeline or tank).
Deep Vertical Anode Groundbed (DW): One or more anodes installed vertically at a nominal depth of 50m or more below the earth’s surface in a drilled hole.
Shallow Vertical Anode Groundbed (SV): One or more anodes installed vertically at a nominal depth of 20m or less below the earth’s surface in a drilled or augured hole.
Distributed Anode System: Several anodes are distributed in close proximity to the structure requiring protection to concentrate the current in a specific area only.
Galvanic anodes are most efficiently used on electrically isolated coated structures. However, this matter will not be discussed further, as it does not apply to the MI-BAF-SAIAF PADMA Project.
An ICCP system protects large bare and coated structures and structures in “high” resistivity electrolytes. The design of any ICCP system must consider the potential for causing coating damage and the possibility of creating stray currents, which adversely affect other structures. Typically, Mixed Metal Oxide (MMO), Precious Metal Oxide (PMO), Silicon Iron (Fe-Si), and Graphite are used as anode materials.

An ICCP system will offer the following advantages:
An ICCP system will also offer the following disadvantages:
The proposed MI-BAF-SAIA Pipelines traverse corrosive to mildly corrosive and generally non-corrosive soils, for which Cathodic Protection (CP) is required.
The following important aspects of the CP Design.
The essential purpose of the CP Design is to ensure that Cathodic Protection can protect the new pipeline(s). The proposed pipeline route is detailed below.

It is extremely important that the correct type of CP system is installed and that the anode ground beds are located suitably in a congested petrochemical environment. If the anodes are not correctly located, an incorrect system may result in poor or no protection or overprotection, which can give rise to problematic and costly maintenance, etc.
A small Impressed Current Cathodic Protection (ICCP) consisting of a shallow horizontal anode groundbed and automatic CP controller will be the most commercially viable system based on the prevailing conditions.
Failures in oil or gas pipelines can have severe environmental and economic consequences. Therefore, large investments have been made in studies relating to preventing the corrosion of these buried pipelines. Important research has been and continues to be conducted in order to determine and predict the corrosiveness of soil in which the pipeline is buried, together with the corrosion mechanisms and the effective protection techniques required, such as protective coating systems. In addition to this, because the pipeline is buried and the location, size and overall geometry of the bare metal areas (coating defects/holidays) are unknown, as are the local soil conditions (resistivity and chemical composition), to obtain this data would require costly and often unreliable above-ground surveys. However, many of these coating defect surveys are intricate, elaborate and expensive and often do not yield all required data without substantial excavations, at great risk and expense.
Optimizing the cathodic protection (CP) system (s) design was necessary to ensure a highly efficient and low-cost CP system for pipelines, particularly in a congested petrochemical facility. This requires an understanding of the electrical/electrochemical process’s behaviour in terms of the current and potential distribution at the electrodes and in the electrolytic medium (soil).
Therefore, it is very important to have an adequate model that describes the performance of the CP system(s) and uses powerful software to simulate the electrical/electrochemical processes.
When designing a CP system, the aim is to obtain a pipe-to-soil potential (P\S) along the developed length of the pipeline network that is more negative than a certain minimum protection level. In soils, this minimum level is normally taken at -0.95V versus a copper-sulphate reference electrode (CSE). The CSE must be placed directly adjacent to the pipeline to reduce the IR- drop in the soil and across the coating to the coating defect. The value obtained in this situation is called the “Off” potential or P\S Off.
In practice, however, due to the unknown location of the defect and its unknown characteristics, it is often impossible to place the CSE directly adjacent to the pipeline coating defect. Instead, the CSE is placed at the soil surface, directly above the pipeline, which can result in significant IR errors. The value in this instance is referred to as the “On” potential or P\S On. In normal operating conditions, this value is more negative than the (true) “Off” potential, overestimating the obtained protection level.
In order to simulate and model pipeline cathodic protection systems, one needs to understand the basic ideas behind the “external” world (the soil) and the “internal” world (the metallic pipeline). The essential basics of the Boundary Elements Model (BEM) are detailed below.

The soil, together with the pipe(s) and anode(s), both of which are ostensibly cylindrical in nature, is essentially considered an electrical/electrochemical system in which the earth acts as the electrolytic solution (conducting medium) and the outer metallic pipe surface(s) (coating defects) act as the electrodes.
Boundary Element Methods (BEM) have been proven to closely follow the more precise yet time-consuming and costly Finite Element Methods (FEM) models. The latter is corroborated in the attached literature, “A Numerical Model for Cathodic Protection of Buried Pipes“.
The output models, which are also detailed individually below and in Appendix A, provide the complete level of protection afforded to the proposed BAF, SAIA, and Hydrants.
The piping model is summarised below, where L is the length, and S is the surface area.
| Pipeline Detail |
Length (m) |
Surface Area (m²) |
|||
| BAF Pipe2 |
1556.00 |
822.40 |
|||
| BAF-Spur |
55.20 |
29.18 |
|||
| BAF-H1 |
116.90 |
61.80 |
|||
| BAF-H2 |
13.86 |
7.33 |
|||
| PADMA8 |
5773.00 |
3973.00 |
|||
| SAIA 10 |
637.80 |
547.10 |
|||
| Total |
8152.76 |
5440.809 |
The BEM model indicates that all “Off” potentials are more negative and -950mV CSE.
The “On” potentials indicate that no substantial over-protection will take place, based upon the “On” and “metal potential”. The metal potential is the pipe potential located directly at the coating interface but remote to the coating defect, thereby limiting the “IR Error” to a better degree. It is more valid in terms of judging the level of overprotection that could occur if the “Off” potentials are more negative than -1100mV CSE (EN 12954 Clause 4.2) than using the “On Potential”.
The current density is indicated to be the highest and closest to the Cp Station. It will also become higher in areas of low soil resistivity (lowest resistance to earth of defects), as the most current will be required in these areas to polarise the pipeline and prevent corrosion.
However, the total current is 10A for the 30-year end-of-life design, which is attainable from the new 50V 25A Transformer Rectifier Unit (TRU) when coupled to a single 50m long 2.5m deep horizontal anode ground bed.
The summary of the current (I) balance and current density (J) is detailed below:
| Pipeline | Current (A) | Current Density (A/m²) |
| BAF Pipe2 | -1.43 | -0.00174 |
| BAF-Spur | -0.06 | -0.00193 |
| BAF-H1 | -0.12 | -0.00189 |
| BAF-H2 | -0.01 | -0.00091 |
| PADMA8 | -7.90 | -0.00199 |
| SAIA 10 | -0.50 | -0.00091 |
| Groundbed1 | 10.00 | 6.30300 |
| Current Balance of All Branches | 0.00011 |
Appendix A details the complete BEM Output Model Data and indicates that the proposed ground’s location is acceptable.
The proposed PADMA ICCP system shall comprise of the following, as a minimum:

Construction Delivery Models: Construction projects can be executed using various delivery models, including design-build, early contractor involvement, and alliance models. To ensure a construction project’s success, choosing the most appropriate delivery model is vital. Each delivery model has distinct features, and the client should consider how the differences align with the project’s goals and characteristics.
In this article, EPCM will discuss the various construction delivery models that a client could consider. Once an overall contract model has been decided on, a client can further refine the contract to suit the project-specific requirements.
When a construction project is undertaken, project personnel often focus on the technical aspects of the implementation of the project. It is, however, vital to first understand under what construction delivery model the project will be delivered, as this influences how the project should be approached. The different delivery models expose each party to the contract to very different risk profiles, which should be taken into consideration when deciding on the strategy, staffing and pricing of construction projects. Not fully understanding the delivery model can lead a contractor to hugely overestimate or underestimate their tender price, leading to an unsuccessful bid or the unsuccessful implementation of the project. Common types of models include:
The design and construction stages are undertaken separately for construction-only projects. The client first procures the services of consultants to undertake the design and engineering. Based on this, the client tenders out the construction of the works. The successful bidder then contracts directly with the client to construct the works, with the consultant acting in a supervisory role. The client, therefore, retains control and oversight over the entire project. This type of contract is suited to straightforward projects, with little to be gained from contractors’ input into the design.
In this construction delivery model, the client retains the risk of the design since the contractor has little if any, input. Because the contractors are merely pricing a completed design, they have a clear indication of what they are pricing for. This is a relatively low risk and, therefore, attracts many contractors, resulting in competitive pricing. This method also provides cost certainty to the client since there should be little variation after the contract award. The client, however, has to ensure that the design and requirements were complete and accurate from the outset, otherwise, there could be costly variations on the project.
Whilst cost-effective and straightforward, there is little incentive for consultants or contractors to optimise the design, potentially missing out on large cost savings. Due to the competitive tendering process, there is also the risk that the lowest bidding contractor mispriced project elements. This can lead to an adversarial project environment, with the contractor likely to take any opportunity to apply for variation claims.
Under the design-build and EPC delivery models, the contractor is tasked with undertaking and taking on the risk of the design. While design-build and EPC contracts are similar, they have some key differences. With a design-build contract, the client will provide a high-level design outline, which the contractor has to refine and detail engineering. With an EPC contract, the client will likely provide output specifications and have little input into the design. Under an EPC contract, the contractor provides performance guarantees for the completed facility.
These projects are suited to industrial and heavy engineering projects, where function precedes aesthetics. They provide a client with a single point of responsibility for the project, who procures and coordinates the design and construction activities of all other subcontractors and specialists. The owner does not get involved in coordinating design and construction interfaces and expects a completed project at the end, delivered at the agreed price. The client, therefore, has little scope for input during implementation and should be comfortable with effectively leaving the project in the hands of others. Therefore, the client’s requirements must be very clear and well-defined at the onset of the project to ensure that the end product meets their need. Any ambiguity will likely lead to disagreements about the final product, and any changes requested later by the client will likely lead to claims by the contractor to recover unplanned costs.
Payment for design-build and EPC contracts is generally a lump sum, and the contractor ensures they meet their quoted price. The contractor is likely to price in the additional risk they take under this delivery model. Whilst the overall price could cost the client more than other delivery models, there is price surety. A substantial profit can be made if the contractor’s price in risks that do not occur. The contractor could, however, also make a substantial loss if risks do occur that cannot be covered by variation claims.
With a lump sum price, the contractor is heavily incentivised to perform the work more efficiently since it will result in greater profits. Arguably, it could also incentivize them to cut costs to such a degree that it impedes quality or performance. The client should, therefore, ensure that the output specifications are well-defined. For this reason, the owner’s engineers are usually employed to verify the requirements are met.
In an EPCM project, the contractor provides a professional service to undertake the design, plan the overall project, and then procure and manage other contractors to implement the construction works. The EPCM contractor does not enter into contracts directly with other contractors, which is in contrast with the EPC model. Instead, the client contracts directly with the various other contractors who deliver the implementation. Therefore, The EPCM contractor isn’t liable for the other contractors’ schedule, cost or performance.
This contract form generally costs less than EPC contracts, as more risk remains with the client. Also, the client can procure each construction and supply contract individually, ensuring the best price is achieved rather than leaving it up to an EPC contractor. Since they are engaging each contractor individually, the client has more scope to change the scope as the project progresses. Even though the EPCM contractor is there to manage the project, an informed client is vital to its success.
The client retains a lot of the project risk due to having separate contracts directly with the various other contractors and suppliers and has no single point of responsibility. Therefore, the interface between the separate contractors is a risk to the client. The client is, however, also more involved in the project and has input into how it is delivered. The EPCM contractor can help the client manage the project successfully, and its oversight can ensure that a high-quality product is delivered.
The Alliance construction delivery model is a collaborative arrangement where the client and contracted parties share the risks and rewards of the project. They are usually used on large, highly complex infrastructure projects which are difficult to scope and implement under other contract models. They require a transparent open-book approach by all participants, who also jointly develop the deliverables, measures of success, and percentage split of costs and profits. They were developed to counter the disputes seen in large, complex projects, which can result in long, costly court battles.
One of the key benefits of the Alliance model is flexibility, with changes that would benefit the project readily accommodated. However, with the focus on the quality of the outcome rather than the process it takes to achieve it, there is a risk of uncertainty and escalation of cost and programme. It is, therefore, vital that agreements, processes, measures of success, etc., are agreed on upfront.
The Alliance model relies on a collaborative, trusting approach where the parties’ interests are aligned. Furthermore, parties must address any issues that arise jointly rather than attributing blame. Whilst these can be addressed in various procedures and with clear performance measures, the success of the Alliance model remains dependent on the attitude and culture that each participant brings to the table.
In the ECI delivery model, the client engages a contractor early to contribute to the development of the design. The ECI model allows for a collaborative approach to the project between the client and the contractor. This can lead to innovation in the technical approach and the project’s implementation. It is particularly useful if the project’s scope is not well defined at the onset. The ECI approach can help ensure that the client and contractor’s interests are aligned and on the same page, which helps prevent future disputes. ECI is usually suited to large, complex projects where there is benefit from a team collaborating to find innovative solutions, but it can be applied to projects of any size.
The delivery model is generally broken into two stages, with the first similar to the Alliance model and the second stage taking only the form of a design-build or construct. In the first stage, a contractor works with the client to develop and optimise the design. The contractor can be responsible for the design or work with the client’s design team. This can lead to innovation and improved constructability, leading to large cost savings due to better integration between design and construction. It also promotes transparency between all parties and creates a less adversarial culture. The contractor’s role should be clearly defined in this early stage, as it could be ambiguous, especially if the client employs an independent design team.
In the first stage of the ECI delivery model, a client could also engage two contractors to refine the design. At the end of Stage 1, the Client could request a competitive tender from each contractor, with the lowest bid being awarded the construction contract of Stage 2. This ensures some price competitiveness for Stage 2, even though engaging with two contractors will result in a more costly Stage 1.
Alternatively, one contractor can be engaged from the start. Still, their price for Stage 2 is transparently built up with the client, and/or subcontracts can be tendered out individually with full price transparency to the client. As an additional option, the client can put a ceiling on construction costs, and if this isn’t met, they can retain the right to go to the open market after Stage 1. However, contractors not involved in the previous design stage might be unable to submit competitive bids.
Before proceeding with an ECI delivery model, the client should plan the process and clearly define roles, responsibilities, and expected deliverables. The client should also be aware that, at the onset of the project, there will be little cost certainty. It should also be remembered that the best contractor for stage 1 might not be the best for the construction stage due to the different skill sets involved.
PPPs are long-term partnerships between the public and the private sector to deliver on infrastructure, buildings or services. Depending on the need, they can take various forms and can be used to make projects viable. The partnership apportions the responsibilities and risks between the public and private sectors. The public sector ensures the project is correctly defined and monitors compliance with the requirements. The private party is usually responsible for partly or fully financing, designing, building and operating the infrastructure or service. In return, the public sector makes payments to the private entity for an agreed period (e.g. 30 years).
Construction of the infrastructure or implementation of service comes with technical and operational risks, which the private partner carries. Where the public partner agrees to make set payments, they carry the demand and price risk they can generate from the facility’s use. There are further risks, such as public perception and acceptance of the project and the impact of future political changes that could lead to the withdrawal of support for the project from the public sector. It is, therefore, vital that the partnership agreements are well-considered and thorough.
Construction delivery models differ greatly in how they apportion risk and responsibility. Clients should understand the project they are embarking on to choose the most appropriate delivery model. In deciding on the delivery model to follow, clients should consider:
To ensure project success for all parties involved, the most appropriate delivery model should be selected to suit each project’s unique requirements.
The Building Information Modelling (BIM) sector has experienced a rapid surge in growth, accompanied by many exciting new developments. However, this rapid expansion brings not only opportunities but also new challenges. While there are numerous explanations on how to successfully execute projects within the BIM environment, the role of the drafting side in these explanations is often lacking. So, this article will highlight some of these challenges on the drafting side of the BIM industry, how to address them, as well as methods and tips to plan, start, and successfully execute projects.
BIM is an intelligent 3D to 6D model-based process that gives architecture, engineering, and construction professionals the insight and tools to plan, design, construct and manage buildings and infrastructure more efficiently.
BIM remains a powerful tool even if you don’t aim to move to the harder-to-reach 6D. However, working up to 5D will already assist both your company and clients in better understanding how projects are executed and managed. Working with BIM is an opportunity for the engineer/contractor to enhance open and transparent communication with the client about their projects.
Let’s first understand the various levels of BIM.
Traditionally, all modelling was done manually in 2D. In fact, despite the incredible advances made in computer and drafting software capabilities, some companies still exclusively use 2D. Of course, some drawings still need to be done in 2D, e.g. process planning, plant layouts, etc.
However, modelling only in 2D does not cut it anymore, and to stay relevant, any serious design office needs to upgrade its drafting capabilities to 3D at least.
At this step, you start incorporating the intelligent modelling side of BIM. Here, you can stop using extrusions as model placeholders and use actual-sized and shaped components. This means structural beams, piping, etc., will have accurate sizes, weights, and specifications from your most often-used design codes.
You can extract the full Bill of Materials/ Bill of Quantity/ Material Take-off/ Material Take-outs for these components from these models.
If you utilize your programs correctly, you can create 2D design drawings from your 3D models, which are linked to each other. So, updating the 3D models automatically updates your 2D drawings.
Here, things get interesting and fun. 4D BIM Modelling incorporates the project schedule.
After all the hard work to set up the 3D modelling, Project Planners need to change the schedule multiple times to accommodate all the subsequent changes made to the 3D model.
With 4D BIM Modelling, you combine that 3D model with the Schedule in one program. Now, you can simulate your construction projects to accurately predict whether your schedule works smoothly or if the changes result in clashes.
During execution, as the schedule is updated, the drafting office can verify that the 3D model still correlates to the updated schedule.
5D BIM modelling takes 4D and adds Project Cost.
When you have successfully integrated your 3D model and 4D Schedule, you can start adding your costs, taking your model up to a 5D level. This means you will be able to immediately determine how much any clash/ delay/ change will cost and the impact on the overall CAPEX of the project.
This allows for quick, efficient, modern decision-making tools to address any proposed changes. The full scale and impact of any changes can be modelled before large amounts of money and time are spent.
Small CMS Station 5D Screenshot – showing a model integrated with cost and schedule
There are various explanations of BIM, but none of them directly address the Drawing office side of this technology, only the theory. Most people, therefore, fail to understand the entire concept, resulting in mistakes. If the drawing programs are not set up correctly, they won’t be used to their full capacity. This is the main reason why most people give up after developing BIM systems.
There might be BIM specialists out there who know the systems’ theory, but so many forget the information they will use in the 3D model when they start moving into 4D and 5D. Yes, the drawing office is just as important to this system as the technology and theory.
The specific drawing programme, or technology, does not matter so much. There are various, and they are all good with their pros and cons. The concept stays the same all the way to level 5D.
Design Drafting Staff have a streamlined way of designing and modelling, and this will have to be adjusted slightly to ensure that the models being produced fit the construction/fabrication schedule to ensure seamless integration in your Secondary programme. But knowing how to design gives you the thought process to make quick and intelligent decisions.
Completed Intelligent 3D Model (Navisworks)
You can use this tool to simulate the construction sequence. You can break it up into sections (Days/hours), so in the morning’s site toolbox meetings, you can show your teams which areas they will be working on. In this way, you can track one program’s actual start and end date.
Setting up a model in the office can give your employees or fellow draughtsperson a visual idea of what you are trying to teach them. They can keep that file (we use Navisworks Manage) so they can measure and refer to those files. They will be able to see the correct specs and safety distances.
Creating an environment where the client can have real input into their Infrastructure (in our case, Plants/Tank farms, etc.) will enable you to deliver a better end product. This minimizes changes later in the project when most of the work has already been done.
When you run the simulations, and construction has started, you can track the costs and actual timelines in one place, using models and updated information. Changing the actual time started will indicate a change in the cost, which you can see immediately.
When a large plant can get noisy, it is very difficult to train an operator in those conditions. Using the BIM tools, you can sit in an air-conditioned office and show them exactly where and when they have to be there and spare your time, reducing the risk of someone not understanding. It’s also safer.
Using the 3D model in a program such as Navisworks will enable you to use that as a fabrication method. Using visuals instead of other drawings, which can confuse some, can save time and predict problems. This is a big step forward; the benefits will be great if you can ensure your designs are sound.
There is quite a lot of preparation to ensure that your company can execute a BIM project. If you realize in the middle that you are not prepared, fixing the projects will be much harder, and the delays will be immense.
You must sit with your dedicated BIM team and create a method statement for how you will execute your projects. Ensure your team has the same idea and that it is aligned with the results. There are a lot of examples of how to do this, but do not overcomplicate it. When you overcomplicate it, there is a chance that your team will not understand the process, and mistakes will be made.
After you have written a Method statement, you will move to the design criteria. This document will assist the drafting staff in knowing the standards to which they should be drawing. This will include 100% correct layer naming, document numbering, details that need to be drawn in, amount of model break-ups, etc.
Training is one of the most important steps in the process. It is important to train your employees on what to expect and what is expected from them in this journey. You will ask them to work with high quality and concentration to ensure their models are correct for using BIM. Letting them understand the entire purpose of BIM and the excitement about it will give everyone a common goal.
It will not be necessary to send everyone on training for 2 days, but maybe send a few leaders and let them guide and teach the rest of the team. The drawing teams must be educated to understand construction sequences because they must draw 3D models to communicate the idea to fit the schedules.
Start with a smaller project. Have a DEDICATED team that executes a smallish project so all the lessons and gaps can be filtered out. On the smaller jobs, it is easier to fix a mistake and catch up, the larger project gets confusing an overwhelming to everybody. Especially when the whole team is still learning and finding their feet, remember that the timelines on these projects differ from those of normal 3D modelling projects because the attention to smaller details should now be considered.
After creating those two crucial documents (Method Statement and Design Criteria), you are ready to set up your projects (referring to the Drawing office environment). This might be different from what you would have done in other projects. Look at how you will split up your drawings and how you will be drawing them.

Model for Two Pipelines Across a Bridge
Knowing there will be pitfalls and how to avoid them is a crucial part of executing a BIM project successfully, and there are a few if you are not ready or not set up for the time to come.
The project managers need to be updated on how long these types of projects take. You will learn this if you do a smaller project to test the waters. It is much harder to keep track of the time limit, which is too short, and it involves a large amount of data, which is a new area of expertise.
It is of utmost importance that the team adhere to the Method Statement and the Design criteria. The BIM software will be confusing when the correct layer numbering and naming are not used. Finding items to connect to your simulations will be difficult in a model with many components.
Do extra research to be sure that you understand the concept correctly. Because there are so many varieties of this process, it can be up to you to take a piece of each puzzle and complete it.
Part of the purpose of BIM is to start creating a more combined working environment for all disciplines. This will stop the battles between each other. Understanding each other’s role in the end goal can improve productivity. At this stage, integrating the project scheduler and the draftsperson is important so they can start drawing the correct information to suit the schedule.
Be sure to make provision to quality check your teams work regularly, once again you do not want to realise at the end that something is not up to standard. Be sure that they stick to the design criteria and double-check that the model correlates to the project schedule that has been set up. In a perfect world, the schedule should be done before the modelling starts, but we all know it is not a perfect world…
Using up-to-date software and computers assists in the process. It can be demotivating to the team to have constant slowness of computers and also slows down the entire process.

Quality assurance example – project set-up in the drafting environment
Incorporating PointCloud data into your BIM is one of the best tools for the Brownfields and even Greenfields sites. An intelligent 3D model can be created from Brownfields As-built Lidar Scans. Scanning is a great tool to assist in clash detections, minimise the risks, and assist with fabrication.
In Greenfields areas, the point cloud can be used for space planning and future expansion planning. What is important to know about this tool is that it can be misunderstood and then misused. Knowing how to use it can improve your productivity and deliver a better end product.
The quality of a scan is the first key point in determining the value of the PointCloud data. Although it is a bit more expensive to use, the value it brings is priceless.
It is important to create a rule of thumb for the scanning teams to know how many times around equipment they should be scanned to create the best resolution for modelling. Having experienced scans that were not up to standard, struggling through modelling with them, and losing faith in this technology (my first scanning project), it is difficult to maintain a high standard of modelling.
Next, determine the length of time the scanner should scan at one position. This also improves the quality of the scan. The longer, the better.
The file sizes of these scans can be enormous, so determine if you can use the black-and-white version or if you need the scan-colour version. It seems to assist if it is in colour because the teams can have a better idea of the site since not the entire team can go to the site.
After the scanning, the correct processing of the scans must be done. This needs to be done by someone who understands the environment and knows what to look out for when problems occur. The problems might be anything from a few misalignments to the orientation being wrong.
Enough time must be given for the scans to be completed and processed. If this is not done, you will have unclear scans or the scan misaligns, and inaccurate work will be done. If improper scans are done, more money will be spent to send people to the site to do manual markups (more inaccurate) or send the scanner again (costly).
No one can be good at anything if they are not trained or at least assisted in the correct direction. Using the PointClouds is a real challenge (take it from me), and training needs to be done. There are intricate ways of dealing with PointCloud. Knowing how to use the PointCloud, the most complex structure/equipment can be modelled from it. Do not lose faith in the technology; if you feel that you are not satisfied with its performance, it might be a flaw in the process. Remember that with correct processes in place and correct scanning, it is a tool to improve productivity and time, not decrease it.
The data from PointCloud scans can vary from 40GB to 600GB, 1TB, or even larger. These are massive amounts of data. The PointCloud data is sensitive, and it references a lot of different files. There are ways to ensure those reference files become one.
To store this type of information, you will either need a massive server just for PointCloud data, or you will have to use those combined data sources and add only the piece of the puzzle that the person is working on on their computer. Breaking the PointClouds up into respectable areas seems to work better than everyone working off one set.
The same principle applies to working with PointCloud Data in your software than with the Modelling, if not more so. PointCloud uses a lot of processing power to run, so computers that can run this should be strong. With that said, making PointCloud more user-friendly comes with the training thereof. Be smart, work smart.

End Result with Quality Assurance. Now, you can start 4D connections and 5D incorporation.
Working with Autodesk products has been accommodating to the PointCloud and BIM environments. They have programs that are just viewers and many designing programs for all disciplines, which work well with Navisworks (also Autodesk). The files import seamlessly into each other.
The entire BIM process, including the various technologies, can be intimidating. Still, with proper research, preparation, and some of the tips discussed, it is possible to achieve huge project success using BIM.
Don’t forget about the worker ants (draught personnel). They have to build the nest, and they know the flaws and challenges behind the theoretical methodologies. Keep your entire team updated and in the loop throughout the project, and ensure their opinions and concerns are collected and incorporated. Without the worker ants, there will be no nests.
Remember that the BIM environment allows people to come together and create a more integrated environment.
Read more about EPCM.
Author: Christelle Bosch, Drawing Office Manager and Draughtsperson at EPCM Holdings (Connect with her on LinkedIn)