CARBON DIOXIDE CAPTURING TECHNOLOGIES: Carbon dioxide (CO2) emissions are either natural or anthropic (due to human activity). Natural emissions come from natural wildfires, animal breathing, plants, aquatic microorganisms, the ground, or even volcanic origin. Anthropic emissions come from heating, vehicles, voluntary fire, and power generation stations of fossil fuels.
Since the Industrial Revolution, human sources of carbon dioxide emissions have been growing. Human activities such as burning oil, coal and gas and deforestation are the primary causes of the increased carbon dioxide concentrations in the atmosphere. Combustible fossil fuels such as coal, power plant gas, oil, vehicles and big industry are the largest sources of carbon dioxide. The production is from various items such as iron, steel, cement, natural gas, solid waste combustion, lime, ammonia, limestone, soda ash, aluminium, and petrochemicals. Carbon dioxide accounts for nearly 85 per cent of all emissions and is produced when natural gas, petroleum and coal are used. The major areas where these fuels are used include electricity generation, transportation, industry and residential and commercial buildings.
CO2 is naturally present in the air, so it’s not harmful to a living organism. However, CO2 emissions are also accompanied by heavy metals, which are different contaminants. These, together, provoke deleterious effects on a living organism. This latest is sensitive to variations of the CO2 concentrations in the atmosphere. This emission has consequences for wildlife and plants.
CO2 can be captured from large point sources, such as large fossil fuel or biomass electricity power plants, industries with major CO2 emissions, natural gas processing, synthetic fuel plants, and fossil fuel-based hydrogen production plants. Capture from the open atmosphere is also possible. Carbon capture has actually been in use for years. The oil and gas industries have used carbon capture for decades to enhance oil and gas recovery. Only recently have we started thinking about capturing carbon for environmental reasons.
Currently, most research focuses on carbon capture at fossil fuel-powered energy plants, the source of most man-made CO2 emissions. Many of these power plants rely on coal to create energy, and coal burning emits CO2 into the atmosphere. Some researchers envision a future where all new power plants employ carbon capture. There are three main steps to carbon capture and storage (CCS) –
Carbon is taken from a power plant source in three basic ways — post-combustion, pre-combustion and oxyfuel combustion. A fossil fuel power plant generates power by burning fossil fuel (coal, oil or natural gas), which generates heat that turns into steam. That steam turns a turbine connected to an electricity generator. Let’s take a more detailed look at the trapping and separation process:
Post-combustion CO2 capture refers to the removal of CO2 from combustion flue gas before discharge to the atmosphere. It is referred to as “post-combustion capture” because the CO2 is the product of the combustion of the primary fuel, and the capture takes place after the combustion of that fuel.
With post-combustion carbon capture, the CO2 is grabbed after the fossil fuel is burned. This process is currently being used to remove CO2 from natural gas. The biggest benefit of using this process is that it allows us to retrofit older power plants by adding a “filter” that helps trap the CO2 as it travels up a chimney or smokestack. This filter is actually a solvent that absorbs carbon dioxide. The solvent can later be heated, releasing water vapour and leaving behind a concentrated stream of CO2. Post-combustion carbon capture can prevent 80 to 90 per cent of a power plant’s carbon emissions from entering the atmosphere, but the post-combustion process requires a lot of energy to compress the gas enough for transport.

Figure 1: Post-combustion CO2 capture
Process Description
In a typical fossil fuel-fired steam generating unit, fuel is burned with air in a boiler to produce steam that drives a turbine/generator to produce electricity. The burning of fossil fuels produces flue gases, which include CO2, water vapour, sulfur oxides (SOx), nitrogen oxides (NOx), hydrochloric acid (HCl) etc. In a post-combustion process, CO2 is separated and captured from the flue gases.
The CO2 capture process is located downstream of the conventional pollutant controls for removing Particulate matter and acid gases, so these components will not interfere with CO2 removal. Challenges to separating CO2 from steam-generating unit combustion flue gas include:
Pre-combustion CO2 capture, as its name implies, occurs before the process gas is combusted to generate steam at a power plant. CO2 is trapped before the fossil fuel is burned, which means it’s trapped before it’s diluted by other flue gases. Pre-combustion capture applies mainly to IGCC processes where fuel is converted into gaseous components by applying heat under pressure in the presence of steam and limited O2.

Figure 2: Pre-Combustion CO2 capture.
Process Description
Coal, oil or natural gas (usually coal or petroleum coke at electric utilities) is heated with water and oxygen in an oxygen-lean environment. Unlike a boiler, a gasifier carefully controls the amount of air or oxygen available inside it so that only a small portion of the fuel burns completely. This “partial oxidation” process provides heat to drive gasification reactions. Rather than burning, most of the fuel is chemically broken apart by the heat and pressure in the gasifier, setting into motion chemical reactions that produce syngas. The fuel (carbon), water and oxygen react to form primarily a mixture of hydrogen (H2) and carbon monoxide (CO) known as synthesis gas or “syngas” according to the following high-temperature reaction:
3C + H2O + O2 H2 + 3CO
Although syngas are predominantly H2 and CO, they can include other gaseous constituents (e.g., hydrogen sulfide (H2S), carbonyl sulfide (COS), and CO2) in varying compositions depending on fuel characteristics and the conditions in the gasifier. Most syngas streams are at a higher pressure and can contain higher concentrations of CO2 than conventional steam-generating units (especially if the syngas is shifted to enrich the CO2 concentration).
Pre-combustion capture systems have been used widely in industrial processes such as natural gas processing. The pre-combustion process is lower in cost, but it’s not a retrofit for older power plant generators. As with post-combustion, pre-combustion carbon capture can prevent 80 to 90 per cent of a power plant’s emissions from entering the atmosphere.
Oxy-combustion (or oxy-fuel) refers to replacing air in the boiler or gasifier with pure oxygen (O2). Purified O2 helps eliminate unwanted byproducts in the air and also increases the CO2 purity of the resulting syngas or flue stream, making CCS more effective. The oxygen required for this technique increases costs, but researchers are developing new techniques to bring this cost down. Oxy-fuel combustion can prevent 90 per cent of a power plant’s emissions from entering the atmosphere.
Oxy-combustion overcomes the technical challenge of low CO2 partial pressure normally encountered in conventional coal combustion flue gas by producing a highly concentrated CO2 stream. The CO2 is separated from water vapour by condensing the water through cooling and compression.
Oxy-combustion’s appeal is tempered by a few key challenges, including the capital cost and energy consumption for a cryogenic air separation unit (ASU), boiler air infiltration that dilutes the flue gas with N2, and excess O2 contained in the concentrated CO2 stream.

Figure 3: Oxy-combustion CO2 capture

Based on economic and environmental considerations, it is necessary to apply efficient and suitable technology for CO2 separation with low operating costs and energy consumption. Up to now, several gas separation technologies are being investigated for post-combustion capture, namely,
(a) Absorption,
(b) Adsorption,
(c) Cryogenic distillation, and
(d) Membrane separation
Although various new methods were suggested for CO2 separation, Granite and Brien reviewed some of the most novel methods for carbon dioxide separation from the flue and fuel gas streams, such as the use of electrochemical pumps and chemical looping for CO2 separation.

Figure 4: Separation Techniques
Gas absorption processes using chemical solvents, such as amines, to separate CO2 from other gases have been used since the 1930s in the natural gas industry to produce food and chemical-grade CO2. As absorbents, the most commonly used are monoethanolamine (MEA), diethanolamine (DEA), methylodiethyloamine (MDEA) and triethanolamine (TEA). Low purchase costs and the availability of monoethanolamine (MEA) make it the most popular sorbent despite some obvious limitations.
The flue gas (containing CO2) is cooled (between 318 and 323 K), and fed to the absorption column (scrubber) where the solvent absorbs CO2. The CO2-rich solution is fed into a heater to increase the temperature of the solution, then to a stripper column to release the CO2. The released CO2 is compressed, and the regenerated absorbent solution is cooled and recycled to the absorber column. Solvent regeneration is responsible for much of the “energy penalty” of the CO2 capture system because the steam that could otherwise be used to generate electricity is instead used in the solvent regeneration process. Development of advanced solvents – those that are chemically stable, have high CO2 absorption capacities, and have low regeneration energy requirements – continues to be an active area of research.
Amines chemically react with CO2 via reversible reactions to form water-soluble compounds. Despite the low CO2 partial pressure in combustion flue gas, amines are capable of achieving high levels of CO2 capture due to fast kinetics and strong chemical reactions. However, the absorption capacity for commercially available amines is chemically limited, requiring two molecules of amine for each molecule of CO2. Besides, usable amine solution concentrations are typically limited by viscosity and corrosion. Therefore, current amine systems are only between 20 and 30 per cent amine, with the remaining being water. Although the water present in the solution helps control the solvent temperature during absorption, which is an exothermic reaction, the water also requires significant amounts of sensible heating and stripping energy upon CO2 regeneration.

Figure 5: Gas Absorption by MEA
(1) Alkanolamines: Between various solvent groups, alkanol amines group is the most important and most used for CO2 A major problem in the usage of amines for CO2absorption is equipment corrosion; the corrosion rate of various amine solvents and the suggested corrosion rate could reduce in the following order:
Monoethanolamine (MEA) > 2-amino-2-methyl-1-propanol (AMP) > diethanolamine (DEA) > methyl diethanolamine (MDEA).
(2) Amino Acid: Amino acids have the same functional groups as alkanolamines and can be expected to behave similarly towards CO2 but do not deteriorate in the presence of oxygen. The most common amino acids used in gas-treating solvents are glycine, alanine, dimethylglycine, diethyl glycine, and several sterically hindered amino acids.
(3) Ammonia: Since ammonia is a toxic gas, preventing ammonia “slipping” into the atmosphere is necessary. Despite this disadvantage, the chilled ammonia process (CAP) was used for CO2 separation. In the CAP, CO2 is absorbed in an ammoniated solution at a lower absorption temperature (275–283 K) that reduced ammonia emissions from the CAP absorber. The ammonium carbonate solution resulted in approximately 38% carbon regeneration compared to the MEA solution.
Adsorption operation can reduce the energy and cost of the capture or separation of CO2 in post-combustion capture. To achieve this goal, it is necessary to find adsorbents with suitable properties. In general, CO2 adsorbent must have high selectivity and adsorption capacity and adequate adsorption/desorption kinetics, remain stable after several adsorption/desorption cycles and possess good thermal and mechanical stability. The method consists of condensation of vapour and gases on the surface of a solid adsorbent due to molecular forces. It uses the differences in sorption capacity of particular components of the separated gas mixture on a given adsorbent. The adsorbents used for CO2 separation are placed into two main categories: physical and chemical adsorbents.
A) Activated Carbon (AC):
It has several attractive characteristics, such as its high adsorption capacity, high hydrophobicity, low cost, and low energy requirement for regeneration. Activated carbons are inexpensive, insensitive to moisture, and easy to regenerate. These adsorbents have well-developed micro- and mesopore structures that are suitable for high CO2 adsorption capacity at ambient pressure.
Activated carbon may be produced from many raw materials such as coal, coke pitch, wood or biomass sources (e.g., sawdust, coconut shells, olive stones), often via two steps: carbonization and activation. Carbon molecular sieves (CMS), which are a sub-class of activated carbon with narrow pore size distribution (PSD), are kinetic-based adsorbents. They have been commercialized mainly for the separation of air and the production of high-purity N2. However, at low CO2 partial pressure, activated carbons exhibit lower adsorption capacity and selectivity than zeolites, mainly due to their less favourable adsorption isotherms. Despite the hydrophobic character of carbon-based adsorbents, their CO2 adsorption ability is adversely affected by the presence of water vapour.
B) Zeolites:
The most popular adsorbents are zeolite and carbon adsorbents, which constitute an adsorption bed when filled into the adsorption tower. For the process to be carried out continuously, at least two adsorption towers are required. In practice, multi-bed systems are used, which benefits the effectiveness of the process.
CO2/N2 selectivities of activated carbon are relatively low; zeolitic materials offer CO2/N2 selectivities 5–10 times greater than those of carbonaceous materials. The adsorption capacity and selectivity of zeolites are largely affected by their size, porous diameter, charge density, and chemical composition of cations in their porous structures. The average value of heat adsorption on zeolites is larger than that of activated carbon, confirming the mentioned affirmation. Moreover, activated carbon can be regenerated easily and completely. Also, its capacity did not decay after 10 consecutive process cycles.
C) Carbon Nanotubes (CNTs):
They are the most famous among nano-hollow structured materials, and their dimensions range from 1 to 10 nm in diameter and from 200 to 500 nm in length. Purified single-walled carbon nanotubes (SWNTs) adsorbed CO2 better than unpurified SWNTs. Also, multi-walled carbon nanotubes (MWNTs) showed stability for 20 adsorption and regeneration cycles.
D) MOFs and Zeolite-like MOFs:
Carbon dioxide adsorbs to a MOF Metal-Organic Framework through physisorption or chemisorption based on the MOF’s porosity and selectivity, leaving behind a Greenhouse gas-poor gas stream that is more environmentally friendly. The carbon dioxide is then stripped off the MOF using temperature swing adsorption (TSA) or pressure swing adsorption (PSA) to reuse the MOF. Adsorbents and absorbents require regeneration where the CO2 is removed from the sorbent or solution that collected it from the flue gas for the sorbent or solution to be reused.
Although an emerging class of porous materials, metal-organic frameworks (MOFs) have attracted a growing interest, motivating extensive studies on their CO2 adsorption properties, both theoretically and experimentally. MOFs are porous crystalline materials composed of self-assembled metallic species and organic linkers. Their pore size and shape can be easily tuned by changing either the organic ligands or the metallic clusters. They are typically rigid materials, but some of them exhibit structural flexibility upon adsorption and desorption of gases or liquids. The wide range of MOFs combined with their desirable properties, such as their remarkably high surface area and controlled pore size and shape, prompted extensive work on their absorptive properties, particularly for storing light gases (H2, CH4) and storing and separating CO2. Although most investigations on CO2 adsorption over MOFs used pure CO2 and CO2-containing mixtures, most measurements and simulations were carried out at high pressure and often at room or sub-ambient temperature.
Five different regeneration strategies were demonstrated in a single-bed CO2 adsorption unit: pressure swing adsorption (PSA), temperature swing adsorption (TSA), vacuum swing adsorption (VSA), electric swing adsorption (ESA), and a combination of vacuum and temperature swing adsorption (VTSA). The difference between these technologies is based on the strategy for the adsorbent regeneration after the adsorption step. In PSA applications, the pressure of the bed is reduced. VSA is preferred to the special PSA application where the desorption pressure is below atmospheric. In contrast, in TSA, the temperature is raised while pressure is maintained approximately constant, and in ESA, the solid is heated by the Joule effect.
The membrane separation method is a continuous, steady-state, clean and simple process, and ideal as an energy-saving method for CO2 recovery. Gas separation using membranes is a pressure-driven process. Due to the low pressure of flue gases, the driving force is too low for membrane processes in post-combustion (low pressure and low CO2 concentration). Membrane processes offer increased separation performances when CO2 concentration in the feed mixture increases.
Membrane separation processes have several advantages over other CO2 separation technologies. The required process equipment is simple, compact, relatively easy to operate and control, clear process and scale up.
The energy required for the recovery of CO2 by membrane processes depends on the target purity, flue gas composition, and membrane selectivity for CO2. However, membrane processes require too much energy for post-combustion CO2 capture; therefore, the low partial pressure of CO2 in the flue gas is a possible disadvantage for the application of membranes. Another disadvantage of the membrane process is that the membrane selectivity for separating CO2 is very low. The membrane process is not useful for high-flow rate applications.
Therefore, the useful membrane for post-combustion CO2 capture should have some specifications, such as:
Most industrially important membranes for gas separations are hollow fibre ones. Asymmetric hollow fibre membranes (such as polyvinylidene difluoride (PVDF)) with inner skinless structures are favourable for CO2 separation and absorption in the gas-liquid membrane by low mass-transfer resistance and high permeability. In addition, this process can achieve significantly high adsorption efficiencies due to the much larger surface area for the gas-liquid interface than conventional gas absorption processes.
The Cryogenic method utilized low temperatures for condensation, separation, and purification of CO2 from flue gases (the freezing point of pure CO2 is 195.5 K at atmospheric pressure). Therefore, the components can be separated under the cryogenic separation process by a series of compression, cooling, and expansion steps. It enables direct production of liquid CO2 that can be stored or sequestered at high pressure via liquid pumping. The advantages of this technology can be summarized as follows:
(1) Liquid CO2 is directly produced, thus making it relatively easy to store or send for enhanced oil recovery.
(2) This technology is relatively straightforward, involving no solvents or other components.
(3) The cryogenic separation can be easily scaled up to industrial-scale utilization.
The major disadvantages of this process are the large amount of energy required to provide refrigeration and the CO2 solidification at a low temperature, which causes several operational problems. Therefore, more studies are required for reducing the cost of cryogenic separation A pilot-scale CO2 capture and compression unit (CO2 CCU) that can separate CO2 as liquid phase from the flue gas of oxy-fuel combustion. Their results showed that cryogenic is the most cost-effective when the feed gas is available at high pressure. Therefore, cryogenic is not suitable for post-combustion, but it is effective for separation streams with high CO2 concentrations, such as oxy-fuel combustion.
In a novel CO2 cryogenic liquefaction and separation system, two-stage compression, two-stage refrigeration, two-stage separation, and sufficient recovery of cryogenic energy were adopted. Furthermore, this CO2 cryogenic separation system is more suitable for gas mixtures with high initial pressure and high CO2 concentration.
After capturing carbon dioxide, it is transported to a storage site. The current method of transporting CO2 is through a pipeline. Pipelines have been used for decades, and large volumes of gases, oil and water flow through pipelines daily.
A CO2 pipeline usually begins at the source of capture and travels directly to the storage site—although, in some cases, it might travel as far as it can in the pipe, then transition to a tanker or ship to finish its journey. It all depends on where the source, pipeline, and storage site are located. Both the public and private sectors can own pipelines.
Pipelines can transport CO2 in three states: gaseous, liquid and solid. Solid CO2 is commonly known as dry ice, and it’s not cost-effective to transport CO2 as a solid. Pipelines commonly transport carbon dioxide in its gaseous state. A compressor “pushes” the gas through the pipeline. Sometimes, a pipeline will have intermittent compressors to keep the gas moving. The CO2 must be clean (free of hydrogen sulfide) and dry. Otherwise, it can corrode a typical pipeline, which is made of carbon manganese steel. As of yet, there are no standards in place for “pipeline quality” carbon dioxide, but experts say that pipelines built from stainless steel would have a lowered risk of corrosion. This, however, may not be economical since we would have to build brand-new pipelines just for CO2.
As CO2 is odourless and colourless, though, adding an odour to the gas could help detect leaks. Regardless, experts recommend the construction of pipelines in low-population areas to minimize any impact. Pipeline costs fluctuate depending on the pipeline route (through heavily congested areas, mountains, offshore). Transporting CO2 as a liquid is possible, using ships or tanker trucks. Liquid CO2 requires low pressure and constant temperature, so cargo tanks must be pressurized and refrigerated.
[1] D.J. Hofmann, J.H. Butler, P.P. Tans, A new look at atmospheric carbon dioxide, Atmos. Environ. 43 (2009) 2084–2086.
[2] Kim Y., Lim J., Jeong S., Yoon Y., Bae S., Nam S., 2013. Comparison of carbon dioxide absorption in aqueous MEA, DEA, TEA, and AMP solutions. Bulletin of the Korean Chemical Society 34 (3), 783-787.
[3] Ben-Mansour R., Habib M., Bamidele O.E., Basha M., Qasem N., Peedikakkal A., Laoui T., Ali M., 2016. Carbon capture by physical adsorption: materials, experimental investigations, numerical modelling, and simulations – a review. Applied Energy 161, 225-255.
[4] J.P. Ciferno, T.E. Fout, A.P. Jones, J.T. Murphy, Capturing carbon from existing coal-fired power plant, Chemical Engineering Progress (April 2009) 33.
[5] J.E. Koresh, A. Soffer, The carbon molecular-sieve membranes—General properties and the permeability of CH4/H2 mixture, Separation Science and Technology 22 (1987) 973.
[6] O.M.Yaghi, M. O’Keeffe, M.W. Ockwing, M. Chae, M. Eddaoudi, J., Reticular synthesis and the design of new materials, Nature 423 (2003) 705–714.
[7] P.L. Llewellyn, S. Bourrelly, C. Serre, A. Vimont, M. Datura, L. Hamon, G. De Wereld, J.S. Chang, D.Y. Hong, Y.K. Hwang, S.H. Jhung, G. Ferey, High uptakes of CO2 and CH4 in mesoporous metal-organic frameworks MIL-100 and MIL101, Langmuir 24 (2008) 7245–7754.
[8] A.R. Millward, O.M. Yaghi, Metal-organic frameworks with exceptionally high capacity for storage of carbon dioxide at room temperature, J. Am. Chem. Soc. 127 (2005) 17998–17999.
[9] K. E. Zanganeh, A. Shaheen, and C. Salvador, “CO2 capture and development of an advanced pilot-scale cryogenic separation and compression unit,” Energy Procedia, vol. 1, pp. 247–252, 2009.
[10] H. Yang, Z. Xu, M. Fan et al., “Progress in carbon dioxide separation and capture: a review,” Journal of Environmental Sciences, vol. 20, no. 1, pp. 14–27, 2008.
Architecture for The Modern Retail Fuel Station: In times of uncertainty, one rings true – opportunity greets the world with the break of dawn and says farewell with the sinking sun. Innovation, creativity, and awareness of the world and environment around us are magnetic forces pulling uncertainty and opportunity into a kaleidoscope of meaningful architecture, representing the spirit of time (and, to some extent, of its creator). The increase, but at this moment somewhat limited, in the travel of today’s society makes nodes along the national and the local travelling routes more and more important. These nodes become an icon in the landscape – not because of its stature, hierarchy, intrigue, beauty or even spatial experience, but merely for the distinct fact that it succeeds in its function: filling up thirsty fuel tanks and hungry stomachs, providing vehicle services and guiding road users on their journey.
Petrol retailing in South Africa began around the turn of the twentieth century. The first concept was based on the design of an underground storage tank with a pump and hose dispensing system and curb pumps placed on the streets. This caused street congestion, fuel stations with off-street and roadside fuelling solutions started to emerge – some even managed by pharmacies and chemical shops (Wilsson,1995). Around 1930, a substantial development started to gain momentum in the United States, and convenience stores and grocers began providing customers with refuelling facilities as an additional service (Minale, 2000). Soon after, South Africa was influenced similarly and gave birth to the modern Retail Fuel Station as we know it.
The South African retail fuel industry is considered vastly sophisticated by the Department of Minerals and Energy with a solid infrastructure as its foundation (Human Sciences Research Council, 1992; Thomas, 2005 and Mbendi, 2004b). This industry has built an empire of more than 4500-6000 retail service stations spread through the landscape of South Africa, but sadly finds itself in an exceedingly competitive environment, characterised by high stock turnover, low return on investment and an overtraded market. This is no surprise when analysing and gaining a better understanding of the key variables influencing this sector’s profitability. The impact of the size of the fuel station and its fuel price had lessened – still effective in its functioning, but replaceable in the minds of most non-loyal customers who seek other non-forecourt activities such as convenience stores, car washes, quick service restaurants, motor car sales, technological advances and ATMs (Smalley, 1999). Location, the size of the fuel station, Price Elasticity of Demand, different users with different needs, time of day and season – all of these and more are key variables that influence this sector’s profitability. In today’s society, the combination of good service, originality, technology, sustainability and the holistic sensory experience of its user governs above all.
An opportunity for meaningful architecture within the functional arises.
An opportunity for dialogue in the visual manifestation of society is presented.
Let’s stop for a moment and think about the mundane – the most functional, non-esthetical, mind-numbing item you can think of. It is effective in functioning the way it was designed for, but does not appeal in any way to the person utilizing it. In this state of limbo, this item becomes replaceable once a more appealing, exciting and innovative solution to the same ‘’problem’’ comes along, and offers its user a glimpse into a world of possibilities, enjoyment and self-discovery.
Effective marketing and advertisement of a strong brand name, good management, promotions and specials, security – all the intangible elements that attract and ensure customers’ loyalty to any fuel station. Shifting the focus to the tangible, we peel away the layers of the human psyche and find that we become emotional about our surroundings and engage in a dialogue with the environment. We connect the smell of freshly baked bread to blissful memories of Sunday-morning breakfast with friends and family, colour and texture awaken the child within you – a visual exploration accompanied by curious hands, the sound of cheerful chatter over a cup of coffee… These things fill the void of an architectural, functional building aiming to create a bold new image for its brand. Although this psyche-engaging experience is sometimes ephemeral, it speaks to our nature as human beings: a need for shelter, a place of solitude, and a dwelling. In this dwelling, we come to know ourselves: our likes and dislikes, our personalities and opinions, we build relationships, we love and make love, we see, feel, smell, touch. We are ultimately the product of our surroundings and shaped by the built environment around us where all human activity occurs. It is important to note that because of this environmental, social and economic influence, each person experiences elements of life differently.
Architects around the world have experimented with various concepts addressing the functional fuel station in a world governed by aesthetics and digital influence. Some have created architecture that contrasts itself to other Retail Fuel Station designs, celebrating the building form itself rather than the visual aesthetics of signage and graphics.
Taking a closer look at Italian practice Damilano Studio’s contemporary ‘Gasoline Petrol Station’, located in Cuneo, Italy, the retro continuous ribbon of asphalt discreetly nods towards the American Retail Fuel Station and continues to link the concept of utilitarian, continuous flow with the urban landscape.

Image 1: Andrea Martiradonna, (2020), Retro Ribbon front elevation [ONLINE]. Available at: https://www.designboom.com/architecture/damilano-studio-architects-gazoline-petrol-station/ [Accessed 4 August 2020].
Of course, no fuel station will be complete without the iconic forecourt canopy, the pinnacle of the site. Mimicking the notion of its visitor’s speed and sculpted geometric form of automotive engineering, a visually dynamic image, point of hierarchy and orientation is created as an oasis in the landscape to offer its user the unprecedented service station experience to be forever associated with its brand. A single free-standing metal-clad column stands proud, supporting the rudimentary forecourt canopy.

Image 2: Andrea Martiradonna, (2020), Night-time canopy view from the main road. [ONLINE]. Available at: https://www.designboom.com/architecture/damilano-studio-architects-gazoline-petrol-station/ [Accessed 4 August 2020].

Image 3: ‘’United Petroleum / Peddle Thorp Architects” (2016), Site Plan [ONLINE]. Available at: https://www.archdaily.com/800498/united-petroleum-peddle-thorp-architects> ISSN 0719-8884’ [Accessed 4 August 2020].

Image 4: ‘’United Petroleum / Peddle Thorp Architects” (2016), Site Entrance view. [ONLINE]. Available at: https://www.archdaily.com/800498/united-petroleum-peddle-thorp-architects> ISSN 0719-8884’ [Accessed 4 August 2020].
The other side of the coin and as the past years’ of published architectural projects revealed, architects and their clients are extensively experimenting with ‘natural’ materials to create warmth in colour and touch, soft environmental textures and the combination of landscape design and ambient elements. This offers a glimpse into the kaleidoscope of the dominant man-made surroundings and natural environment. Combining age-old basic architectural principles and high-tech building solutions has created a hybrid approach to sustainability and human intrigue. Sustainability in building design has entered the mainstream and has become the goal for many architects and clients. The objective of this goal must be weighed against the outcome: does your client want to make a difference in his environmental footprint, or does Western influence bring on this intervention? To promote environmental innovation, we need to understand its conceptual challenges first, and then we can only manoeuvre our way on the pathway to sustainable design and a lower environmental impact.
Sustainable architecture and the interlacing concept of environmentally friendly elements has brought the measuring of physical performance to the forefront of several contemporary models. This image is grounded in two core expectations: environmental issues are only physical and global; secondly, environmental ‘’bads’’ can be corrected by understanding the ‘rational science’ behind such environmental crimes. Believing that the ‘’greenness’’ of a building can be predetermined by objective technical analysis of a building’s life-cycle, carbon and ecological footprint, or any other assessment method, can help architects shape and determine a sustainability model that directly addresses energy efficiency issues. Whether your client opts for on-site wind turbines, photovoltaic panels, heat pumps, passive solar and daylighting strategies, or merely bulking up on insulation or passive ventilation over a cooled exterior water body – we need to consider the ‘’health’’ of the building and its user or occupant. This, however, becomes a linear model of sustainability and needs to acknowledge the specific social context in which these fuel stations are placed, both in time and space.
The Sustainable Gas Station, designed by Knevel Architecten, is located in a prominent industrial area between Provincial Road N99 and the Mainroad to Den Over in the Netherlands.

Image 5: “Sustainable Gas Station Avia Marees / Knevel Architecten (2012), Site Plan. [ONLINE]. Available at https://www.archdaily.com/283889/sustainable-gas-station-avia-marees-knevel-architecten> ISSN 0719-8884 [Accessed 4 August 2020].

Image 6: “Sustainable Gas Station Avia Marees / Knevel Architecten (2012), Main Road Elevation. [ONLINE]. Available at https://www.archdaily.com/283889/sustainable-gas-station-avia-marees-knevel-architecten> ISSN 0719-8884 [Accessed 4 August 2020].

Image 7: “Sustainable Gas Station Avia Marees / Knevel Architecten (2012), Forecourt Canopy. [ONLINE]. Available at https://www.archdaily.com/283889/sustainable-gas-station-avia-marees-knevel-architecten> ISSN 0719-8884 [Accessed 4 August 2020].
At this moment in the architectural world, environmental architecture is widely debated. It causes a split between an Arcadian marginal intent and the rationalist approach of technologies and contemporary environmental design. In a South African context, the third dimension of this approach is probably the most influential on the outcome of an authentic, proudly South African Architectural masterpiece: giving a voice to the different values of those individuals and landscape involved in the design and construction process. Although this is not the primary concern for most South African designers and developers who seek to realise Westernised ideas of Architecture in an African context, we should aim to distinguish South African Architecture as an approach deeply rooted in ecology and not mainstream environmentalism. To reshape the Retail Fuel Station typology, the design strategy must be adjusted to specifically or concurrently emphasise socially cohesive design that promotes the health of its building and occupants, values and respects nature, maximises the efficient use of resources and minimises its environmental footprint.
But sadly, the conundrum remains: how can we, as architects, create a new, relevant, environmentally sustainable, and visually striking retail fuel station typology meaningfully while improving the overall service-oriented experience and reducing the cost of building maintenance by incorporating technology into our buildings?
Although no simple answer is readily available to this complex question, we can aim to approach each future project with a unique concept, tailored to a specific type of fuel station in its unique setting. The spectrum of applicable Retail Fuel Station Architecture stretches far and wide, searching for inspiration in just about anything. Contrasting the human frailty and scale with that of the scale and ruggedness of a fuel station’s industrial and mechanical elements, it is clear to see why a more forgiving and gracious approach to built elements is needed. If it’s an eye-catching, dramatic exploration of sculptural art amidst highway industrial architecture, or a delicate road-side intervention of principles of sustainability, specific crafts from the region and climate-neutral buildings – the message is clear and the warning loud: designers of the future must seek to celebrate their inheritance of climate, culture, and knowledge. A more holistic and influenced approach is strived for, hoping to create a relatable typology of inviting comfortability, safety, warmth and relaxation for its users. The proposal is to create an architectural language of vernacular simplicity, environmental engagement, technological innovation and human interaction.
In taking this approach to design, it is important to note that a combination of various complex actors comes into play, together with funding regimes, locational constraints and opportunities. Locally owned farm-to-table restaurants are proposed for the Quick Service Restaurant, juice bars, meditation and resting pods, electrical device charging ports, community shops, gyms, clinics, medical care, and lodging are just some of the interventions being implemented today. Modular building design and implementation can easily provide a plug-and-play solution for any Retail Fuel Station Developer looking to mitigate risk and test the market or location of their fuel station. Creating a campus of permanent and temporary activity on such a development, like music festivals, can provide the backdrop for many future opportunities and customers. Fuel stations are no longer just about refuelling vehicles. Fuel station milieus have transformed into experiences of interaction, relaxation, and receiving the best possible service, in the shortest amount of time. Although they strive to provide people with what they need in one-stop, or longer, Fuel Stations design aims to provide all-in-one experiences that maximize people’s time and money. In this way, we as architects might begin to grasp how different logics, influences, locations, technologies, social groups and green design are mobilised and combined to assist other designers, developers and planners with distinct architectural approaches and strategies for future retail fuel station typologies.
Attempting to offer its users the best experience, the Retail Fuel Station of the future will focus on the wellbeing of motorists, not just their motor vehicles. Service and convenience are at the front line of this experience. They should be reflected in the building design, offering a motorist and their companion the age-old requirement of comfort and information – but focusing on the human enjoyment of this offering. Referencing our basic human need for shelter, carefully selected materials must provide a feeling of warmth, safety and relaxation to contrast the industrial context of the exterior function of the service station. Protected spaces, designed to enhance the re-fuelling, purchasing and ‘resting’ experience, are seen throughout the interior but focus mainly on convenience food outlets and public seating inside and out. Although refuelling one’s motor vehicle is the primary attraction of a fuel station, modern society has become bound and motivated by time and money. It therefore seeks a place of convenience, quick service and low cost. The opportunity exists to re-route this thinking of a retail fuel station customer and present an end-destination, rather than a stop-over point. By adopting this building design perspective, we can begin to recognise the hybrid nature of the Retail Fuel Station Typology and pave the way for meaningful architecture – even in the mundane.
References:
Mbendi, Information for Africa. SAPIA, South African Petroleum Industry Association. 2004
Annual Report [Online] Available from:
www.mbendi.co.za/Sapia/pubs/2004_ARep/SAPIA_Appendices_ 2004.pdf [Accessed: 19/07/2020].
Minale, M., (2000), How to design a successful petrol station, Booth-Clibborn Editions,
12 Percy Street, London, United Kingdom
Smalley S., 1999. Measuring the convenience of gas stations. Appraisal Journal, October:339-347
Wilsson, O., (1995), Full tank, Tago Förlag, Stockholm
About EPCM
In this article, EPCM explains the principle of horizontal directional drilling as it relates to pipeline installation. It will also highlight some technical requirements that should be fulfilled for the successful execution of horizontal directional drilling.
It should be noted that horizontal directional drilling is not only used for pipelines installation but is commonly used for installing cables below features (obstacles).
HDD can be conveniently used for installing pipelines made of different materials, including steel pipes and HDPE pipes. However, this article covers pipelines made of carbon steel materials.

Figure 1: Horizontal Drilling Machine
Various features (obstacles) are encountered during pipeline installation. These obstacles include roads, railways, water bodies, sensitive areas, buried pipelines, and cables.
They require special crossing technology when an open cut cannot be performed. Therefore, it is imperative to select an appropriate crossing method during the design phase of the project.
Horizontal directional drilling (HDD) is one of the most suitable means of crossing such obstacles.
Horizontal Directional Drilling application has expanded to cover shore crossing for pipeline transiting from offshore to onshore.
Horizontal directional drilling is a trenchless method of installing a pipeline underground below identified features (obstacles) without disruption to any of the identified features. It entails drilling a hole at a specified depth below the features (obstacles) and pulling in the pipeline into the drilled hole.
Crossing length is dependent on the drilling rig capacity. However, there has been significant improvement in technology, which has led to the successful crossing of large water bodies and greater depth.
HDD has been utilised for crossing length of over 1km utilising one rig; however, the advent of drill and intersect method has led to the successful execution of crossing length longer than 2km.
Drill and Intersect method entail drilling the pilot hole from each side of the proposed drill path and intersecting the two pilot holes. This method requires high drilling precision to ensure that the pilot hole intersects at the designed point.
In this section, I have defined/explained the meaning of some of the terms used in HDD
Horizontal directional drilling is a trenchless method of installing pipelines underground below identified features (obstacles) without disruption to any of the identified features
This is the major equipment of a typical horizontal directional drilling setup. It is positioned on a flat surface and may be appropriately anchored to the ground to ensure the machine stays in position during drilling and pipeline pulling operations. The rig is equipped with a power unit that drives a travel mechanism back and forth on a structural framework. Within the rig assembly is a component attached to the drill pipes, this component performs rotational motion during drilling activities.

Figure 2: Structural Framework (Front and Back Travel Mechanism)

Figure 3: Rotating Component of a Drilling Rig
The Cabin is placed almost immediately beside the drill rig. The drilling machine operator controls drilling activities from here. It also houses the HDD steering system and other display devices for monitoring and controlling drilling activities.
Drilling Mud is a mixture of natural and synthetic chemical compounds that may be oil-based or water-based. Appropriate additives are added to the drilling fluid, depending on the drilling requirements. It provides lubrication and cooling effect for the drill bit, stabilises the hole, prevents the hole from collapsing, suspends, and transport the cuttings from the drilled hole.
Drilling fluids are typically made from Bentonite, water, and other additives. The type of additive to the drilling mud is a function of the soil type. When drilling coarse or sandy soil, the drilling fluid should prevent water loss. This can be achieved by using a water/filtrate control additive such as polyanionic cellulose.
The Mixer is an assembly of drilling mud hopper and centrifugal pumps. They are used for bentonite mixing, which is the drilling fluid utilised for HDD drilling activities.

Figure 4: Mud Mixer
Drill pipes are essential components of horizontal directional drilling activity. They are usually furnished with threaded ends, internal threads at the rear, and external threads in front. With the aid of the threaded ends, the pipes are easily joined as the drilled length increases. The drilling machine has a rotating mechanism with external thread that connects to the drill pipe at the rear, rotates and drives the pipes into the ground.

Figure 5: Stacked Drill Pipes
This is the primary boring tool attached to the drill pipes and used to drill the pilot hole. The type of soil to be drilled determines the type of drill bit, e.g., rocky soil requires special drill bits. After the pilot drill, the drill bit is removed and replaced with a reamer.
Reamers are drilling tools used to widen or increase the diameter of the pilot hole to a diameter greater than the pipeline size. They are larger than the drill bit and are equipped with cutting teethes. High-pressure drilling fluid flows through ports provided on the reamer to lubricate the reamer and soften the soil.
The type of reamer selected is dependent on the soil type as well as the hole configuration desired. Below are three types of reamers commonly used:
This type of reamer has an open body with good cutting and mixing capabilities. Fly cutter reamers are mostly used for dense soil applications.
They are mostly used for good soil such as sandy soil, loamy soil, tightly packed clay etc.
This is the most common reaming tool that can be used for various types of soil. Their body is round with tapered nose equipped with cutting teethes and fluid ports.

Figure 6: Barrel Reamer
The pulling head is a fabricated attachment to the pipeline that is hooked to the drill pipes during pipeline pullback. It is welded to the pipeline and cut out after pullback is complete.

Figure 7: Pull Head Welded to a Pipeline Bundle
Before the commencement of actual drilling activities, there are activities performed to guaranty a successful Horizontal Directional Drilling.
The output data of these activities are used as inputs to the design. Activities performed include pipeline route selection, surface and topographical survey, subsurface investigations.
Pipeline route selection is one of the essential activities in HDD design. It should be noted that the section of the pipeline installed using HDD is not routed separately from the entire pipeline. However, the HDD section routing shall be done with attention given to the space required for drilling activities, features (obstacles) to be crossed, etc. Usually, a desktop study is performed to develop various route options. These routes are further narrowed down to one after site investigation.
Surface surveys are carried out to identify and locate all visible obstacles and utilities within a defined width along the proposed route. Also, a topographical survey is performed to determine the elevation along the route. The elevation is a crucial component of the survey works because the minimum required pipeline depth can reduce tremendously in the undulating ground. The minimum required depth is defined concerning the point with minimum elevation.
All collected data are presented in appropriate drawings and documentation, such as crossing plans, crossing lists, profile drawings, etc. As stated in ASME B31.4 Section 434.13.5 (a) crossing plan and profile drawings should show all pipelines, utilities, cables, and structures that cross the drill path, are parallel to and within 100 ft. (30 m) of the drill path, and that are within 100 ft. (30 m) of the drilling operation, including mud pits and bore pits.
Below is a list of some of the data that should be collected during the survey activities
After the completion of surface investigations, the subsurface investigation should be performed. These activities can be categorised into the following:
It is mandatory to perform an underground survey to detect all underground infrastructures including buried pipelines, buried electric cables along the proposed pipeline route. The survey should be performed to capture utilities parallel or crossing the drill path. The depth of the utilities should be captured as well as the coordinates. As stated in ASME B1.4 section 434.13.5 (a) crossing plan and profile drawings should show all pipelines, utilities, cables, and structures that cross the drill path are parallel to and within 100 ft. (30 m) of the drill path, and that are within 100 ft. (30 m) of the drilling operation, including mud pits and bore pits. The survey method employed should be capable of detecting all buried utilities. Some of the survey methods are:
The metal (pipe locator) is used to detect underground metallic structures such as pipes. They are mostly employed to give a preliminary assessment of buried metals within 4m depth, however more sophisticated versions of these devices can be used for depths greater than 4m. It should be noted that this device cannot detect plastic pipes and HDPE pipes that are not installed with tracing wire. Some of these devices detect metallic objects by the interference of magnetic fields generated by the device when it is operated. More sophisticated devices utilise the application of electric current on the identified utility, the current travels through the metallic object, which is further detected by a surface metal detector. This method is more accurate than the previously described method.
The device utilises the principle of reflection of sounds. The sound wave generated by the device is recorded by microphones (geophones) connected along a predetermined and prepared path. The time required for the wave to reflect after striking the buried infrastructure is recorded. This is used to calculate the depth of the object.
The device works on the principle of radio wave reflection. Radio waves are sent into the ground and reflected to the surface; a receiver records the reflected waves. The data are further analysed to calculate the actual depth of the infrastructure.
Excavation may be performed to detect unground infrastructures that are shallow. Depending on the utility, manual excavation or vacuum excavation may be utilised.
Geotechnical investigations are performed to determine minimum soil conditions along the proposed route. These investigations are performed by drilling boreholes at appropriate locations and collecting soil samples for classification and further laboratory analysis. Seismic survey and ground-penetrating radar may as well be utilised to collect geotechnical information.
The actual number of boreholes and spacing is project-dependent as well as the length of the HDD alignment. As stated in GP 59-01-22, ExxonMobil requires that spacing between boreholes should be at least every 500–750 ft. (150–230 m) along the HDD alignment, a minimum of three borings shall be required at each HDD site. If geotechnical results indicate significant variation in soil strata, additional boreholes should be drilled.
The depth of each borehole should be deeper than the depth of the proposed HDD profile. As stipulated in ExxonMobil GP 59-01-22, the borehole should penetrate through an elevation below the depth of the proposed HDD hole profile by at least 30 ft. (9.1 m). This is necessary to provide information for HDD design modifications as well as pilot hole deviations during construction. Drilled borehole should be minimum 20 to 30 ft. below the proposed hole depth (ASCE MOP 108-2014). Boreholes should be at perpendicular offset from the HDD profile centreline. Perpendicular offset distance from centreline required by ExxonMobil in GP 59-01-22 is 15–30 ft. (4.6–9.1 m). Also, soil sampling in a borehole shall extend 20–40 ft. (6.1–12.2 m) below the HDD profile, and under any obstacle, by 40 ft. (12.2 m).
This is performed in conjunction with geotechnical investigations. It is executed by taking samples of underground water, performing a visual examination, and smell to check for preliminary pollution. The water sample should be further analysed to determine the presence of hazardous materials. It should be noted that underground water if contaminated, can be harmful to drilling personnel and also affect the drilling mud.
Layout drawings showing the entire drilling site, facilities utilised for drilling activities at the exit point should be prepared. The layout in minimum should include areas reserved for:
The site should be planned such that there is no or minimal interruption to drilling activities. The available space is planned such that lifting equipment (crane) can position between the drill pipe stacking area and the drill rig. It is essential to minimise crane travel after picking up a drill pipe. The crane should be able to swing and position the drill pipe on the rig.
The layout area required to execute HDD varies depending on the drilling rig size, which is a function of the pipeline size. However, an area of 70m by 70m has been proven to be sufficient.
Drilled path design shall take into consideration all identified obstacles, geotechnical survey reports. The drilled path for water bodies is more complicated compared to other obstacles (features). Drilled path design for river crossings shall take into consideration
This is the angle between the drill bit/drill pipe assembly and the horizontal plane at the location where the drill bit penetrates the ground surface. Entry angle is usually between 8o and 20o. However, this is mostly dependent on the pipeline diameter and the drilling rig capabilities. Large pipeline diameter may require entry angles lesser than 8o because they require a larger bending radius.
This is the angle between the drill bit/drill pipe assembly and the horizontal plane at the location where the drill bit exits the ground surface. The exit angle should be designed such that the pipeline can be easily pulled into the drilled hole as well as facilitate easy support for the pipeline during pullback. The exit angle ranges from 5o to 12o. However, this is dependent on the pipeline diameter. It is better to specify a small exit angle to limit pulling loads.
The depth of penetration is dictated by the location of obstacles and geological features.
The possibility of hole frac-out, the surface settlement should also be evaluated in setting the depth of penetration. The minimum depth should provide a margin for error during preconstruction (surveying) and construction activities. Where complex soil type will be encountered the depth of penetration may be increased to soil location that is more drilling friendly. A minimum clearance of 15 ft. beneath the obstacle should be maintained (Directional Crossing Contractors Association 1995, Hair and Hair 1988).
The radius of curvature is dictated the pipeline diameter, the thickness of the pipeline, and the bending stress imposed on the pipeline as the pipeline is pulled into the curved drilled hole. A radius of curvature of 1200D (1200 x Pipeline Diameter) is generally used for large diameter pipelines while a smaller radius is utilised for smaller diameter pipelines. The radius can be further optimised after necessary analysis and calculations have been performed to justify a reduction in radius.
It should be noted that there might be deviations from the planned/designed drilled path; however, the deviation should be within defined tolerances. Also, the drilling accuracy is well dependent on the type of machine, downhole tool, and the ability of the steering engineer to control directional changes.
During the drilling operation, care shall be taken to ensure there is no significant deviation from the designed drilled path. Below is a summary of some requirements stipulated by ExxonMobil in GP 59-01-22. These may be taken as guidelines during pilot hole drilling.
The only difference in installation stress analysis in HDD is the resulting high tensile stress, bending stress, and external fluid pressure imposed on the pipeline by the drilling fluid.
Appropriate pipe material must be selected to withstand the loads imposed on the pipeline.
In performing the analysis, the HDD profile is broken down into several sections. These profiles are grouped into curved sections or straight sections.
Though there are specialised software and in-house spreadsheets for performing HDD calculations, this section gives preliminary guidelines on how pipeline stresses may be estimated. Calculated stresses should be within allowable limits as defined in appropriate codes and standards.

Figure 8: Typical HDD Profile
The weight of pipeline can be estimated using the formulae below. I have assumed that the pipe is coated with 3LPE (3- Layer Poly Ethylene).




This is the force exerted on the submerged pipeline in the drilled hole by the drilling fluid. It can be estimated using the equation below

This is the resulting weight of the submerged pipeline, which may be negative or positive. This is estimated using the formula below.

This is the force required to pull the pipeline from the exit point to the entry point. This force must overcome the frictional force, drag force and the force required to overcome the elevation changes along the drilled path. The total pull force is therefore equal to the summation of the forces required to pull the pipeline in each section of the profile (curved and straight sections).

Figure 9: Typical Straight Section
Pull force required for straight sections is estimated using the below equation.


Figure 10: Typical Curved Section
Pull force required to pull the pipeline through curved sections of the hole can be estimated using the equation below.
![]()
The frictional force has two components. They are the forces acting between the pipe and the rollers and the force acting between the pipe downhole and the soil. These two frictional forces can be estimated using the formula below.
Frictional force acting between pipeline and rollers

The frictional force acting between pipeline straight section and soil

Frictional force acting between pipeline curved section and soil

Drag force results from the fluidic drag between the drilling fluid (Bentonite) and the downhole pipeline.
Drag force can be estimated using the formula below

The elevation change either support or counters pulling in of pipeline. When the pipeline is pulled downhole the elevation change supports the pulling in when pulled uphole elevation changes obstructs pulling in, for horizontal sections the force is zero.
The force due to change in elevation can be estimated using the formula below:

The tensile stress for each section and the entire pipeline can be estimated using

The bending stress is estimated using the equation below

The hoop stress resulting from external pressure generated by drilling fluid on the empty pipeline can be estimated using.

Unity Check for Tensile and Bending Stress
This should satisfy the equation below
![]()
Unity Check for Tensile, Bending and Hoop Stress
This should satisfy the equation below

Operation stress is the same as in a conventional pipeline. However, the elastic bending stresses should be taken into consideration.
All pipes should be appropriately tested as per written specifications approved by the client. See below requirements for testing/examination to be performed before pipeline pullback.
After pipeline welding, all pipeline welds shall be inspected by qualified personnel. As stated in ASME 31.8 section 841.1.9 (j) (5) (a) non-destructive examination of 100% of all circumferential welds before installation
Holiday test shall be performed on pipelines to detect defective external coatings and appropriate repairs shall be performed on defective coating.
Pipelines to be installed by Horizontal Directional Drilling shall be hydrotested before pullback into the drilled hole. The requirement for hydrotesting is also corroborated by ASME 31.8 section 841.1.9 (j) (5) (a) and ASME B31.4 Section 434.13.5 (e)
Horizontal directional drilling comprises of three stages:
It should be noted that the above activities cannot start until site preparation has been completed. So I will discuss site preparation before the above listed three stages.
This is the first activity performed before the commencement of drilling.
Activities performed include:
This is the first drilling activity performed; below are typical activities performed during the pilot drill. This should commence after all preparatory works have been completed.
It should be noted that the HDD operator steers the drill bit into an appropriate location (designed drilled path) during the drilling operation.
During the drilling operation drilling fluid is continuously pumped into the hole to lubricate the drill bit, loosen the soil and stabilise the hole.
Suspended particles are transported back to the entry pit for further separation from drilling fluid.

Figure 11: Execution of Pilot Drill (Drilling Fluid at Entry Pit)
After the completion of the pilot drill, i.e. the drill bit has emerged at the exit point, the drill bit is disconnected, and the reaming tool is attached to the drill pipe. The reaming tool is run through the pilot hole, gradually increasing its size. Depending on the size of the pipeline to be installed in the drilled hole, there might be more than one cycle of reaming. The reamed hole usually has an oversize of 1.2 to 1.5 times the diameter of the pipeline. Achieving the size of the hole depends on the soil type, soil stability, drilling depth and drilling mud used. The last reaming activity performed is to run a swab reamer through the hole; this is done to verify that the hole is clear and free of obstructions. It should be noted that the swab reamer diameter should be equal or larger than the pipeline diameter but smaller than the largest reamer utilised for hole widening.

Figure 12: Fly Cutter Reamer and a Swab Reamer Connected During Reaming Operation
Before pipeline pullback, all the pipes are welded together at a designated location. The total length of the pipeline should be a little longer than the length of the drilled hole.
A pulling head is welded to the pipeline (the side of the pipeline facing the exit point). The pulling head is the component that will be hooked to the drill pipe; therefore, it must be of adequate strength. Non-Destructive Testing (X-Ray) is performed on all welded joints to verify their integrity.
All welded joints are coated with 3LPE or FBE as may be required depending on the design conditions. A holiday test is performed on the entire pipeline to detect defective coating, and appropriate repairs are performed accordingly.
Before installation, the entire pipeline is hydrotested by pressurising the pipeline as per relevant codes and standards such as ASME B31.4, ASME B31.8, etc.
The pipeline may be positioned on rollers and appropriately aligned to the axis of the exit point. The pipeline should be appropriately positioned to facilitate easy pullback without much resistance at the exit point and curved sections.
The pulling head is connected to the drill pipe, and the pipeline is pulled into the reamed hole. In some cases, a swab reamer is attached to the drill pipe before connecting the pull head. The function of the reamer is to clear all debris in the hole as the pipeline is pulled back.
When the pipeline emerges at the entry point, all drill pipe connections are disassembled and the pulling head cut out.

Figure 13: Pullback Operation (Pipeline Emerges at HDD Entry Point)
In this section, I will share my project experience as it relates to pipeline installation using horizontal directional drilling.
The project entailed building an import berth platform with shallow water of approximate depth 20m. Oil Vessels would berth on the platform to offload their products for onward transportation to various Storage facilities.
Three different pipelines were installed as a bundle from a product reception and metering facility to the Import Berth Platform using Horizontal Directional Drilling. The total drill length is over Eight Hundred Meters (800m).
The pipeline sizes are
16” Multi-Product pipeline
6” Firewater Pipeline
4” Pipeline for Cables
It should be noted the project area (Import Berth Facility) is a bustling lane for ocean vessels. The shipping lane is always dredged to increase its depth; therefore, the pipeline must be installed at greater depth.
The drilling rig was set up onshore at the reception/metering station, and the proposed exit point is offshore just after the import berth platform.

Figure 14: Barge Offshore (Drill Pipes, Crane, and Excavator).

Figure 15: Drill Pipe on Stinger

Figure 16: Pipeline Bundle. Launching into Water

Figure 17: Pipeline Towing Offshore

Figure 18: Pulled Back Pipeline Bundle.
ASME B31.4: Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids
ASME B31.8: Gas Transmission and Distribution Piping Systems
ASCE MOP 108-2014: Pipeline Designed for Horizontal directional Drilling
ExxonMobil GP: Horizontal Directional Drilling
Skid Mounted LNG Liquefaction For Flare Gas: Natural gas is the cleanest of all fossil fuels, but it is quite expensive to transport and store when compared to oil. In terms of energy, 1000 litres (1m3) of gas has an energy content equivalent to 1 litre of oil in ambient conditions. Thus to transport gas economically, it is either liquefied or compressed to increase energy content per unit volume. Consequently, “gas-only” exploration and production is limited to economically recoverable quantities where transport to consumption centres is feasible.
For associated fields, producing oil and gas, there are instances when gas is either not produced (re-injected into reservoir) or flared, owing to commercial considerations. Re-injection of gas into a reservoir is often a sunk cost, and so is gas flaring, which contributes to environmental degradation. Technological developments in gas production coupled with advances in gas transportation methods are gradually lowering the costs and increasing the contribution of this clean hydrocarbon fuel in the world economy. For example, when gas is converted to LNG, its volume is reduced to six-hundredths of the original volume, so gas transmission costs are significantly reduced.
Until recently, flaring was a frequent and unobjectionable practice in the upstream petroleum sector. In 2015, the World Bank took the global initiative[1] of “Zero Routine Flaring by 2030” to end more than a century-old tradition of petroleum industry related to gas flaring at petroleum production sites. A growing number of governments, IOCs / NOCs and development institutions recognize and participate in the on-ground realization of this initiative.
Given previous, commercial interest in implementing solutions for flare gas utilization has significantly improved, with a range of technology applications. One of the most promising options is converting flare gas to LNG through mini or small scale LNG liquefaction plants – modular (skid-mounted) LNG liquefaction plants. These skid-mounted LNG liquefaction plants can also be used to produce stranded gas reservoirs far from the pipeline network, conveniently transporting produced gas to consumption points. LNG, thus produced through modular LNG liquefaction plants, can be shipped conveniently via road tankers for regasification and supplied to the consumer location or a pipeline network.
Various governments around the world are in the process of putting in place legal frameworks and policy initiatives/guidelines to incentivize flare gas utilization through the use of skid-mounted LNG liquefaction plants in the following forms:
In addition to policy support initiatives, technology development and maturation of small-scale LNG businesses are key enablers for flare gas utilization through skid-mounted LNG liquefaction plants. More efficient and cost-effective small-scale liquefaction processes are commercially developed with supporting developments in LNG road tankers for LNG transport and cheap availability of modular regas technologies.
The LNG market that started as a secretive wholesale market (managed through long-term supply contracts) has been opening up to short-term (5-year supply contracts), spot purchases and cargo re-directing options. Small Scale LNG (SS LNG) operations, including skid-mounted LNG liquefaction plants, have been identified during IGU-Conference 2014 and have now been actively pursued. The recent decline in energy supplies due to COVID-19 also adversely affected long-term supply contracts between LNG suppliers and purchasers, highlighting the importance of small-scale LNG business and the potential of modular LNG liquefaction plants.

Source: Triennium Work Report – SS LNG – IGU 2015
According to IGU-2015 report, key observed drivers for SSLNG developments including the use of flare gas to modular LNG liquefaction plants are:

Source: Triennium Work Report – SS LNG – IGU 2015
Standard land-based LNG liquefaction plants take raw gas directly from the wellhead for gas processing and liquefaction to -162°C temperature for convenient storage/transportation in low pressure (50 – 100 PSIG) vacuum-insulated road tankers specially designed to preserve low temperature for weeks. Such plants have the following process schematic:

Source: Petrowiki website
Modern land-based LNG liquefaction plants are usually built as multiple trains with a capacity of an individual train in the range of 3 – 5 mtpa (million tons per annum). Larger LNG trains up to 7.8 mtpa are operational in Qatar, supplying LNG equivalent to a natural gas supply of 1,120 MMSCFD[1] (1.12 BSCFD) per train. These LNG trains are individual processing facilities, with a combined capacity of all trains giving the liquefaction capacity of the plant.
The traditional practice of flare gas usage through re-compression for re-injection use related to enhanced oil recovery adds cost without any tangible benefit. Water injection, steam injection and down-hole steam generation technologies are the right applications for enhanced or tertiary oil recovery. Profitable use of flare gas is its use as an energy source, which can be achieved through careful analysis of location, flare gas composition, and available infrastructure. Development of modular LNG liquefaction plants has opened new avenues for generating additional revenue from existing reservoirs. Studies have indicated that substantive quantities of currently flared gas resources can be converted to valuable LNG with a payback period as low as five years (actual payback period is required to be calculated for each location as it significantly varies with a calorific value of flared gas).
Modular / Skid-mounted LNG liquefaction plants are operated on the premise that flare gas (or stranded gas where applicable) is a resource that should be put to use for profitable company operations. Commercially viable modular LNG liquefaction plants for flare gas utilization must balance CAPEX, OPEX, and the revenue stream (including environmental benefits/incentives). The following considerations are essential:
Relocation and redeployment (with minimal modifications) are key commercial benefits offered by modular LNG liquefaction plants. In this way, the CAPEX requirement gets diluted over geographically scattered assets and maximises shareholder value.
Modular / Skid-mounted LNG liquefaction plants are designed to meet the criteria of commercial viability, compactness and lighter weight. For varying requirements, they are classified as:
A requirement of liquefaction is clean, dry gas that is free of contaminants. Accordingly, processing modules are required along with liquefaction, power generation, and control modules depending on the composition of flare gas. These modules act as mini processing plants for water separation, acid gas removal, water dew-point control, heavy hydrocarbon removal, hydrocarbon dew-point control, and delivering gas that is ready for the refrigeration process.
This is usually the first step in a processing plant whereby bulk gas separation is achieved from oil and water. This module is usually not required for flare gas applications and may be required for stranded gas applications where raw gas is directly coming from wells.
H2S and CO2 are acid gases that can corrode the pipelines and gas vessels used for gas storage and transportation. Additionally, H2S is harmful to health and must be reduced to levels of less than 10 ppmv. Various technologies are commercially available for removing H2S and CO2 from gas.
Amines
Amine sweetening is a proven technology for removing H2S and CO2 from sour gas. Commonly used amines are mono-ethanol-amine (MEA), di-ethanol-amine (DEA), and methyl-di-ethanol-amine (MDEA). Amine systems consist of an absorber column in which the H2S and CO2 are absorbed in the amine. The regeneration section consists of a regeneration column with a re-boiler for evaporation of contaminants mixed with an amine. Amine thus processed in the regeneration section is re-injected into the absorber column.
Molecular Sieves
Molecular sieve systems are multi-use modules for removing water, hydrocarbons, H2S, and CO2 from gas. These modules handle gas with low concentrations of H2S and CO2.
Solid Bed Scavengers
This gas sweetening technology is very efficient and can reduce the H2S content to ultra-low levels. Solid bed scavenger technology efficiently removes H2S from gas by chemically bonding it to non-regenerable adsorbent granules.
These modules remove entrained and dissolved water from the gas, an essential liquefaction requirement. Technological solutions include Glycol-based Dehydration and Molecular Sieve-based Dehydration.
Glycol-Based Dehydration
Various commercially available glycols, including di-ethylene glycol (DEG), tri-ethylene glycol (TEG), and tetra-ethylene glycol (TREG), are used to control water dew point. Wet gas is brought into contact with glycol in the contact column.
After absorbing the water from the gas stream, the glycol is regenerated for reuse in a closed-loop system.
Molecular Sieve-Based Dehydration
Molecular sieve-based technology can remove water from gas as well as CO2 and produce gas streams with low water and hydrocarbon dew points. Water dew points obtained by molecular technology are far lower than those achieved with absorption (glycol) technology—as low as -80°C or even -100°C.
Strict hydrocarbon dew-point control is required for LNG liquefaction applications. Depending on feed gas composition, Low-Temperature Separation, Silica Gel-based Dew Point Control or a combination of both technologies can be used in the same module.
Low-Temperature Separation
Low-Temperature Separation (LTS) is widely used to remove both water and hydrocarbons from gas. This technology is also helpful in increasing the methane number of gas for compatibility as fuel gas for LNG plant power generation. LTS technology depends on the allowable pressure drop required to achieve the Joule Thompson effect and is often supported by a chiller.
Silica Gel-based Dew Point Control
Silica is a solid desiccant that removes water and hydrocarbons from gas. Solid desiccant technology can achieve very low dew points—as low as -80°C or even -100°C. In the regeneration mode, gas is obtained directly from the process or an external source. Repeated cycles are performed using consecutive heating and cooling of the saturated column.
Fractionation
Fractionation technology is a conventional method for removing light hydrocarbons, such as Liquefied Petroleum Gas (LPG) and (condensate) C5+, from the gas stream. This separation process is based on distillation using controlled heating and cooling, which exploits the difference in boiling points of the light hydrocarbons.
Traditionally, land-based LNG liquefaction plants usually deploy a varying combination of Propane-Precooled Mix Refrigerant (C3MR) Cycle with Nitrogen recycle expansion process sub-cooling to produce LNG. Liquefaction has three basic steps:
To optimize for space and weight for modular LNG liquefaction plant applications, different variations in refrigeration cycles are commercially used, as listed below:
Note: Under normal atmospheric pressure, Nitrogen exists as a liquid between the temperatures of -210°C and -196°C, and hence, it is significant in LNG production. Additionally, Nitrogen is abundantly available in air and can be separated through proven Nitrogen Recycle Expander technology.
LNG is stored at the production site in ISO vacuum-insulated tanks with provisions for handling boil-off vapours. A dispatch requirement is the transfer of LNG to road tankers through tank gauging applications. GIIGNL[3] provides necessary guidelines for LNG transfer and measurement requirements.
Operating modular LNG liquefaction plants has unique challenges that must be carefully overcome for successful operations. These were identified in the IGU Triennial Report published in 2015 and reproduced below:
About EPCM

Process Control Automation in oil & gas (Downstream): Process Control Automation is the latest and innovative value-adding service in oil & Gas downstream. In the oil and gas industry, it is crucial to regulate process variables to achieve the task of process automation. In the oil and gas Sector, especially downstream, different chemical processes take place to refine crude oil and to produce Liquid Petroleum Gas (LPG), Diesel, Kerosene oil, Petrol, Heavy Gas Oil, Gasoline, Naptha, Lubricating oil, Residual and different carbon components from crude oil.
There are specific chemical processes for converting crude oil into these products, which require proper technology-based control systems. These control systems consist of sensors, transmitters, controllers, control valves, and final control elements to regulate process variables within the desired range and successfully carry out the operation. In oil & gas downstream, the critical process variables which are very important to control include pressure, level, flow, temperature, and density. There is a complete closed-loop of a control system, as shown in the figure, which is used for chemical plant processing and control applications.

Process Control Automation in Oil & Gas (Downstream): Pressure Measurement in Oil & Gas Downstream
Process Control Automation in Oil & Gas (Downstream): Flow Measurement in Oil & Gas Downstream

Level Measurement in Oil & Gas Downstream
The level is a critical process variable of oil & gas downstream. The position of an interface between two different or the same mediums, such as liquid and gas or between two liquid mediums, is known as Level Measurement. For controlling and accounting at the level is a crucial variable used in every oil & gas Industry. We measure level in meters or percentage; sometimes we also measure level in feet. The level is the name of two interfaces. We can also calculate level by calculating density in a few applications.
Three main principles that Level Measuring Devices follows:
Direct Method
Indirect Method
Indirect level measurement refers to the measurement of level through some property or parameter of liquid, like pressure, density, conductivity. These methods include
Temperature Measurement in Oil & Gas Downstream
Temperature is also an important process variable in oil and gas downstream. Controlling the temperature of the chemical process is crucial to achieving the goal of automation—in oil and gas downstream, all chemical processes are heat-dependent. Different specialized instruments are used to measure temperature in industry. These include thermocouples and a thermistor. We measure temperature in Kelvin, °C, or °F.
Thermocouples are the most widely used temperature sensors in the chemical industry and oil & gas downstream; they are junctions or combinations of two different conductors or metals that are welded together. A thermocouple produces a small voltage in milli-volts when the temperature of the process changes. It transfers heat change into electric volts. Thermocouples are cheap and flexible, but their limitation is their measurement accuracy. Its range is around -250 °C to 2500 °C. Thermocouple operates on the Seebeck effect; it states that “If two metals are joined together and heated, then it generates an EMF”. When joined or welded together at one end, two different metallic conductors and an EMF are produced between the open ends of a thermocouple, depending upon the junction’s temperature. The thermocouple is divided into different categories based on different materials and temperature range; its types include Type E, Type T, Type K, and Type J.

A thermistor is of two types;
PTC is temperature dependent; the resistance increases with the increase in temperature. While in NTC, it is also temperature dependent, but opposite in proportionality, the resistance decreases as the temperature increases. Thermistor generally behaves with a high negative resistance temperature coefficient. Its sharp sensitivity makes it very useful for precise temperature measurement, control & compensation. Its resistance ranges from 0.5 Ohm to 0.75 milli-Ohms. It is also used for temperature compensation in sophisticated electronic equipment and measurement of thermal conductivity.
Area of Application
Summary of Process Control Automation

Process Control Automation in Oil & Gas (Downstream): Benefits Due to Upgradation in Technology

These companies offer services for Process Control Automation:
About EPCM
Electricity has become indispensable to improving human life and achieving economic development. Households use it for cooking and refrigeration; essential facilities such as hospitals require it for cooling, lighting, and emergency equipment. Agriculture is more efficient with electricity, and industrial plants rely heavily on electricity. [1]
Africa is on a back foot when it comes to electricity access and supply. In 2013, Africa had a total installed capacity of 147 GW, equivalent to what China installed in one or two years to sustain their economy and way of life just a few years ago. Since then the gap has just widened. [1] This starkly contrasts the difference in electricity access between Africa and other countries worldwide. Africa is in desperate need of electricity, not only for their economy but also to improve the quality of life of people on the continent. For example, Uganda recently launched a project called “The Uganda Rural Electricity Access Project” (UREAP), which specifically focused on driving development in providing rural areas with electricity access to improve livelihoods. Many other African countries such as Ghana are currently busy with large projects to develop natural gas import facilities to address the growing energy demand. Mckinsey and Company predicts that the need for electricity in Sub-Saharan Africa will dramatically increase leading up to 2040 from 452 TWh to a potential total requirement of 1570 TWh. This indicates the expected and continued increase in the supply and demand gap that needs to be filled. [2]
Figure 1 illustrates the current energy mix in African countries on the coast of Africa. The figure shows that most countries rely on renewables or oil as their main energy source. Important to note that due to location, these countries can more easily resort to importation of additional energy resources. South Africa is seen to have the highest reliance on coal, mainly due to its domestic coal resources. To fill the gap in increasing the energy generated, these countries must either invest in more renewable energy sources, oil or natural gas.

FIGURE 1: PRIMARY ENERGY DEMAND MIX BY COUNTRY (2013). [2]
The use of natural gas to generate power has been rapidly increasing over the last few years. This is mainly due to shale fracking in the USA, which has caused a significant drop in gas prices, making gas more competitive as an energy source globally. This made natural gas a feasible option for African countries to bridge the energy gap.
Currently, 22 African countries have proven gas reserves, which is good news for the continent’s energy demands [3]. Nigeria, Libya, Algeria and Egypt hold 91% of Africa’s gas reserves, and Africa holds approximately 10% of the global gas reserves [4]. This has driven many African countries to start developing their gas reserves for exportation, especially for those who does not have a developed local natural gas market. However, natural gas could be the best way for some African countries to fill their local energy gap. So, the need to develop domestic gas infrastructure to create a local market has been initiated.
Under the current economic circumstances (low gas cost) and in most cases (depending on the capex and transport costs), natural gas is less expensive to power generation than coal. In situations where a country has access to renewable resources for hydro, solar or wind power generation, natural gas has also been found to be cheaper to develop. Hydroelectricity relies on a country’s access to sufficient water to generate power even to be considered, but is mainly economically feasible on a large scale (> 100 MW). On a small scale (0.1 MW – 10 MW), the costs are higher per kW to generate, and it is often not a feasible solution for power generation. [5] Hydro electricity is also affected by climate change and droughts, introducing risk for investors and less reliable power [6]. Solar and wind power both have long payback periods. Often, the IRR is at the point when the plant needs significant maintenance, reducing the project’s profitability. This makes it less attractive to investors. [7]
One of the other benefits driving development in natural gas power generation is that power plants can be constructed faster, this means quicker turnaround times. This enables countries to address the energy demand faster, which is a huge benefit in countries desperate for electricity. It must be said that the shorter lead times may come at a higher price due to more labour required to get the plant up and running faster, which could offset some of the benefit. Natural gas is also flexible, and plants of different scales can easily be constructed and remain profitable, which is beneficial in addressing the specific energy demand in an area. This flexibility makes it an attractive solution in Africa, especially as power generation can be sized according to a specific area’s need.
The low gas cost, high flexibility, and short lead times have made natural gas an attractive alternative for Africa to address the gap. This has also made it a more attractive option for investors, which has further driven the development of natural gas in Africa.
Three methods are typically used to generate power with natural gas:
Natural gas power stations can be divided into open cycle (simple-cycle) and combined cycle (this video describes it well). An open cycle plant uses a gas turbine, where natural gas and air are mixed and burned to form a high-pressure gas that turns the turbine. A combined cycle power station uses this same principle to generate power but then seeks to utilize the hot gas as it exits the gas turbine. This hot gas, or waste heat, is then used to turn water into steam, which can drive a steam turbine. This added Heat Recovery Steam Generator (HRSG) can add up to 50% more electricity than achieved with only the open cycle gas turbine. The open cycle generating units are often employed as back-ups to generate additional electricity based on increased demand. In contrast, the combined units tend to be utilized for the day-to-day electricity usage. [9]
As mentioned, another alternative is to convert an existing coal power station to use natural gas. However, the feasibility and profitability of a conversion depend highly on each specific case. Different economics would drive the investment opportunity. The efficiency of the equipment is also affected and needs to be considered.
One benefit of this method is that the conversion technology for converting a coal fuel plant to gas is mature. There are also existing training and maintenance procedures. This significantly reduces the risk of conducting such a conversion and the required design time, reducing development costs.
However, the overall economics of such a conversion should be considered. The potential lower cost of gas or easier access to gas and growing energy demand must be weighed against the conversion cost and cost of operations. Logistics such as access to gas and transmission and distribution infrastructure are also major considerations.
The downside of converting to gas from coal is a reduction in boiler efficiency, along with the initial CAPEX investment. Some changes to the O&M are also expected. However, the upside is reduced auxiliary power requirements; annual non-fuel O&M costs are expected to be lower than coal [10]. No two plants are alike, and conversion must be evaluated on a case-by-case basis to determine if it makes economic sense.
Considering all of this, natural gas is often a more efficient method of power generation, which gives credence to African countries adopting natural gas as the solution to address the energy gap.
Despite Africa’s desperate need for energy and rapid development of natural gas, there are still numerous challenges to address. Some of which other natural gas consumer/producing countries have also faced or are still addressing.- while others are unique to Africa. A few of these challenges currently faced in Africa are:
The sustainability of import needs. It may be that gas importation is a temporary solution while a country’s production recovers or is increased. After a period, domestic production may be sufficient, and import contracts may be cancelled. This poses a high risk for countries that invest heavily in import infrastructure that may be abandoned or export facilities if they cannot secure off-takers. As a result, investors are also a bit reluctant in some cases if there is a possibility of cancellation in the future. [2]
Sizing of the future gas market is problematic. A FEED or feasibility study is usually required before continuing with any development project. Such a study includes a market analysis to understand the demand and supply of the product. This poses a challenge in Africa as development could spark additional investment and growth, resulting in a larger market than initially anticipated. It also poses a risk to attract future investment if a high confidence in the project’s bankability cannot be provided because of these uncertainties.
Another challenge is paying for natural gas in forex, which makes import countries more susceptible to economic changes and volatile prices.
Major challenges include the lack of infrastructure and the need to develop ports, pipelines, and LNG facilities [3]. There are precious few existing gas transmission and distribution facilities, which are critical to optimising natural gas’s value. Without adequate infrastructure, gas cannot be fully utilised [11]. Countries wishing to export/import or use their own gas domestically face this challenge.
There is also a challenge with obtaining funding for midstream infrastructure. Investors are often eager to invest in import facilities or power generation but reluctant to invest in pipelines or distribution networks. Without this, development is severely hampered. [2]
In Africa, there are often significant distances between domestic gas sources and the major demand centres. This makes it more expensive and requires additional resources for the necessary infrastructure to connect the source and demand centres [11]. Similar challenges are faced in linking sources to export facilities and getting the imported gas to demand centres.
Most African countries also lack the necessary policies and regulations, which delays development and discourages investment opportunities. A lack of well-developed policies and regulations makes financial investment decisions more complicated and risky.
Another serious issue that African countries in particular face is corruption, which discourages investments and leads to funding difficulties during the project, especially when it comes to the final investment decision. [12]
However, it is encouraging to see that significant development is still occurring despite these challenges, which is discussed in the next chapter. Africa is working towards overcoming these challenges to ensure the sustainability and success of future developments.
Despite the abovementioned challenges, Africa has seen an annual increase of 4% in gas production and 6% in consumption since 2000 [13]. A few of the current developments are:
Virginia Gas Project: Tetra4 (Pty) Ltd has reserved rights to develop the Virginia Gas Fields in South Africa. Natural gas containing high amounts of Helium will be extracted and sold as separate commodities. This is the first natural gas project in South Africa. [14]
Rovuma Liquid Natural Gas project: This is a significant development in Mozambique. It constitutes a 15.2 million tonnes per annum LNG export facility and is operated by the Mozambique Rovuma Venture (MRV). MRV is a joint venture by ExxonMobil, Eni, CNPC and smaller shares by Galp, KOGAS and Empresa Nacional de Hidrocarbonetos.
Eni is responsible for the upstream facilities and transportation to the onshore facilities. ExxonMobil is responsible for the midstream facilities. The project is based on three gas reservoirs of the Mamba complex in Area 4 of the Rovuma Basin, which is located approximately 40 km off the Cabo Delgado coast of Northern Mozambique. The successful completion of this project will allow Mozambique to become one of Africa’s biggest LNG exporters. [15]
Mozambique LNG project: This project is being developed in Mozambique, which will have a two-train liquefaction plant with a capacity of 12.9 million tonnes per year. The project is led by a consortium that includes Total, Mitsui & Co, ONGC, ENH, Bharat PetroResources, PTEP, and Oil India Ltd, with Total leading the project. [16]
Tema LNG: A 1.7 million tonnes per annum LNG import facility is being developed in Ghana. Tema LNG is the owner of the project and a combination of purpose-built FRU in parallel with FSU will be utilised for the facility. Russian oil giant Rosneft will supply the LNG. [17]
Tanzania Liquified Natural Gas Project: Tanzania is in the process of developing an LNG liquefaction plant. It is set to have two LNG trains, each with a capacity of 5 million tonnes per annum. The construction of a gas pipeline to supply Uganda was also in consideration. Unfortunately, development has been slow, and governmental complications have plagued the project. Construction is planned to start in 2022, and the operation is set to start in 2028. [16]
Gas Revolution Industrial Park (GRIP): A downstream refinery and petrochemical complex in Nigeria is planned for Ogidigben in the Delta region. The Nigerian National Petroleum Corporation wholly owns the complex. The complex will also include new chemical plants using natural gas from Nigeria as feedstock. The complex will be fed from the nearby gas reserves in Odidi, Okan and Forcados fields as well as supplemented by a gas pipeline network called ELPS. [16]
Akonikien project: Equatorial Guinea launched their first gas-to-power development. It forms part of the LNG2Africa initiative. The initiatives’ primary objective is to develop small-scale LNG projects to supply gas to countries and regions with limited infrastructure. Once complete, the plant will have a storage capacity of 14,000 cubic metres and 12 bullet tanks. These tanks are the largest cryogenic bullet tanks in the world, each with a capacity of 1,228 cubic meters. [18]
Other projects which are all specifically related to power generation in Africa are:
Significant natural gas development is already occurring in Africa, and there is potential for even more. Natural gas is one solution to address the energy gap in Africa. What remains to be seen is whether this will be enough.
Bibliography
[1] International Renewable Energy Agency, “Prospects for the African Power Sector,” International Renewable Energy Agency, 2012.
[2] A.-S. Corbeau, “LNG for Africa,” in King Abdullah Petroleum Studies and Research Center, 2016.
[3] W. Lindecke, “LNG’s potential as an African power source,” Biz Community, 2017. [Online]. Available: https://www.bizcommunity.com/Article/196/693/162244.html.
[4] Return to Africa Connected, “The role of gas in powering Africa’s future,” DLA Piper, 2019. [Online]. Available: https://www.dlapiper.com/en/us/insights/publications/2019/11/africa-connected-issue-3/the-role-of-gas-in-powering-africas-future/.
[5] IFC, “Hydroelectric Power,” IFC.
[6] Power Africa, “Understanding Natural Gas and LNG Options,” Ghana Ministry of Petroleum, 2017.
[7] C. Haydu, “Renewable Problem: Why Natural Gas, LNG Remain Key To Energy Transition,” Daily Oil Bulletin, 2019.
[8] Chiyoda Corporation, “Chiyoda Corporation,” 2017. [Online]. Available: https://www.chiyodacorp.com/en/service/receive/power-generation/.[Accessed July 2020].
[9] GE Power, “Tour a combined cycle power plant,” GE Power, 2020. [Online]. Available: https://www.ge.com/power/resources/knowledge-base/combined-cycle-power-plant-how-it-works.
[10] R. Bedilion, Technology Considerations for Coal-to-Natural Gas Conversions, 2017 EIA Energy Conference, 2017.
[11] Energy Future Initiative, “Investing in Natural Gas for Africans: Doing Good and Doing Well,” Africa50, 2018. [Online]. Available: https://www.africa50.com/fileadmin/uploads/africa50/Photos/Knowledge_Center/Investing_in_Natural_Gas_for_Africans_-_Doing_Good_and_Doing_Well.pdf.
[12] KWM, “Challenges and opportunities facing LNG projects in Africa,” King&Wood Mallesons, 2012. [Online]. Available: https://www.kwm.com/en/de/knowledge/insights/challenges-and-opportunities-facing-lng-projects-in-africa-20160101.
[13] EY, “Natural gas in Africa: The Frontiers of the Golden Age,” EY, 2013. [Online]. Available: https://www.ey.com/Publication/vwLUAssets/EY_-_Natural_gas_in_Africa:_The_frontiers_of_the_Golden_Age/$FILE/EY-Natural_gas_in_Africa_The_frontiers_of_the_Golden_Age.pdf.
[14] A. Bajic, “Renergen completes Virginia gas plant design,” 2020. [Online]. Available: https://www.offshore-energy.biz/renergen-completes-virginia-gas-plant-design/.
[15] NS Energy, “Rovuma LNG Project, Mozambique,” 2019. [Online]. Available: https://www.nsenergybusiness.com/projects/rovuma-lng-project-mozambique/.
[16] N. Withers, “7 Major Upcoming Oil and Gas Projects in Africa,” 2020. [Online]. Available: https://www.fircroft.com/blogs/7-major-uapcoming-oil-and-gas-projects-in-africa-07818161439.
[17] S. Zawadzki, “Ghana resurrects LNG import terminal with Chinese deals,” 2018. [Online]. Available: https://www.reuters.com/article/lng-ghana/ghana-resurrects-lng-import-terminal-with-chinese-deals-idUSL2N1VX09W#:~:text=LNG%20is%20expected%20to%20be,previous%20LNG%20suppliers%20lined%20up..
[18] B. Bungane, “Equatorial Guinea to build West Africa’s first LNG storage and regas plant,” ESI Africa, 2019. [Online]. Available: https://www.esi-africa.com/industry-sectors/generation/equatorial-guinea-to-build-west-africas-first-lng-storage-and-regas-plant/.
HYDRAULIC FRACTURING – GEOMECHANICS: Fracking, as a technique, was born in the 1830s, with the use of acids to fracture the reservoir rock. In 1947, studies to change acids for water began; in 1960, the use of dynamite in its base state, nitroglycerin, was being tested on the coast of the United States. However, it was not until 1998 that hydraulic fracturing began to be used commercially, thanks to George P. Mitchell, the father of the fracking technology.
A study conducted by the IEA states that thanks to technologies such as fracking, by 2019, the United States will produce more oil than the largest producer in the world, Saudi Arabia. In 2020, that will be a fact. Despite the production benefits offered by hydraulic fracturing, whether for fracturing source or reservoir rocks, the technique’s difficulty generates high implementation costs. Because of this problem, new alternatives are sought to face the heterogeneity of the formations.
Geomechanics is a branch of geology that is shown as one of the scientific alternatives to decipher formations’ behaviour when the fracking technique is practised. Below is a detailed explanation of how geomechanics can be an essential ally when discussing hydraulic stimulation.
Hydraulic stimulation consists of injecting a highly-viscous fracturing fluid at a pressure above the pressure of the fractured formation, intending to change the skin factor and looking for negative values. That is to say, to generate flow channels or fractures around the drainage area, placing elements in the generated channels in a packaging form that help the fracture take longer to close and generate sufficient permeability for fluid passage.
During the process, the fundamental concepts of the operation must be taken into account, which are:
Geomechanics is closely related to the main currents of geology, classical mechanics, and mechanics of materials. Despite being widely used in the mining and civil engineering sectors, geomechanics is positioned as an excellent ally for operations in the oil and gas industry.
It is based on the calculation of the stress field in equilibrium in the subsoil. It expresses the maximum stress, the minimum stress, the overburden stress, and the shear and sliding stresses.
Soils behave under the action of loads as elastic materials, in some cases, greater deformations than the regular ones are produced, having to turn to calculations that take plasticity into account. For the oil and gas industry, it is crucial to understand the nature of the shear strength to create a simulation or prediction of the different problems that may arise under certain types of operations.
The geomechanical model explicitly describes data relevant to the construction and production of oil wells; these include pore pressure, the state of the stresses, mechanical properties, and the strength of the rock for the total stratigraphic section penetrated by the wellbore.
Today, different methodologies are used to construct a geomechanical model. One of the most used is the one by geomechanical engineer Marcelo Frydman. In his methodology, he details processes such as:

Marcelo Fridman’s methodology, SLB – Source: OnePetro
Additionally, a geomechanical model can be calculated in two ways: a dynamic model, where all the calculated resources depend on indirect data, such as records or area iterations, to create data simulations, and static models, which are characterized by using core samples and direct data from the formation.
Geomechanics is shown as an ally of high importance when facing the heterogeneous challenge that hydraulic fracturing represents. Each reservoir is a new world for fracture specialists. Every wellbore is a new adventure since the conditions of pressure, temperature, rock strength, and elastic rock do not necessarily maintain homogeneous behaviour. Due to these factors, using data from constructing a geomechanical model is a high-impact ally.
During geomechanical modelling, an inspection of the behaviour of the reservoir is performed, analyzing each wellbore. During this process, possible operational problems related to borehole stability are identified, as in turn, it is identified if the wellbore was fractured.
If the wellbore was fractured, data such as fracture pressure, type of fluid used, type of control fluid, and proppants used to maintain the fracture are detailed, as well as the closing pressure and well flow rate that the wellbore registered. The data also analyze the functionality of the fracture over time and how much the wellbore’s skin factor was achieved after the process. These data provide a background of the reservoir events.
The stratigraphic framework helps to understand how old the rock is, what type of rock it is, and where the work will take place. For example, rocks from Eocene ages are characterized as hard rocks and have a high degree of compaction. It is understood that the deeper, the more compact and resistant type of rock is expected in theory.
One of the processes practised within stratigraphic mechanics is taking petrographic samples. This type of task is performed using direct core samples, which are analyzed using a petrographic microscope. This direct analysis allows going beyond a wellbore’s electrical or special records. They provide knowledge of factors such as:
The types moderate, poor, and very poor are optimal for good fracking because they reflect less opposition to the fracture. In turn, their deformities help the adaptation of flow channels.
For fracking processes, knowing the type of grain helps in deciding the proppants that should be used to avoid slipping processes, size, and shape. The use of proppants of a much larger size than those of the formation would create spaces in the pore throats created with the fracture. It would facilitate the detachment of the grains of the formation by the effect of fluid friction, occupying the spaces created by the proppants, thus creating slipping over time.
The stresses operating in the sub-soil are divided into three main stresses: the overburden stress (Sv), the maximum horizontal stress (SH), and the minimum horizontal stress (Sh):
In turn, horizontal stresses have preferred routes in the subsoil; this translates into directions of preferential flow, porosity, and natural fractures in the study’s formation. They are opposite and obtained by the practice of 6-arm or so oriented calliper records, image logs, or sonic-oriented records, which allow noticing fractures in the formations.
This type of information allows the fracture specialist to determine the optimal direction of fracture. In a normal regime, the recommendation is to direct the fracture towards the maximum stress; only the opposition of the fracture’s minimum effect will have to be kept open.
On the other hand, the correct selection of the hand direction of the stress regime avoids tortuosity in the pore throats; this type of problem prevents the passage of proppant towards the fracture and, therefore, its functionality.
The overburden parameter is the weight generated by the layers of formations on the target formation being studied. It is obtained using density registers (RHOB), and Gardner’s equation is subsequently applied. An overburden pressure reading is obtained at each point read by the register, considering the existence of shale.

Gardner’s Overburden equation
For hydraulic fracturing, the knowledge of an abnormal overburden pressure is crucial in selecting the strength of the proppant. Fracturing studies conducted in Venezuela and Argentina demonstrate an abnormal behaviour of the stresses, with the overburden stress (SV) equal to or greater than the maximum stress (SH).
Therefore, it is established as an abnormal stress regime. If the fracture is planted in a horizontal area, the overburden stress directly affects the closure of the formation; therefore, it affects the proppant’s strength pressure. In some cases, crushing effects have been evidenced on proppants that degrade their size and become part of the production.
To obtain the results on the properties of the rock, dynamic tests are carried out, which are sonic logs (DOC, DT), depending on the travel times that the sound waves take and using software such as Drillworks or Skua Geolog. Profiles of mechanical properties of the rock are obtained, both elastic and resistance. These programs are based on the formulas of Horner, Eaton, and Bowers.
On the other hand, there are tests of sample destruction. These are based on the sampling of the nuclei. After tests are performed, such as:
Knowing the rock’s mechanical properties, it is possible to calculate the magnitude of the area’s main horizontal stresses. The minimum stress translates into the pressure required to open the rock with the fracture. To achieve a correct propagation of the fracking technique, it is necessary to know the magnitude of the maximum stress since this value is the rock’s maximum strength. After this point, the rock is no longer elastic. The fundamental objective of the fracture is achieved: opening the rock.
One of the most used failure analyses in the oil industry is the Mohr-Coulomb equation; this type of test takes factors such as Biot coefficient, Young’s and Poisson’s modules, UCS values, and TRX values. To determine the angle of internal friction and the values of the rock’s cohesion, the fracture specialist can estimate the values of collapse pressure and fracture gradient along the rock, either in a vertical or horizontal plane.
Knowing the rock’s cohesion value and degree of compaction allows the fracture specialist to establish an adequate type of fracturing and control fluid. Hard rock does not necessarily contain characteristics of high cohesion, so using a highly viscous fluid can cause problems if this characteristic is not known.
Fracking technology is not a failure-safe process to full functionality. Despite this, the use of the geomechanics discipline establishes a clear view of the properties and features that the fracturing fluid will face, as well as the proppant, which will be added to provide a lasting effect on this process. A profound understanding of the rock is and always will be necessary.
Extracted from: https://www.iea.org/news/united-states-to-lead-global-oil-supply-growth-while-no-peak-in-oil-demand-in-sight
Extracted from: https://oilmanmagazine.com/article/geomechanics-the-nemesis-of-the-npt/
About EPCM
Fuel Gas Booster Skid Systems: A fuel gas booster is desired when a gas engine or gas turbine requires a pressure above the available pipeline pressure. The fuel gas booster (gas booster) compressor provides gaseous fuel (natural gas, biogas, or similar) to a gas turbine or piston-type engine at high pressure. The engine operates best with a steady fuel gas supply at a constant pressure. The gas booster provides a steady supply of fuel gas at a constant pressure by using two tanks and a back pressure control valve (also called a back pressure regulator). A fuel gas boosting compressor is the “blood pump” for gas turbine power plants because it supplies steady gas to the gas turbine power plant. Figure 1 shows a typical fuel gas booster unit for industrial applications.

Fig 1: A typical fuel gas booster unit (Image Source: Corken Inc.).
Gas booster compressors are crucial for reliable gas turbine power plant operations. The demand for fuel gas booster has been increasing because gas turbines require higher fuel gas pressures to achieve increased performance efficiency and because pipeline pressures fluctuate due to increased overall and peak demand requirements. The gas turbine requires a certain pressure during fuel gas combustion and pressurized air. When the gas pressure of the main pipelines is inadequate, gas booster compressors are installed. The required gas pressure for conventional industrial gas turbines is around 230 to 330 pounds per square inch gauge (psi), or 16 to 23 barG on average. However, the latest industrial gas turbines require high-pressure fuel gas, such as 500 to 600 pis (35 to 42 bar). Besides, aero-derivative type gas turbines now require gas pressure as high as 700 to 1,000 psi (49 to 70 bar).
At the same time, natural gas demand has been increasing so that the new supply of natural gas is not sufficient for the growth of demand in many parts of the world. As a result, the gas pressure in the pipeline cannot be maintained as high as required. This is particularly true during peak demand, such as summertime or daytime. This means that the gas pressure in the pipeline will gradually decrease and fluctuate. A fuel gas booster unit correctly handles such fluctuations of gas pressure from the pipeline while simultaneously meeting the gas turbine’s required gas flow rate. Two changeable conditions are most relevant to fuel gas boosters: the inlet gas pressure fluctuations and the turbine’s load changes. Besides, reduced oil carryover and low pulsation/vibration are also important, because they can lead to mechanical problems. The gas turbine combustors are very sensitive to pulsation. Thus, pulsation is a big concern to gas turbines with dry low NOX combustors. Natural gas can include impurities or dirt, and its precise composition can even be subject to change.
The gas booster system is used in many sectors, especially industrial applications. However, the gas booster system can also be used for the following applications-
Figure 2 shows a schematic of a gas booster skid. The gas passes through the air filter and goes to the inlet of the gas booster. The supply pressure is measured by using a pressure gauge. Several pneumatic valves are being controlled by compressed air. Fuel gas boosters are usually piston or plunger type compressors. A single-acting, single-stage booster is the simplest configuration. It comprises a cylinder and a piston, designed to withstand the operating pressures. The piston is driven back and forth inside the cylinder. The cylinder head is fitted with inlet and outlet ports. Each inlet and outlet pipes or hose are connected with a non-return valve, constraining flow in one direction from the supply to the discharge. When the booster is inactive, and the piston is stationary, gas will flow from the inlet pipe, through the inlet valve into the space between the cylinder head and the piston. If the pressure in the outlet pipe is lower, it will flow out to whatever the outlet pipe is connected to. This flow will stop when the pressure is equalized, taking valve opening pressures into account. This system is called the gas purging system of a compressor.

Fig 2: Flow schematic of a gas booster unit.
When the booster is started, the piston withdraws along with the cylinder, increasing the volume between the cylinder head and the piston head. As a result, vacuum pressure will be developed, and gas will flow in from the inlet port. On the return stroke, the piston moves toward the cylinder head, decreasing the volume of the space and compressing the gas. When the pressure is sufficient to overcome the pressure in the outlet line and the opening pressure of the outlet valve, the gas will flow out of the cylinder. This cycle starts over again and continues during the unit’s operation. Depending on the required pressure for the operation of the industrial equipment, there may be multiple compression stages for the fuel gas booster compressors. In a multi-stage fuel gas booster compressor model with a compression ratio > 5, the fuel gas outlet is cooled by an intercooler for cooling.
Gas boosters work on the principle of a pressure intensifier. They are used to compress gases and compressed air to higher pressures and are operated with a driving pressure of up to 10 bar of compressed air. The driving pressure is required to compress the respective fluid to a higher operating pressure. The transmission ratio is calculated from the piston area of the large air piston to that of the smaller high-pressure piston. Depending on the booster type, the primary pressure should be selected. The main components of a single-stage gas booster compressor assembly are described as follows-
The pilot valves enable the air piston to move the stop positions. The air piston actuates the pilot valves in the stop positions and transmits air pulses to the spool valve. This enables the pilot valves to air out and vent the actuator chamber of the spool valve, which moves the spool valve from one stop position to the other.
The purpose of the spool valve is to use compressed air alternately to the top and bottom of the air piston. The spool valve is controlled by the pilot valves, which ensure that the drive air reaches the opposite side of the air piston.
To take up the drive air (compressed air) and actuate the high-pressure booster piston via a piston rod the drive unit is used. Therefore, the fuel gas is compressed to a higher pressure. The pressurized fuel gas is supplied to the gas turbine unit.
The fuel gas booster locks the compression chamber and separates this spatially from the ambient pressure. The gas booster contains the inlet and outlet valves for the intake and exhaust of the gas in the system. The gas to be compressed enters and exits the booster compression chamber through these inlet and outlet valves.
A single-stage booster high-pressure unit consists of the pressure cylinder, a gas booster with inlet and outlet valves, and the high-pressure piston with seal and guide elements. The unit is used to compress the respective gas. There are lubrication systems for the smooth run of the piston inside the cylinder.
The exhaust silencer reduces noise when expanding the drive fluid, which is discharged from the booster. After completing the task, the drive fluid exits the booster via the exhaust silencer. Depending on the booster model, the exhaust air silencer may be made of plastic or aluminium.
The cooling cylinder serves to insulate and cool the high-pressure booster unit. The cooling cylinder encloses the high-pressure cylinder. The expanding (very cold) drive air is routed into the space between the two cylinders to cool the high-pressure cylinder during operation. For a packaged compressor system, the following-
Depending on the compression ratio required, single or two-stage compressors can be used in the system. The single-stage compressors are typically used for compression ratios of 5:1 or less. The two-stage compressors are required for higher compression (typically at 5:1 compression ratio). Water-cooled or Air-cooled intercoolers and aftercoolers can be used depending on the availability of cooling water at the site and size of the compressor. A pulsation system is used in the fuel gas skid for the regulators and the gas meters because gas booster compressors work best with minimal gas pulsations. Tank storage is recommended as the tanks protect these pulsation-sensitive components by dampening pulsations generated by the fuel gas compressor. Selecting the correct type of fuel gas compressor is one of the most critical factors in achieving a successful plant operation. There are different configurations of the gas booster compressors-
A single-acting, single-stage booster is the simplest configuration of the gas booster unit. It comprises a cylinder designed to withstand operating pressures, with a piston driven back and forth inside the cylinder. The cylinder head is fitted with inlet and outlet points, to which the supply and discharge pipes are connected, with a non-return valve on each, constraining flow in one direction from supply to discharge. Single acting-single stage gas boosters are the smallest and lightest with pressure capabilities up to 39,000 psi (2690 bar). A single acting-single stage gas booster provides an economical means of boosting pressure for testing small components and similar applications where volume is small and efficiency is not important. Figure 3 shows a typical single-acting single-stage gas booster compressor.

Fig 3: Single-acting single-stage gas booster compressor (Image Source: Haskel)
Double-acting single-stage gas booster pumps twice the volume of a single-acting-single-stage booster per cycle. It requires less air drive since the inlet gas pressure assists the air drive in each direction, providing a substantial portion of the required driving force. A double-acting single-stage gas booster compressor is very efficient for boosting the large gas volumes at low to medium compression ratios. The applications of the double-acting single-stage gas boosters are in high-pressure gas testing or process testing, charging of accumulators, boosting the gas pressures from nitrogen or oxygen bottles and generators, leak detection system, nitrogen injection for moulding machines, pressure autoclaving, etc. Figure 4 shows a typical double-acting single-stage gas booster compressor.

Fig 4: Double-acting single-stage gas booster compressor.
5.3 Double-Acting Two-Stage Triple Air-Head
In a double-acting two-stage triple air-head booster compressor, two cylinders operate alternately, each pressurizing gas while the other is refilling. In the second stage, there is a smaller bore filled by the gas, which is pressurised by the first stage and pressurizes the gas further. The stages operate in series, and the gas passes through both in turn. Figure 5 shows a typical double-acting two-stage triple air-head gas booster compressor.

Fig 5: Double-acting two-stage triple air-head gas booster compressor. Image source: High-Pressure Technologies LLC.
The main difference between single- and two-stage gas boosters is the number of times that gas gets compressed between the inlet valve and the tool nozzle. In a single-stage gas booster, the gas is compressed once; in a two-stage gas booster, the gas is compressed twice for double the pressure. Single-stage gas boosters are also known as piston type gas boosters. The processes that take place within a single-stage gas booster:
Gas is passed into a cylinder.
The trapped gas is compressed in a single stroke with a piston roughly up to a certain pressure.
The compressed gas is delivered onward to the service line.
The process within a two-stage gas booster is similar to a single-stage, but with one variation: the compressed gas isn’t sent to the service line directly. Instead, it is sent to the intercooler and cooled. This intercooler decreases the compressor work, and at the second stage of compression, more high pressure is attained at a low work input. Therefore, the high-pressurized gas is delivered to the service line for different purposes, such as power plants and industrial applications.
The relative quietness of the single-acting single-stage gas booster compressor makes them ideal for smaller working environments. Because it has only one cylinder, there is only one piston stroke for each revolution of pressurized gas. On the other hand, the two-stage gas booster is ideal for high pressure boosting and larger industrial applications. The choice between a one-stage or multi-stage gas booster compressor should be based on the size and nature of your operations. In summary, one-stage units are for small-scale projects, while two-stage models are more geared toward industrial-scale arsenals.
Two-stage gas booster compressors are more expensive than the single-stage counterparts because more parts are involved. However, the parts in a two-stage unit typically require maintenance at less frequent intervals. In the long run, operating a two-stage compressor could be less expensive. A two-stage gas booster compressor can also make your operations less expensive if your applications are industrial. In a power plant, a single-stage compressor wouldn’t likely suffice. You would probably need a second single-stage gas booster compressor to attain high pressure, thus raising the operating costs. For industry use, the upfront investment in a multi-stage gas booster compressor could save money over time.
Gas booster selection involves the calculation of the gas pressure lift required for operation and the gas volume flow rate. The gas flow rate can be calculated by dividing the burner firing rate by the calorific value of fuel gas. When a single gas booster supplies several burners, selection involves calculating the total gas flow of all the appliances and the maximum gas supply pressure required by any single appliance. The ability of the booster to increase pressure is a function of the driving pressure, multiplied by the nominal booster ratio. Within each booster model, there are standard construction materials.
It is also crucial to note that all pipework should be sized as normal, regardless of whether a booster is used, aiming for a 1 bar pressure drop between the gas supply meter and the appliance. Installing a gas booster is not a way to enable the use of smaller gas pipework. Using a gas booster will not overcome any issues with the undersized piping design. When installing the gas booster, it may be necessary to provide information about the ramp profile to the gas supplier. It will be helpful to ensure the pipework upstream of the meter has the correct value. The ramp profile is not governed by the booster but by the burner/boiler or other appliance consuming the gas for smooth industrial operation.
The life cycle of a gas booster is also important during the selection of the gas booster unit. The system’s life cycle will vary depending on several parameters such as the use of the booster unit, what it is being used for, how hard it is used, and the schedule maintenance practices. There are standard life cycle expectations with the caution that everything depends on how well you care for the machines in the system. The cost-effectiveness ultimately depends on the use, life cycle, maintenance costs, and depreciation rate. The overall cost-effectiveness of the system is an integral part of identifying the budget ahead of time and considering selecting the appropriate system.
Gas booster skid installation and operation may have different standards based on the location, size, and type of the gas booster unit. All the parties related to the gas booster skid unit, such as the owner of the gas booster skid unit, the operation and maintenance (O&M) company, the engineering procurement and construction (EPC) company, and also the manufacturer of the unit, need to follow the local and international safety and standard guidelines. Here are some industry standards for the gas booster skid-
For an industrial-grade gas booster skid design system, the designer needs to design an incoming and outgoing piping system, compressed air supply system for pneumatic valve control system, gas booster control system, gas treatment system, unit basement civil construction system, gas compression system, and so on. No matter the required size and specification, the entire system needs a high precision engineering comprehensive design process for completely tailored, highly reliable operation conditions. The methodology involved close collaboration of mechanical, control, civil, and instrumentation engineering works. The first step of the design process involves a client consultation with a specification to understand the system requirements and formulate an ideal design.
As a second step, after consulting the design engineers about the clients’ requirements, the experienced team can determine the required characteristics of the gas booster skid. The design engineers determine the necessary operational characteristics, such as specific fluid properties, flow rate, temperature, pressure, etc. As the third stage, the safety engineers determine the safety features that need to be included in the design, as in some cases the system will be handling materials that pose hazards, such as natural gas or certain types of chemicals. Therefore, the final design has the required standard sizes of pumps, coolers, compressors, motors, heat exchangers, control systems, control valves, enclosures for specific locations, weather conditions, etc. The design might be submitted with the list of required major equipment for client approval, and addresses any input or feedback they may have. Once the customer signs off, the design process moves onto creating the piping and instrumentation diagram (P&ID). When creating a PI&D, the layout indicates the entire process flow for the system, from skid inlet to outlet. At this point, specific requirements and features of the skid should have been established and identified, needed valves, drains, piping sizes, and connection points. In addition to working on skid system design, the implementation of the design of the control system, and the locations of control valves and sensors for pressure, temperature, and flow are decided.
After designing an original diagram that noticeably depicts all necessary information for the skid systems and other equipment, the design team meets the customer to ensure the design meets all their unique requirements. Once the design team gets the customer’s approval at this stage, the team uses the P&ID to make a complete, highly detailed 3D model of the system. The model allows the customer to identify specific details, including the precise inlet/outlet locations, dimensions, weight, and structural steel base anchor points. Often the design team runs stress and vibration simulations to analyze the system further and ensure optimal performance and reliability.
The presentation of the gas booster skid drawings and 3D model files allows the client to see how the system will integrate with existing equipment, and illuminate essential details, such as component materials, connection types, clearances around major components for maintenance purposes, and the electrical or control panel locations. With the 3D model in hand, the customer can provide additional input, and any required changes can be made before the actual construction process begins.
After the customer approves the design of the gas booster skid, the construction steps are initiated. By keeping customers involved at every stage of the design process, cost and time can be saved significantly, improving the system performance and reliability. The active participation of the client and the construction team eliminates errors and inefficiencies at an early stage. The construction phase starts at the manufacturer’s construction yard. High capacity overhead cranes, painting facilities, welding equipment, and fabrication machinery may be required. The bases and structural steel can be fabricated in-house or outsourced. The manufacturer completed the instrumental and control system testing at the manufacturer’s entity testing laboratories. The manufacturers’ in-house fabrication of pressure vessels, platforms/supports, and structural bases allows custom components to be made in less time while saving costs. Besides those testing and construction works, the construction site needs to be prepared. The civil works for the basement of the gas booster skid need to be done by following the local and international standards. It may be required permission from local authorities. Additional safety paperwork and environmental issues need to be completed in due time.
During the mechanical installation phase, the piping, testing, and pre-commissioning of mechanical equipment must be done. The fuel gas booster skid installation needs to be accomplished in concurrence with the manufacturer’s instructions, standard industrial practices, and relevant codes and standards. The electrical/instrumentation installation work is usually identified in a separate document. The electrical/ instrumentation work shall be coordinated with the mechanical work to provide a complete, safe, and reliable system. Finally, the manufacturer usually performs a test run per the manual and guidelines to ensure the system’s performance, safety, and reliability.
About EPCM
Design of shell and tube exchanger: A shell and tube heat exchanger is one of the most popular exchangers due to its flexibility. In this type, there are two fluids with different temperatures; one flows through the tubes and the other flows through the shell. Heat is transferred from one fluid to another through the tube walls, either from the tube side to the shell side or vice versa. This system handles fluids at different pressures; higher pressure fluid is typically directed through tubes, and lower pressure fluid is circulated through the shell side.

Figure 1: Shell and Tube Heat Exchanger
The shell is constructed from pipe up to 24 inches or rolled and welded plate metal. Low carbon steel is standard for economic reasons, but other materials suitable for extreme temperatures or corrosion resistance are often specified. Using commonly available shell pipes with 24-inch diameter reduces cost and ease of manufacturing, partly because they are generally more perfectly round than rolled and welded shells. Roundness and consistent shell inner diameter are necessary to minimize the space between the baffle outside edge and the shell, as excessive space allows fluid bypass and reduces performance.
In applications where the fluid velocity for the nozzle diameter is high, an impingement plate is specified to distribute the fluid evenly to the tubes and prevent fluid-induced erosion, cavitation, and vibration. An impingement plate can be installed inside the shell, eliminating the need to install a full tube bundle, which would provide a less available surface. The impingement plate can be installed in a domed area (either by reducing coupling or a fabricated dome) above the shell. This style allows a full tube count and maximizes utilization of shell space.

Figure 2: Impingement Plate in Tube Layout
The channel type is selected based on the application. Most channels can be removed to access the tubes. The most commonly used channel type is the bonnet. It is used for services that do not require frequent channel removal for inspection or cleaning. The removable cover channel can be flanged or welded to the tube sheet. The removable cover permits access to the channel and tubes for inspection or cleaning without removing the tube side piping.
The rear channel is often selected to match the front channel. For example, a heat exchanger with a bonnet at the front head (B channel) will often have a bonnet at the rear head (M channel) and be designated as BEM. Pass partitions are required in channels of heat exchangers with multiple tube passes. The pass partition plates direct the tube side fluid through multiple passes.
Tubes are generally made seamless or welded. Seamless tubing is produced in an extrusion process; welded tubing is produced by rolling a strip into a cylinder and welding the seam. Tubes are made from low carbon steel, stainless steel, titanium, Inconel, Copper, etc. Standard tube diameters of 5/8 inch, 3/4 inch, and 1 inch are preferably used to design compact heat exchangers. Tube thickness should be maintained to withstand:
1) Pressure on the inside and outside of the tube
2) The temperature on both the sides
3) Thermal stress due to the differential expansion of the shell and the tube bundle
4) Corrosive nature of both the shell-side and the tube-side fluid.
The tube thickness is expressed in terms of BWG and true outside diameter (OD). Tube lengths of 6, 8, 12, 16, 20, and 24 feet are commonly used. Longer tubes reduce shell diameter at the expense of higher shell pressure drops. Tubes of larger diameter are sometimes used to facilitate mechanical cleaning or achieve lower pressure drop. A maximum number of tubes in the shell increases turbulence, which increases the heat transfer rate. Finned tubes are also used when fluid with low heat transfer coefficient flows in the shell side.
Tube sheets are made from a round flat piece of metal with holes drilled for the tube ends in precise locations and patterns relative to one another. Generally, the tube sheet material is the same as the tube material. Tubes are appropriately attached to the tube sheet, so the fluid on the shell side is prevented from mixing with the fluid on the tube side. The tubes are inserted through the holes in the tube sheets and held firmly in place by welding, mechanical or hydraulic expansion. A rolled joint is the common term for a tube-to-tube sheet joint resulting from a mechanical expansion of the tube against the tube sheet. Holes are generally drilled in the tube sheet in either of two patterns, triangular or square.

Figure 3: Tube sheet
The distance between the centres of the tube hole is called the tube pitch; it is typically taken as 1.25 times the tube’s outside diameter. The minimum value is restricted to 1.25 because the tube-sheet ligament (a ligament is the portion of material between two neighbouring tube holes) may become too weak to roll the tubes into the tube sheet properly. Other tube pitches reduce the shell side pressure drop and control the shell side fluid’s velocity as it flows across the tube bundle. Triangular pitch provides higher heat transfer and compactness. Square pitch facilitates mechanical cleaning of the outside of the tubes.

Figure 4: Types of Tube Pitch
Baffles serve the following functions:
1) Support the tubes during assembly and operation
2) Prevent vibration from flow-induced eddies and maintain the tube spacing
3) Direct the flow of fluid in the desired pattern through the shell side.
A segment, called the baffle cut, is cut away to permit the fluid to flow parallel to the tube axis as it flows from one baffle space to another. The spacing between baffles is called the baffle pitch. The baffle pitch and the baffle cut determine the cross-flow velocity, heat transfer rate and pressure drop.
The orientation of the baffle cut is essential for the heat exchanger installed horizontally. The baffle cut should be horizontal when the shell side heat transfer is sensible heating or cooling with no phase change. This causes the fluid to follow an up-and-down path and prevents stratification with warmer fluid at the top of the shell and cooler fluid at the bottom. For shell-side condensation, the baffle cut for segmental baffles is vertical to allow the condensate to flow towards the outlet without significant liquid holdup by the baffle. The baffle cut may be vertical or horizontal for shell-side boiling, depending on the service.
The cut areas represent 20 to 25% of the shell diameter for most liquid applications.

Figure 5: The orientation of Horizontal and Vertical Baffles
Tie rods hold the baffle in place with spacers, tubing or pipe placed to maintain the selected baffle spacing. The tie rods are screwed into the stationary tube sheet and extend the bundle’s length to the last baffle. Tie rods and spacers may also be used as sealing devices to block bypass paths due to pass partition lanes or the clearance between the shell and the tube bundle. The minimum number of tie rods and spacers depends on the shell’s diameter and the size of the tie rod and spacers.
Code rules and standards aim to achieve minimum requirements for safe construction and provide public protection by defining those materials, design, fabrication, and inspection requirements; ignoring this may increase operating hazards. Following are some mechanical design standards and pressure design codes used in heat exchanger design:
1) TEMA standards (Tubular Exchanger Manufacturer Association., 1998)
2) HEI standards (Heat Exchanger Institute, 1980)
3) API (American Petroleum Institute)
4) ASME (American Society of Mechanical Engineers)
To understand the shell and tube heat exchanger’s design and operation, it is important to know the vocabulary and terminology used to describe them. This vocabulary is defined in terms of letters and diagrams. The first letter describes the front header type, the second letter the shell type, and the third letter the rear header type. For example, BEM, CFU, and AES.
TEMA has classified the front head channel and bonnet types according to the letters (A, B, C, N, D). The shell is classified according to the nozzle locations for the inlet and outlet. There is a type of shell configuration (E, F, G, H, J, K, X). Similarly, the rear head is classified (L, M, N, P, S, T, U, W).

Fig 6: TEMA Designation
High velocities will yield high heat transfer coefficients and a high pressure drop, causing erosion. The velocity must be high enough to prevent any suspended solids settling, but not so high as to cause corrosion. High velocities will reduce fouling. Plastic inserts are sometimes used to reduce erosion at the tube inlet. Typical design velocities are given below:
LIQUIDS
Tube-side process fluid: 1 to 2 m/s
Shell-side: 0.3 to 1/m/s
VAPORS
The velocity used for vapours will depend on the operating pressure and fluid density; the lower values in the range given below will apply to molecular-weight materials.
Vacuum: 50 to 70 m/s
Atmospheric pressure: 10 to 30 m/s
High pressure: 5 to 10 m/s
The closer the temperature approach used (the difference between the outlet temperature of one stream and the inlet temperature of the other stream), the larger the heat transfer area required for a given duty. The optimum value will depend on the application and can only be determined by economically analysing alternative designs. As a general guide, the greater temperature diff should be at least 20 °C and the least temperature diff 5 to 7 °C for cooling using cooling water and 3 to 5 °C using refrigerated brine. The maximum temperature rise in recirculated cooling water is limited to around 30°C. Care should be taken to ensure that cooling media temperatures are kept well above the freezing point of the process materials. When heat exchange is between process fluids for heat recovery, the optimum approach temperatures will typically not be lower than 20°C.
The value suggested below can be used as a general guide and usually gives designs near the optimum.
LIQUIDS
Viscosity<1 mN s/m2, ΔP=35 kN/m2
Viscosity=1 to 10mN s/m2, ΔP= 50-70 kN/m2
GAS AND VAPORS
High vacuum: 0.4-0.8 kN/m2
Medium vacuum: 0.1 x absolute pressure
1 to 2 bar: 0.5 x system gauge pressure
Above 10 bar: 0.1 x system gauge pressure
When a high-pressure drop is utilized, care must be taken to ensure that the resulting high fluid velocity does not cause erosion or flow-induced tube vibration.

Where,
T1, T2 = Inlet and Outlet temperatures of hot fluid
t1, t2 = Inlet and Outlet temperatures of cold fluid
∆t = FT*∆TLMTD
![]()
A’= π* do *L
Where,
do = Tube outside diameter
L = Length of tube
![]()
Where,
Pt = Pitch
![]()
![]()
Where,
Ms = Fluid flow on the shell side
Ds = Shell inside diameter
![]()
![]()
![]()
![]()
Where,
k = thermal conductivity
= dynamic viscosity of the water fluid
= shell fluid dynamic viscosity at the average temperature
De= equivalent diameter of shell side
C = specific heat of the shell side fluid
![]()
![]()
Where,
Mt= Fluid flow on the tube side
![]()
![]()
Where,
k = thermal conductivity
= dynamic viscosity of the water fluid
= tube fluid dynamic viscosity at the average temperature
di = inside diameter of tube side
C = specific heat of the tube side fluid
![]()
![]()
Where,
Ro = outside dirt coefficient (fouling factor)
Ri = inside dirt coefficient (fouling factor)
![]()
![]()
Where,
ΔPs pressure drop for shell side
N+1= number of crosses = Tube length / Baffle spacing
Ǿs= viscosity correction factor for shell-side fluid
f = Friction factor
![]()
Where,
ΔPt = pressure drop for tube side
n = number of passes
L = length of the tube
Ǿt= viscosity correction factor for tube side fluid
f = Friction factor
![]()
Where,
s = Specific gravity of the fluid
g = acceleration due to gravity
n = number of passes
v2/2g = velocity head
![]()
[1] D. Q. Kern, “Process Heat Transfer”, McGraw-Hill Book Company, Int. ed. 1965.
[2] Thulukkanam Kuppan, “Heat Exchanger Design Handbook”, First Edition, Marcel-Dekker, (2000).
[3] Saunders, E. A. D. (1988) Heat Exchangers “Selection, Design, and Construction”, Longman Scientific and Technical. DOI: 10.1016/0378-3820(89)90046-5
[4] NPTEL – Chemical Engineering – Chemical Engineering Design – II
[5] R.K. Sinnott, Coulson & Richardson’s Chemical Engineering Design, Volume 6, 3rd Edition, Butterworth-Heinemann
About EPCM
Pyrolysis is the process of thermal conversion of organic matter using a catalyst in the absence of oxygen, typically to produce liquid fuel. The products of biomass pyrolysis include bio-oil, biochar and Non-Condensable Gases (NCG) including various compositions of hydrogen, carbon monoxide and carbon dioxide depending on the biomass selected (1). The condensed gases collected during pyrolysis produce the final desired product, bio-oil. Pyrolysis has been drawing increasing attention due to its high efficiency and reduced environmental impact, in contrast to the crude oil sector, which creates an opportunity to recover energy from waste materials. Various raw materials may be pyrolysed, for example, used tyres are pyrolysed in some regions of the world. In this article, the pyrolysis of agricultural residues will be analysed.
The bio-oil collected during pyrolysis produces approximately 40 MJ kg-1. This is similar to the amount of energy contained in other commercially produced fuels such as crude oil, diesel, and petrol, which contain 45.5 MJ kg-1, 45.8 MJ kg-1, and 46.6 MJ kg-1, respectively (2).
During pyrolysis woody biomass is converted according to the reactions illustrated below:

Biochar produced during pyrolysis, as a by-product, enhances crop yield and acts as a soil enhancer providing numerous nutrients to the soil and thus improving crop yield. Excess biochar generated can be sold to the agricultural sector to recover costs. As a result, it is recommended that the generated biochar be sold as a soil amendment (3).
For the maximum production of char and gases, the thermal degradation process and conditions should be optimised for maximum bio-oil production for fast pyrolysis (4). For optimum reaction conditions, the following is recommended (5):
Fast pyrolysis typically results in a product distribution of 75 wt. % bio-oil, 12 wt. % char, and 13 wt. % gases (5). The bio-oil generated has the following properties: low pH, low heating value, poor volatility, high viscosity, and high oxygen content. The quality of the bio-oil can be enhanced by using a catalyst during the pyrolysis (6).
Char is a solid by-product consisting of carbon, oxygen, hydrogen, and Nitrogen. The char yield range is dependent on the pyrolysis temperature, and it can vary from 10 – 20 wt.%. Coke is formed on the surface of the catalyst during fast pyrolysis. This catalytic coke can deactivate the catalyst and should be removed. This is done by burning it away (1).
Numerous investigations have concluded that catalytic fast pyrolysis optimises bio-oil yield and quality by enhancing the NCG emitted. The amount of char produced is also decreased, which thereby minimises the instability or ageing of the bio-oil (7). Due to the endothermic nature of this pyrolysis reaction, adding a catalyst will decrease the overall process costs and energy consumption, as it lowers the temperature of the reaction. Various catalyst choices exist, and the selection depends on process feedstock and the selected pyrolysis process system. An LDH catalyst is recommended. The catalyst eliminates the need for bio-oil upgrading and simplifies the production procedure (8).
Eucalyptus was selected as the type of biomass modelled due to its rapid growth rate and abundant supply in South Africa. Also, it contains a smaller percentage of ash and Nitrogen compared to other biomass types. (9).
The rate of heating directly influences the reaction pathway and substances produced. Rapid heating results in smaller amounts of char. Moreover, the heating rate affects the oil yield, which decreases at lower heating rates (10).
The main methods of heat transfer during flash pyrolysis are gas-solid heat transfer using convection and solid-solid heat transfer using conduction. A fluidised bed is beneficial because 90% of the heat transfer is from conduction and the remainder from convection. Also, due to fluidisation, attrition occurs whereby there is friction between the biomass and the hot catalyst. This erodes the surface of the biomass, thereby exposing fresh biomass for a reaction and eroding the carbon layer around the catalyst which can hinder its activity. This can slightly reduce the particle size of the biomass. However, the con is that micro carbon is formed, which can prove difficult to remove from the vapour phase and may make up a bio-oil component. However, the amount of micro carbon formed is minimal in fluidised beds compared to other pyrolysis reactors (4). The hot sand flows from the combustor to the pyrolyser as illustrated below:

Vapour residence times of less than 2 s are recommended, as longer residence times result in secondary cracking of the primary products, which reduces yield and negatively influences the quality of the bio-oil (4).
A wood particle size of 4 mm was used as recommended by Liao & Thomas (11).

A mass and energy balance is vital for sizing the reactors and needs to be conducted over the entire pyrolysis process. The moisture content of the biomass should also be known for this mass and energy balance. The chemical formula for the biomass can be obtained in a study conducted by Adebayo et al. (3). For a full layout of the entire pyrolysis production process, refer to the diagram below. This article will illustrate the calculations necessary to size the combustor and pyrolyser, outlined in red.
The main goal for conducting an energy balance in the pyrolyser is to achieve a temperature of 500 °C to enable fast pyrolysis to produce a high-quality bio-oil. The energy required for the pyrolyser is obtained by heating the catalyst, modelled as sand using the software AspenPlus for the simulation, in the combustor, which should operate at 900 °C. The catalyst is then fluidised and overflows via the overflow pipe into the pyrolyser for heat exchange with the woody biomass. An energy balance should be first conducted over the pyrolyser to determine the catalyst flow rate required to provide sufficient energy. The diagram below illustrates the main streams for this energy balance.

The catalyst (Qcatalyst) needs to provide enough energy to heat the biomass (Qbiomass) and water contained in the wood (Qwater,1) exiting the dryer at a specified temperature and heat it to 500 °C, evaporate the water at 100 °C (Qevap), heat the water from boiling point to 500 °C (Qwater,2) as well as supply energy for pyrolysis (Qpyrolysis) which is an endothermic reaction. Lastly, adequate energy is needed to compensate for environmental energy losses (QLoss,pyr). Equation 1 illustrates how the above energy requirements are determined.
(1)
All Q values listed in equation 1 are found using equation 2,
(2)
Qevap is found using equation 3 and the latent heat of vaporisation
and the mass of water vaporised, m.
(3)
The combustor supplies the energy needed to heat the catalyst (Qcatalyst), which burns both NCG and biochar to provide this energy. In the NCG, the hydrogen (QH2 in NCG) and carbon monoxide (QCO in NCG) combust to provide energy and, in the biochar, the carbon (QC in char) and hydrogen (QH in char) also combust to provide energy.
The amount of biochar needs to: provide sufficient energy to heat the sand from 500°C to 900 °C (QNCG), heat up the NCG exiting the heat exchanger from 500 °C to 900 °C, heat the air from 25 °C to 900 °C (Qair) and heat up the carbon dioxide (Qco2) and water vapor (QH2O) formed from the combustion of bio-char at the specified temperature it enters at to 900°C and provides energy to recompensate for the heat loss to the environment, QLoss, comb. The bio-char flow rate varies until the energy balance is satisfied.
The amount of NCG selected is a fixed variable based on the volumetric flow rate of gas entering the bed, which provides a suitable operating velocity and a sized diameter of the bed, as explained in the Fluidised Beds section of this article.
(4)
Qcatalyst, QNCG, Qair, Qco2 and QH2O are determined according to equation 2. QLoss comb is found in the Insulation section. QC in char, QHinchar, QH2 in NCG and QCO in NCG are found by multiplying the molar flowrate by the heat of reactions. Equation 4 shows the energy balance.
The process consists of fluidised beds, namely the Combustor and the Pyrolyser as depicted in the figure below:

Figure 1: Schematic of fluidised beds adapted from Swart (12).
The operating velocity, height, diameter, wall thickness, and distributor plate are designed according to the procedure below (13) using the values for the density and viscosity to be calculated for the relevant components at the specified temperature and pressure of 101,325 kPa.
The assumption that the char particles immediately react to form flue gases in the combustor and that the wood chips instantly pyrolyse due to fast pyrolysis to form NCG is made. Therefore, the following calculations only consider the solid catalyst particles present throughout fluidisation in the circulation fluidised beds. According to the Geldhart chart, the sand was classified as a group B powder. Thus, the relevant equations for group B powders are used below.

Figure 2: Geldhart powder categorisation (14)
The Archimedes number, the ratio of viscous forces within the bed compared to outside the bed, is calculated according to equation 5, this is used in equation 6, (Wen and Yu (15) to solve for the Reynolds number at minimum fluidisation (Remf). Using Remf it is possible to solve for the velocity at minimum fluidisation (umf) in equation 7 which is the start of fluidisation.
(5)
(6)
(7)
Increasing the velocity beyond this results in the creation of bubbles. If the velocity is increased more significantly, the velocity will surpass the terminal velocity (ut) calculated using equation 8, which is the velocity to transfer particles out of the bed. Further increasing the velocity results in entrainment. The operating velocity, uop, should be greater than umf but smaller than ut.
(8)
The porosity at minimum fluidisation
is the bed voidage at the instant fluidisation occurs. It can be solved according to equation 9. The height at minimum fluidisation, Hmf, assumes that the extra height of the particles at fluidisation compared to without fluidisation is the height of the particles in equation 10.
(9)
(10)
The slugging velocity, ums in equation 11, is the velocity at which the bubbles created to have the same diameter as that of the bed. The operating velocity should be below the slugging velocity.
(11)
The operating Reynolds number is determined according to
(12)
Where the operating velocity is selected to meet the criteria outlined in equation 13, an appropriate range of operating velocities for fluidised beds is 1 ms-1 to 3 ms-1 (16).
(13)
The pressure drop across the bed
is found by equation 14 where g is 9.81 ms-1 and hp is the height of the particles in the bed.
(14)
The pressure drop across the distributor,
, is the larger of 10 % of
or 3500 kPa. The gas velocity through an orifice in the distributor is found by equation 15.
(15)
Corr is 0.6. It should be ensured that the orifice velocity is greater than 50 m s-1 to prevent particle backflow through the orifice (12).
The number of orifices per bed area, Norr, is found by equation 16. Multiplying the bed area by the number of orifices enables the total number of orifices to be found.
(16)
The height of the beds is calculated using equations 17 and 18 to determine the total disengagement height and the height to place the overflow pipe. The figure below illustrates the zones calculated when determining the bed height. The region depicted “Bed” is the packed bed height.

Figure 3: Height regions in a fluidised bed (14)
(17)
(18)
In equation 17, dbv is the diameter of a bubble at the surface. The total heights should be multiplied by a safety factor of 1.2, and the overall height for both beds is selected as the height of the taller bed.
The thickness of the walls is important to ensure that they can withstand the pressure created. Equations 19 and 20 allow the calculation of the appropriate wall thickness due to hoop stress and longitudinal stress, respectively. P is the design pressure of 101.325 kPa for both beds, S is the maximum allowable yield stress of stainless steel, and E is the joint efficiency, which is approximated to be 0.6. The final minimum wall thickness is the sum of these two values.
(19)
(20)
Insulation has demonstrated to be advantageous in the following circumstances:
Insulation materials should be selected based on their service temperature range, whether they would react with the raw materials, and their combustibility. Furthermore, the thickness choice should be based on the thickness of the material typically available from suppliers (17,18).
Insulation protection is crucial for the longevity of the materials. As a result, firebrick clay is recommended as the outermost layer of insulation, both to protect the inner insulation and to provide an additional layer of insulation (18).

The Qloss used in the energy balance is determined according to equation 25. In equation 21, RinsulatorX refers to the outermost layer of insulation. The figure below depicts an example of materials used in combination with equation 21
(21)
Heat transfer by convection and conduction are modelled according to equations 22 to 24.
(22)
(23)
(24)
Equation 23 represents the radii of the combustor before and after the layer of insulation, where L is the height of the reactor. A represents the area across which heat transfer occurs. Equations 26 and 27 illustrate how the area is calculated where L is the height of the reactor, already determined.
(25)
(26)
(27)

Temperatures larger than 60°C cause discomfort in a plant environment for the plant workers. For this reason, the surface wall temperature of the fire clay brick on the sides should be restricted to a maximum of 55 °C.
Some safety elements have already been considered in the previous sections of this report, such as a maximum allowable wall temperature of 55 °C.
A key safety consideration is the absence of oxygen in the pyrolyser, as this could lead to an explosion. To combat this issue, a paramagnetic sensor detects the presence of oxygen and issues a warning (3).
Additionally, the entire system should be cleaned with inert gas, such as Nitrogen, to eliminate the presence of oxygen both at the commencement of the process and whenever the oxygen sensor issues a warning.
A pressure sensor should be placed in both the combustor and the pyrolyser to detect significant pressure changes as the normal operating pressure of both beds is atmospheric pressure. An anomalous pressure reading could indicate a blockage in either the screw conveyors or the distributor and would require further investigation.
A level sensor should be placed above the total disengagement height to detect the presence of large amounts of particles and to issue a warning that the fluidisation velocity is too high, and that reactor inspection is necessary. Before any inspection, the reactors should be allowed to cool to room temperature. Employee education is vital to ensure a safe process. Personnel working around the fluidised beds should be informed of safety strategies, aware of all hazards, and safeguard themselves by wearing PPE.